Invitation to Bid


Procurement of Medical Equipment – 2021

The PROVINCIAL GOVERNMENT OF AURORA, through its Bids and Awards Committee (BAC), invites all eligible suppliers/manufacturers/distributors/contractors to bid for the hereunder project:

Name Of ProjectLocationApproved Budget for the Contract
PROCUREMENT OF MEDICAL EQUIPMENTPHO, BRGY. RESERVA, BALER, AURORA1,609,800.00
TOTAL  

Prospective bidders should have experience in undertaking a similar project within the last two (2) years with an amount of at least 50% of the proposed project for bidding. The Eligibility Check/Screening as well as the Preliminary Examination of Bids shall use non-discretionary “pass/fail” criteria.  Post-qualification of the lowest calculated bid shall be conducted.

All particulars relative to Eligibility Statement and Screening, Bid Security, Performance Security, Pre-bidding Conference, Evaluation of Bids, Post Qualification and Awards of Contract shall be governed by the pertinent provisions of RA 9184 and its Implementing Rules and Regulations (IRR).

The complete schedule of activities is listed, as follows:

ActivitiesSchedule
1.  Issuance of Bid DocumentsJanuary 6, 2021 – January 26, 2021  until 9:00 AM
2.  Pre-bid ConferenceJanuary 14, 2021 @  2:00 PM
3.  Submission of Eligibility and BidsJanuary 26, 2021 until 9:00 AM
4.  Opening of BidsJanuary 26, 2021  @ 10:00 AM
  • Pre-Bid Conference/ Opening of Bids’ date is automatically re- scheduled to the next working day whenever such date is declared a holiday.

The BAC will issue to prospective bidders Eligibility Forms upon payment to the Provincial Treasurer’s Office of the PGA of a non-refundable amount for the following approved budget for the contract.

The Provincial Government of Aurora assumes no responsibility whatsoever to compensate or indemnify bidders for any expenses incurred in the preparation of the bid. Only those who have purchased the Bidding Documents shall be allowed to participate in the pre-bid conference and raise or submit written queries or clarifications. The PGA also reserves the right to reject any or all bids, to declare the bidding a failure or waive any defect or informality and to accept bids as may be considered most advantageous to the PGA without thereby incurring any of the following: (a) liability whatsoever to offset expenses or losses the bidder may incur in the preparation of the bids and (b) obligation to inform the affected bidder/s of the grounds for the basis of BAC’s action.


Printing and Reproduction of Instrumental Materials and SLMs – 2021

The PROVINCIAL GOVERNMENT OF AURORA, through its Bids and Awards Committee (BAC), invites all eligible suppliers/manufacturers/distributors/contractors to bid for the hereunder project:

Name Of ProjectLocationApproved Budget for the Contract
PRINTING AND REPRODUCTION OF INSTRUCTIONAL MATERIALS AND SLMsBALER, AURORA5,800,000.00
TOTAL 5,800,000.00

Prospective bidders should have experience in undertaking a similar project within the last two (2) years with an amount of at least 50% of the proposed project for bidding. The Eligibility Check/Screening as well as the Preliminary Examination of Bids shall use non-discretionary “pass/fail” criteria.  Post-qualification of the lowest calculated bid shall be conducted.

All particulars relative to Eligibility Statement and Screening, Bid Security, Performance Security, Pre-bidding Conference, Evaluation of Bids, Post Qualification and Awards of Contract shall be governed by the pertinent provisions of RA 9184 and its Implementing Rules and Regulations (IRR).

The complete schedule of activities is listed, as follows:

ActivitiesSchedule
1.  Issuance of Bid DocumentsJanuary 12, 2021 –February 1, 2021  until 9:00 AM
2.  Pre-bid ConferenceJanuary 20, 2021 @  2:00 PM
3.  Submission of Eligibility and BidsFebruary 1, 2021  until 9:00 AM
4.  Opening of BidsFebruary 1, 2021  @ 10:00 AM
  • Pre-Bid Conference/ Opening of Bids’ date is automatically re- scheduled to the next working day whenever such date is declared a holiday.

The BAC will issue to prospective bidders Eligibility Forms upon payment to the Provincial Treasurer’s Office of the PGA of a non-refundable amount for the following approved budget for the contract.

The Provincial Government of Aurora assumes no responsibility whatsoever to compensate or indemnify bidders for any expenses incurred in the preparation of the bid. Only those who have purchased the Bidding Documents shall be allowed to participate in the pre-bid conference and raise or submit written queries or clarifications. The PGA also reserves the right to reject any or all bids, to declare the bidding a failure or waive any defect or informality and to accept bids as may be considered most advantageous to the PGA without thereby incurring any of the following: (a) liability whatsoever to offset expenses or losses the bidder may incur in the preparation of the bids and (b) obligation to inform the affected bidder/s of the grounds for the basis of BAC’s action.


PROCUREMENT OF MATERIALS FOR FIBERGLASS BOAT – 2021

The PROVINCIAL GOVERNMENT OF AURORA, through its Bids and Awards Committee (BAC), invites all eligible suppliers/manufacturers/distributors/contractors to bid for the hereunder project:

Name Of ProjectLocationApproved Budget for the Contract
PROCUREMENT OF MATERIALS FOR FIBERGLASS BOATOPAg- ATC Compound, Baler, Aurora2,500,000.00
TOTAL 2,500,000.00

Prospective bidders should have experience in undertaking a similar project within the last two (2) years with an amount of at least 50% of the proposed project for bidding. The Eligibility Check/Screening as well as the Preliminary Examination of Bids shall use non-discretionary “pass/fail” criteria.  Post-qualification of the lowest calculated bid shall be conducted.

All particulars relative to Eligibility Statement and Screening, Bid Security, Performance Security, Pre-bidding Conference, Evaluation of Bids, Post Qualification and Awards of Contract shall be governed by the pertinent provisions of RA 9184 and its Implementing Rules and Regulations (IRR). The complete schedule of activities is listed, as follows:

ActivitiesSchedule
1.  Issuance of Bid DocumentsJanuary 27, 2021 – February 16, 2021 until 9:00 AM
2.  Pre-bid ConferenceFebruary 4, 2021 @  2:00 PM
3.  Submission of Eligibility and BidsFebruary 16, 2021 until 9:00 AM
4.  Opening of BidsFebruary 16, 2021 @ 10:00 AM
  • Pre-Bid Conference/ Opening of Bids’ date is automatically re- scheduled to the next working day whenever such date is declared a holiday.

The BAC will issue to prospective bidders Eligibility Forms upon payment to the Provincial Treasurer’s Office of the PGA of a non-refundable amount for the following approved budget for the contract.

The Provincial Government of Aurora assumes no responsibility whatsoever to compensate or indemnify bidders for any expenses incurred in the preparation of the bid. Only those who have purchased the Bidding Documents shall be allowed to participate in the pre-bid conference and raise or submit written queries or clarifications. The PGA also reserves the right to reject any or all bids, to declare the bidding a failure or waive any defect or informality and to accept bids as may be considered most advantageous to the PGA without thereby incurring any of the following: (a) liability whatsoever to offset expenses or losses the bidder may incur in the preparation of the bids and (b) obligation to inform the affected bidder/s of the grounds for the basis of BAC’s action.


Goods Batch 2 – 2021

The PROVINCIAL GOVERNMENT OF AURORA, through its Bids and Awards Committee (BAC), invites all eligible suppliers/manufacturers/distributors/contractors to bid for the hereunder project:

Name Of ProjectLocationApproved Budget for the Contract
PROCUREMENT OF MEDICAL EQUIPMENTAURORA MEMORIAL HOSPITAL, BRGY. RESERVA, Baler, Aurora1,609,800.00
PROCUREMENT OF FEMALE CATTLE (BRAHMAN GRADES)PROVINCIAL VETERINARY OFFICE1,400,000.00
PRINTING AND REPRODUCTION OF INSTRUCTIONAL MATERIALS AND SLMsDEP-ED, DIVISION OF AURORA11,384,321.00
 PROCUREMENT OF TARPAULIN ECO SOLVENT PRINTERPROVINCIAL GENERAL SERVICES OFFICE1,100,000.00
TOTAL  

Prospective bidders should have experience in undertaking a similar project within the last two (2) years with an amount of at least 50% of the proposed project for bidding. The Eligibility Check/Screening as well as the Preliminary Examination of Bids shall use non-discretionary “pass/fail” criteria.  Post-qualification of the lowest calculated bid shall be conducted.

All particulars relative to Eligibility Statement and Screening, Bid Security, Performance Security, Pre-bidding Conference, Evaluation of Bids, Post Qualification and Awards of Contract shall be governed by the pertinent provisions of RA 9184 and its Implementing Rules and Regulations (IRR).

The complete schedule of activities is listed, as follows:

ActivitiesSchedule
1.  Issuance of Bid DocumentsFebruary 1, 2021 – February 21, 2021 until 9:00 AM
2.  Pre-bid ConferenceFebruary 9, 2021 @  10:00 AM
3.  Submission of Eligibility and BidsFebruary 21, 2021 until 9:00 AM
4.  Opening of BidsFebruary 21, 2021 @ 10:00 AM
  • Pre-Bid Conference/ Opening of Bids’ date is automatically re- scheduled to the next working day whenever such date is declared a holiday.

The BAC will issue to prospective bidders Eligibility Forms upon payment to the Provincial Treasurer’s Office of the PGA of a non-refundable amount for the following approved budget for the contract.

The Provincial Government of Aurora assumes no responsibility whatsoever to compensate or indemnify bidders for any expenses incurred in the preparation of the bid. Only those who have purchased the Bidding Documents shall be allowed to participate in the pre-bid conference and raise or submit written queries or clarifications. The PGA also reserves the right to reject any or all bids, to declare the bidding a failure or waive any defect or informality and to accept bids as may be considered most advantageous to the PGA without thereby incurring any of the following: (a) liability whatsoever to offset expenses or losses the bidder may incur in the preparation of the bids and (b) obligation to inform the affected bidder/s of the grounds for the basis of BAC’s action.


Infrastructure Project Batch 1 – 2021

The PROVINCIAL GOVERNMENT OF AURORA, through its Bids and Awards Committee (BAC), invites all eligible contractors registered with and classified by the Philippine Contractors Accreditation Board (PCAB), to bid for the hereunder contract:

Name Of ProjectLocationApproved Budget for the Contract
CONSTRUCTION OF WAREHOUSE WITH MPDP GENERAL REQUIREMENTSLAYOUT & EXCAVATIONFILLING OF MATERIALSCONCRETE & MASONRY WORKSFORMWORKS & SCAFFOLDING CARPENTRY WORKSDOORS & WINDOWSPAINTING WORKSTILE WORKSDOWNSPOUTPLUMBING WORKSROOF FRAMING & ROOFING WORKS DRYING PAVEMENT (1.8X16.225M X 0.15M)ELECTRICAL WORKSBRGY. URA, DILASAG, AURORA4,500,000.00
CONSTRUCTION OF FTMR DITUMABO L. PIMENTEL PART A OTHER GENERAL REQUIREMENTS B.4 CONSTRUCTION SURVEY AND STAKING B.5(a) Project Billboard/ Sign Board (PGA) b.5b  Project Billboard/ Sign Board (COA) B.9 Mobilization/ Demobilization PART B Earthworks 100(1) Clearing & Grubbing (with stripping) 102(2)a Roadway Excavation (surplus common) 103(1)a structure Excavation (Surplus Common) 104(1)a Embankment (from borrow) 105(1) Subgrade Preparation (common material) PART C SUBBASE AND BASE COURSE 200 Aggregate Subbase Course PART D SURFACE COURSE 311(1)a.2 PCCP pavement (Plain) – Conventional Method, 200mm thk. PART E DRAINAGE AND SLOPE PROTECTION STRUCTURES 505(5) Grouted Riprap (Class A)SAN LUIS, AURORA3,000,000.00
CONSTRUCTION OF TWO-STOREY MULTI-PURPOSE BLDG. GENERAL REQUIREMENTS GENERAL REQUIREMENTS (MOB./DEMOB.,AND PGA SIGN BOARD AND OTHER REQUIRED DOCUMENTS)EARTHWORKS 803(1)a STRUCTURE EXCAVATION(COMMON SOIL) 804(4) GRAVEL BEDDING 804(4)1 EMBANKMENT SPCL ISOIL POISONING CONCRETE WORKS 900.0 REINFORCED CONCRETE 902(1)a1 REINFORCING STEEL OF REINFORCED CONCRETE STRUCTURES, GRADE 40 MASONRY WORKS 1046(2)a1 150mm CHB Non –Load Bearing (including Reinforcing Steel) 903(2) FORMWORKS AND FALSEWORKS PLASTERING 1027(1) CEMENT PLASTER FINISH DOORS (1-D1,2-D2, 2-D3) 1010(1) FRAMES (JAMBS, SILL, HEAD, TRANSOMS AND MULLIONS) 1004(2)G HINGES WINDOWS (GROUND FLOOR ONLY) 1005(1) UPVC CASEMENT WINDOW 1005(1)a UPVC AWNING –FIXED WINDOW WITH TRANSOM 1005(1)b UPVC AWNING YPE WINDOW IX CEILING WORKS (GROUND FLOOR ONLY) 1003(1) ¼ THK MARINE PLYWOOD ON METAL FRAME CEILING X ROOFRAMING WORKS 1047(2)b STRUCTURAL STEEL PURLINS INCLUDING C FASCIA BOARD 1047(2)a STRUCTURALL STEEL TRUSSES 1047(6) METAL STRUCTURE ACCESSORIES (STEEL PLATES) 1047(7)b METAL STRUCTURE ACCESSORIES (SAGRODS) XI TINSMITHRY WORKS 1014(1)b1 PREPAINTED METAL SHEETS (CORRUGATED, LONG SPAN, 0.5MM THK.) 1013(2)a FABRICATED METAL ROOFING ACCESSORY (RIDGE ROLL) 1013(2) c FABRICATED METAL ROOFING ACCESSORY (GUTTER) SPCL II DOWNSPOUT XII PAINTING WORKS 1032(1)c PAINTING WORKS (METAL PAINTING) 1001(6)b1 CATCH BASIN SPCL III SEPTIC VAULT 1001(6)b1 PLUMBING WORKS SANITARY   PIPE AND FITTINGS, WATER LINES XIII ELECTRICAL WORKS (ROUGH IN)BRGY. DIBARAYBAY, DINALUNGAN, AURORA2,500,000.00
TOTAL  

Prospective bidders should possess a valid PCAB License applicable to the contract, have completed a similar contract with a value of at least 50% of the ABC, and have key personnel and equipment available for the prosecution of the contract.  The BAC will use non-discretionary pass/fail criteria in the Eligibility Check/Screening as well as the Preliminary Examination of Bids.  The BAC will conduct post-qualification of the lowest calculated bid.

All particulars relative to Eligibility Statement and Screening, Bid Security, Performance Security, Pre-bidding Conference, Evaluation of Bids, Post Qualification and Award of Contract shall be governed by the pertinent provisions of RA 9184 and its Implementing Rules and Regulations (IRR).

The schedule of BAC activities is as follows:

ActivitiesSchedule
1.  Issuance of Bid DocumentsJanuary 6, 2021 – January 26, 2021  until 9:00 AM
2.  Pre-bid ConferenceJanuary 14, 2021 @  2:00 PM
3.  Submission of Eligibility and BidsJanuary 26, 2021 until 9:00 AM
4.  Opening of BidsJanuary 26, 2021  @ 10:00 AM
  • Pre-Bid Conference/ Opening of Bids’ date is automatically re- scheduled to the next working day whenever such date is declared a holiday.

The BAC will issue to prospective bidders Eligibility Forms at BAC Secretariat Office, Capitol Compound, Baler, Aurora, upon their submission of a LOI.  Prospective bidders shall submit the Eligibility Requirements to the BAC at the said address.  They may also obtain the results of the

Eligibility Check by the BAC at the same address. Bids document will be available only to prospective bidders upon payment to the Provincial Treasurer’s Office (PTO) of the Provincial Government of Aurora (PGA) of non-refundable amount for the following approved budget for the contract:

The Provincial Government of Aurora assumes no responsibility whatsoever to compensate or indemnify bidders for any expenses incurred in the preparation of the bid. Only those who have purchased the Bidding Documents shall be allowed to participate in the pre-bid conference and raise or submit written queries or clarifications.  The PGA also reserves the right to reject any or all bids, to declare the bidding a failure or waive any defect or informality and to accept bids as may be considered most advantageous to the PGA.


Infrastructure Project Batch 2 – 2021

The PROVINCIAL GOVERNMENT OF AURORA, through its Bids and Awards Committee (BAC), invites all eligible contractors registered with and classified by the Philippine Contractors Accreditation Board (PCAB), to bid for the hereunder contract:

Name Of ProjectLocationApproved Budget for the Contract
CONCRETING OF APPROACH SLAB INSTALLATION OF ROAD GUARDRAIL IGANG BRIDGE PART B OTHER GENERAL REQUIREMENTS B.5 PROJECT BILLBOARD/SIGNBOARD B.7 OCCUPATIONAL SAFETY AND HEALTH PROGRAM PART C EARTHWORKS 104(1)b EMBANKMENT (from BORROW) PART D SUBBASE AND BASE COURSE 200 AGGREGATE SUBBASE COURSE PART E SURFACE COURSE 311(1)a.3 PORTLAND CEMENT CONCRETE PAVEMENT (UNREINFORCED) 230MM THK,-14DAYS PART H MISCELLANEOUS STRUCTURES 603(3)a METAL GUARDRAILS (METAL BEAM) INCLUDING CONCRETE POST 603(3)b GUARDRAIL END PIECES 605(2)a REGULATORY SIGN, 600MM CIRCULAR POST 605(3) INFORMATORY SIGN 750MM TRIANGULAR WITH POST 612(1) REFLECTORIZED THERMOPLASTIC PAVEMENT MARKINGS (WHITE) 612(2) REFLECTORIZED THERMOPLASTIC PAVEMENT MARKINGS (YELLOW) 620(A) CHEVRON SIGN (450MMX600MM)DILASAG, AURORA3,000,000.00
IMPROVEMENT OF TOURISM SITE AT BRGY. PALTIC (WHITE BEACH GOING TO MOUNTAIN VIEW) PART A FACILITIES FOR THE ENGINEER A.1.1(8) PROVISION OF FIELD OFFICE FOR THE ENGINEER PART B OTHER GENERAL REQUIREMENTS B.4 CONSTRUCTION SURVEY AND STAKING B5(a) PROJECT SIGNBOARD B.5 (b) PROJECT BILLBOARD/SIGNBOARD B.7 OCCUPATIONAL SAFETY AND HEALTH PROGRAM B.9 MOBILIZATION/DEMOBILIZATION PART C EARTHWORKS 100(2)a INDIVIDUAL REMOVAL OF TREES (SMALL A, 150-300mmǾ) 103(1)b STRUCTURE EXCAVATION (SOFT ROCK) 103(3) FOUNDATION FILL 103(3a) VIEW DECK AND STAIR BASE PREPARATION PART D ALL CONCRETE WORKS D.1 VIEW DECK 404 REINFORCING STEEL BAR, GRADE 40 (MINOR STRUCTURES) 405 STRUCTURAL CONCRETE CLASS A (MINOR STRUCTURE) D.2 STATUE 404(1a) REINFORCING STEEL BAR, GRADE 40 (MINOR STRUCTURES) 405.0 STRUCTURAL CONCRETE CLASS A(MINOR STRUCTURE) D.3 STAIR 404(1a) REINFORCING STEEL BAR, GRADE 40 (MINOR STRUCTURES) 405.0 STRUCTURAL CONCRETE CLASS A(MINOR STRUCTURE) PART E PAINTING WORKS E.1 VIEW DECK AND STAIR 1032(1)a PAINTING WORKS(MASSONRY PAINTING) E.1 STATUE 1032(1)a PAINTING WORKS(MASSONRY PAINTING)DINGALAN, AURORA5,000,000.00
CONCRETING OF ROAD SPCL I GENERAL REQUIREMENTS I.1 MOBILIZATION/ DEMOBILIZATION I.2 SETTING OUT AND STAKING I.3 CONSTRUCTION SAFETY AND HEALTH PROGRAM I.4 PROJECT SIGNBOARD (PGA) I.5 SIGNBOARD COA 104 EMBANKMENT (FROM BORROW) 105(2) SUBGRADE PREPARATION (EXISTING PAVEMENT) 200 AGGREGATE BASE COARSE 311(1)a.2 PCC PAVEMENT (PLAIN) CONVENTIONAL METHOD, 200mm thk.BRGY. 02, SANLUIS, AURORA1,000,000.00
COMPLETION OF BRGY. PORTABLE SYSTEM, DIBUTUNAN GENERAL REQUIREMENTS I.1 MOBILIZATION/STACKING I.2 CONSTRUCTION OF SAFETY AND HEALTH PROGRAM I.3 PROJECT SIGNBOARD (PGA) I.4 PROJECT SIGNBOARD (COA) 103(1)a STRUCTURE EXCAVATION (COMMON SOIL) SPCL 1 BACKFILLING/RESTORATION 404 REINFORCING STEEL BAR, GRADE 40(MINOR STRUCTURE) 405 STRUCTURAL CONCRETE CLASS A(MINOR STRUCTURES) SPCL 2 PIPE LINEDIPACULAO, AURORA1,500,000.00
CONSTRUCTION OF BLOOD BANK, PHILIPPINE NATIONAL RED CROSS BALER, AURORA GENERAL REQUIREMENTS I GENERAL REQUIREMENT (COA AND PGA SIGNBOARD, AND OTHER REQUIRED DOCUMENTS SPCL I DEMOLITION OF EXSISTING STRUCTURES (WALLS, COLUMN) BEAM, ETC.) II EARTH WORKS 803(1)a STRUCTURE EXCAVATION (COMMON SOIL) 804(4) GRAVEL BEDDING 804(1) EMBANKMENT III CONCRETE WORKS 900 REINFORCED CONCRETE 902(1)a1 REINFORCING STEEL OF REINFORCED CONCRETE STRUCTURES, GRADE 40 IV MASONRY WORKS 1046(2)a1 150mm CHB NON-LOAD BEARING (INCLUDING REINFORCING STEEL) 903(2) FORMWORKS AND FALSEWORKS V PLASTERING 1027(1) CEMENT PLASTER FINISH VI DOORS 1010(1) FRAMES (JAMBS, SILL HEAD, TRANSOMS, AND MULLIONS) 1010(2)b WOODEN PANEL DOOR 1010(2)a SWING FLUSH DOOR 1010(2)d GLASS DOOR 1010(2)e GLASS DOOR WITH TRANSOM 1010(2)f FRAMELESS GLASS DOOR 1004(2)a LOCKSET 1004(2)g HINGES VII WINDOWS 1005(1) UPVC CASEMENT WINDOW W/ TRANSOM 1005(1)a UPVC FIXED WINDOW 1005(1)b UPVC AWNING TYPE WINDOW 1005(1)c LOUVER TYPE WINDOW VII TILE WOKS 1018(1) GLAZED TILES AND TRIMS 1018(2) UNGLAZED TILE IX CEILING 1003(1) ¼ thk MARINE PLYWOOD ON METAL FRAME CEILING X ROOFRAMING 1047(2)b STRUCTURAL STEEL PURLINS INCLUDING c FASCIA BOARD 1047(2)a STRUCTURAL STEEL, TRUSSES 1047(6) METAL STRUCTURE ACCESSORIES (STEEL PLATES) 1047(7)b METAL STRUCTURE ACCESSORIES (SAGRODS) XI TINSMITHRY WORKS 1014(1)b1 PREPAINTED METAL SHEETS(CORRUGATED, LONG SPAN, 0.5mm.thk.) 1013(2)a FABRICATED METAL ROOFING ACCESSORY (RIDGE ROLL) 1013(2)c FABRICATED METAL ROOFING ACCESSORY (GUTTER) 1013(2)b FABRICATED METAL ROOFING ACCESSORY (SPANDREL) SPCL II DOWNSPOUT XII PAINTING WORKS 1032(1)c PAINTING WORKS (METAL PAINTING) 1032(1)a PAINTING WORKS (MASSONRY PAINTING) 1032(1)b PAINTING WORKS (CEILING PAINTING) SPCL III CATCH BASIN SPCL IV SEPTIC VAULT PLUMBING WORKS 1001(6)b1 SANITARY PIPE FITTINGS, WATER LINES, TOILET FLUSH TYPE WITH FIXTURES XIII ELECTRICAL WORKSBALER, AURORA4,000,000.00
BRGY. POTABLE WATER SYSTEM, DIAMANEN I GENERAL REQUIREMENTS I.1 MOBILIZATION/ DEMOBILIZATION 1.2 CONSTRUCTION SAFETY AND HEALTH PROGRAM I.3 PROJECT SIGN BOARD (PGA) 1.4 PROJECT SIGN BOARD (COA) 103(1)a STRUCTURE EXCAVATION (COMMON SOIL) SPCL 1 BACKFILLING/RESTORATION SPCL 2 PIPE LINEDIPACULAO, AURORA1,500,000.00
CONCRETING OF BANGCO-FLORIDA SPCL I GENERAL REQUIREMENTS I.1 MOBILIZATION/DEMOBILIZATION I.2 SETTING OUT AND STACKING I.3 CONSTRUCTION SAFETY AND HEALTH PROGRAM I.4 PROJECT SIGNBOARD (PGA) I.5 SIGNBOARD COA 102(1) ROADWAY EXCAVATION (UNSUITABLE) 103(1)a STRUCTURE EXCAVATION (COMMON SOIL) 104 EMBANKMENT (FROM BORROW) 105(2) SUBGRADE PREPARATION (EXISTING PAVEMENT) 200 AGGREGATE BASE COARSE 311(1)a2 PCCP PAVEMENT (PLAIN) –CONVENTIONAL METHOD, 200mm thk. 404 REINFORCING STEEL BAR, GRADE 40(MINOR STRUCTURE) 405 STRUCTURAL CONCRETE CLASS A (MINOR STRUCTURE) 505(5) GROUTED RIPRAP (CLASS A) 500(1)a PIPE CULVERTS, 610mm dia. (24”Ǿ)MARIA AURORA, AURORA2,000,000.00
CONSTRUCTION OF MULTI-PURPOSE HALL PHASE II SPCL I MOBILIZATION/DEMOBILIZATION (TRASHIPMENT OF MATERIALS) SPCL II GENERAL REQUIREMENTS (PGA & COA SIGN BOARD, CONSTRUCTION & HEALTH PROGRAM AND OTHER REQUIRED DOCUMENTS) 900 REINFORCED CONCRETE 902(1)a1 REINFORCING STEEL OF REINFORCED CONCRETE STRUCTURES, GRADE 40 903(2) FORM WORKS AND FALSE WORKS 1027(1) CEMENT PLASTER FINISH 1047(2)b STRUCTURAL STEEL PURLINS 1047(2)a STRUCTURAL STEEL, TRUSSES, STRUT 1047(6) METAL STRUCTURE ACCESSORIES (STEEL PLATES) 1047(7)b METAL STRUCTURE ACCESSORIES (STEEL SAGRODS) 1047(4) METAL STRUCTURE ACCESSORIES (CROSSBRACING) 1047(3)c METAL STRUCTURE ACCESSORIES (TURNBUCKLE) 1014(1)b1 PREPAINTED METAL SHEETS CORRUGATED, LONG SPAN,0.5mm thk.) 1032(1)c PAINTING WORKS (METAL PAINTING)BRGY. DIMANAYAT, SAN LUIS, AURORA1,500,000.00
CONSTRUCTIONOF MULTI-PURPOSE HALL SPCL I MOBILIZATION/DEMOBILIZATION (TRASHIPMENT OF MATERIALS) SPCL II GENERAL REQUIREMENTS (PGA & COA SIGN BOARD, CONSTRUCTION & HEALTH PROGRAM AND OTHER REQUIRED DOCUMENTS) 900 REINFORCED CONCRETE 902(1)a1 REINFORCING STEEL OF REINFORCED CONCRETE STRUCTURES, GRADE 40 903(2) FORM WORKS AND FALSE WORKS 1027(1) CEMENT PLASTER FINISH 1047(2)b STRUCTURAL STEEL PURLINS 1047(2)a STRUCTURAL STEEL, TRUSSES, STRUT 1047(6) METAL STRUCTURE ACCESSORIES (STEEL PLATES) 1047(7)b METAL STRUCTURE ACCESSORIES (STEEL SAGRODS) 1047(4) METAL STRUCTURE ACCESSORIES (CROSSBRACING) 1047(3)c METAL STRUCTURE ACCESSORIES (TURNBUCKLE) 1014(1)b1 PREPAINTED METAL SHEETS CORRUGATED, LONG SPAN,0.5mm thk.) 1032(1)c PAINTING WORKS (METAL PAINTING)BRGY. DIBAYABAY, SAN LUIS, AURORA2,500,000.00
CONSTRUCTION OF TWO STOREY MULTI-PURPOSE HALL GENERAL REQUIREMENTS I GENERAL REQUIREMENT (COA AND PGA SIGNBOARD, AND OTHER REQUIRED DOCUMENTS) II EARTH WORKS 803(1)a STRUCTURE EXCAVATION (COMMON SOIL) 804(4) GRAVEL BEDDING 804(1) EMBANKMENT SPCL 1 SOIL POISONING III CONCRETE WORKS (GROUND FLOOR ONLY) 900 REINFORCED CONCRETE 902(1)a1 REINFORCING STEEL OF REINFORCED CONCRETE STRUCTURES, GRADE 40 IV MASONRY WORKS 1046(2)a1 100mm CHB NON-LOAD BEARING (INCLUDING REINFORCING STEEL) 903(2) FORMWORKS AND FALSEWORKS V PLASTERING (GROUND FLOOR ONLY) 1027(1) CEMENT PLASTER FINISH VI DOORS (D1,D2,(CR),2D3) 1010(1) FRAMES (JAMBS, SILL HEAD, TRANSOMS, AND MULLIONS) 1010(2)b WOODEN PANEL DOOR 1010(2)a SWING FLUSH DOOR 1004(2)a LOCKSET 1004(2)g HINGES VII WINDOWS (GROUND FLOOR ONLY) 1005(1) UPVC SLIDING WINDOW 1005(1)a UPVC AWNING FIXED WINDOW WITH TRANSOM 1005(1)b UPVC AWNING TYPE WINDOW VII ELECTRICAL WORKSBRGY. 02, CASIGURAN, AURORA1,500,000.00
TOTAL  

Prospective bidders should possess a valid PCAB License applicable to the contract, have completed a similar contract with a value of at least 50% of the ABC, and have key personnel and equipment available for the prosecution of the contract.  The BAC will use non-discretionary pass/fail criteria in the Eligibility Check/Screening as well as the Preliminary Examination of Bids.  The BAC will conduct post-qualification of the lowest calculated bid.

All particulars relative to Eligibility Statement and Screening, Bid Security, Performance Security, Pre-bidding Conference, Evaluation of Bids, Post Qualification and Award of Contract shall be governed by the pertinent provisions of RA 9184 and its Implementing Rules and Regulations (IRR).

The schedule of BAC activities is as follows:

ActivitiesSchedule
1.  Issuance of Bid DocumentsJanuary 12, 2021 –February 1, 2021  until 9:00 AM
2.  Pre-bid ConferenceJanuary 20, 2021 @  2:00 PM
3.  Submission of Eligibility and BidsFebruary 1, 2021  until 9:00 AM
4.  Opening of BidsFebruary 1, 2021  @ 10:00 AM
  • Pre-Bid Conference/ Opening of Bids’ date is automatically re- scheduled to the next working day whenever such date is declared a holiday.

The BAC will issue to prospective bidders Eligibility Forms at BAC Secretariat Office, Capitol Compound, Baler, Aurora, upon their submission of a LOI.  Prospective bidders shall submit the Eligibility Requirements to the BAC at the said address.  They may also obtain the results of the

Eligibility Check by the BAC at the same address. Bids document will be available only to prospective bidders upon payment to the Provincial Treasurer’s Office (PTO) of the Provincial Government of Aurora (PGA) of non-refundable amount for the following approved budget for the contract:

The Provincial Government of Aurora assumes no responsibility whatsoever to compensate or indemnify bidders for any expenses incurred in the preparation of the bid. Only those who have purchased the Bidding Documents shall be allowed to participate in the pre-bid conference and raise or submit written queries or clarifications.  The PGA also reserves the right to reject any or all bids, to declare the bidding a failure or waive any defect or informality and to accept bids as may be considered most advantageous to the PGA.


Infrastructure Project Batch 3 – 2021

The PROVINCIAL GOVERNMENT OF AURORA, through its Bids and Awards Committee (BAC), invites all eligible contractors registered with and classified by the Philippine Contractors Accreditation Board (PCAB), to bid for the hereunder contract:

Name Of ProjectLocationApproved Budget for the Contract
CONSTRUCTION OF TWO-STOREY MULTI-PURPOSE BLDG. GENERAL REQUIREMENTS GENERAL REQUIREMENTS (MOB./DEMOB.,AND PGA SIGN BOARD AND OTHER REQUIRED DOCUMENTS) 803(1)a STRUCTURE EXCAVATION(COMMON SOIL) 804(4) GRAVEL BEDDING 804(4)1 EMBANKMENT SPCL ISOIL POISONING 900. REINFORCED CONCRETE 902(1)a1 REINFORCING STEEL OF REINFORCED CONCRETE STRUCTURES, GRADE 40 1046(2)a1 150mm CHB Non –Load Bearing (including Reinforcing Steel) 1027(1) CEMENT PLASTER FINISH 903(2) FORMWORKS AND FALSEWORKS 1010(1) FRAMES (JAMBS, SILL, HEAD, TRANSOMS AND MULLIONS) 1010(2)b Wooden Panel Door 1010(2)a Swing Flush Door 1004(2)a Lockset 1004(2)G HINGES 1005(1) UPVC CASEMENT WINDOW 1005(1)a UPVC AWNING –FIXED WINDOW WITH TRANSOM 1005(1)b UPVC AWNING YPE WINDOW 1003(1) ¼ THK MARINE PLYWOOD ON METAL FRAME CEILING 1032(1)a PAINTING WORKS (MASONRY PAINTING 1001(6)b1 CATCH BASIN SPCL III SEPTIC VAULT 1001(6)b1 PLUMBING WORKS XI ELECTRICAL WORKS (ROUGH IN)BRGY. DIBARAYBAY, DINALUNGAN, AURORA2,500,000.00
TOTAL  

Prospective bidders should possess a valid PCAB License applicable to the contract, have completed a similar contract with a value of at least 50% of the ABC, and have key personnel and equipment available for the prosecution of the contract.  The BAC will use non-discretionary pass/fail criteria in the Eligibility Check/Screening as well as the Preliminary Examination of Bids.  The BAC will conduct post-qualification of the lowest calculated bid.

All particulars relative to Eligibility Statement and Screening, Bid Security, Performance Security, Pre-bidding Conference, Evaluation of Bids, Post Qualification and Award of Contract shall be governed by the pertinent provisions of RA 9184 and its Implementing Rules and Regulations (IRR).

The schedule of BAC activities is as follows:

ActivitiesSchedule
1.  Issuance of Bid DocumentsFebruary 1, 2021 – February 21, 2021 until 9:00 AM
2.  Pre-bid ConferenceFebruary 9, 2021 @  10:00 AM
3.  Submission of Eligibility and BidsFebruary 21, 2021 until 9:00 AM
4.  Opening of BidsFebruary 21, 2021 @ 10:00 AM
  • Pre-Bid Conference/ Opening of Bids’ date is automatically re- scheduled to the next working day whenever such date is declared a holiday.

The BAC will issue to prospective bidders Eligibility Forms at BAC Secretariat Office, Capitol Compound, Baler, Aurora, upon their submission of a LOI.  Prospective bidders shall submit the Eligibility Requirements to the BAC at the said address.  They may also obtain the results of the Eligibility Check by the BAC at the same address. Bids document will be available only to prospective bidders upon payment to the Provincial Treasurer’s Office (PTO) of the Provincial Government of Aurora (PGA) of non-refundable amount for the following approved budget for the contract:

The Provincial Government of Aurora assumes no responsibility whatsoever to compensate or indemnify bidders for any expenses incurred in the preparation of the bid. Only those who have purchased the Bidding Documents shall be allowed to participate in the pre-bid conference and raise or submit written queries or clarifications.  The PGA also reserves the right to reject any or all bids, to declare the bidding a failure or waive any defect or informality and to accept bids as may be considered most advantageous to the PGA.


Infrastructure Project Batch 4 – 2021

The PROVINCIAL GOVERNMENT OF AURORA, through its Bids and Awards Committee (BAC), invites all eligible contractors registered with and classified by the Philippine Contractors Accreditation Board (PCAB), to bid for the hereunder contract:

Name Of ProjectLocationApproved Budget for the Contract
CONSTRUCTION OF FLOOD CONTROL AT SAPSAP RIVER PART B GENERAL REQUIREMENTS B.5a Project Billboard/Signboard (PGA) B.5b Project Signboard (COA) B.7 Occupational Safety and Health Program B.9 Mobilization/Demobilization PART J FLOOD CONTROL AND DRAINAGE PART I-A EARTHWORK 1701 (a) Channel Excavation 1702 Structure Excavation (Refer to Item 103) PART I-B BANK AND SLOPE PROTECTION WORKS 1714(a) Gabions 1714(b) MattressesBRGY. DILAGUIDI, DILASAG, AURORA10,000,000.00
FLOOD CONTROL PROJECT PART B GENERAL REQUIREMENTS B.5a Project Billboard/Signboard (PGA) B.5b Project Signboard (COA) B.7 Occupational Safety and Health Program B.9 Mobilization/Demobilization PART J FLOOD CONTROL AND DRAINAGE PART I-A EARTHWORK 1702 Structure Excavation 1704(1)b Embankment from Borrow PART I-B BANK AND SLOPE PROTECTION WORKS 404 Reinforcing Steel Bars G40 405 Structural Concrete Class A 1714(a) GabionsBRGY. 1, CASIGURAN, AURORA3,000,000.00
FLOOD CONTROL PROJECT SPCL. I GENERAL REQUIREMENTS B.9 Mobilization/Demobilization B.7 Occupational Safety and Health Program B.5 Project Signboard 100(1) Cleaning & Grubbing (with stripping) 103(1)a Structure Excavation (Common Soil) 104(1)b Embankment (from Borrow) 511(1) Gabions 511 (2) MattressesBRGY. LUAL, CASIGURAN, AURORA3,000,000.00
CONSTRUCTION OF FLOOD CONTROL PROJECT CASALOGAN RIVER, CONSTRUCTION OF FLOOD CONTROL AT SAPSAP RIVER PART B GENERAL REQUIREMENTS B.5a Project Billboard/Signboard (PGA) B.5b Project Signboard (COA) B.7 Occupational Safety and Health Program B.9 Mobilization/Demobilization PART J FLOOD CONTROL AND DRAINAGE PART I-A EARTHWORK 1702 Structure Excavation (Refer to Item 103, Vol. II Blue book) 1704(1)b Embankment from Borrow PART I-A EARTHWORK 1712(2) concrete slope protection 404 Reinforcing Steel Bars G40 405 Structural Concrete Class A 1717(2)a1 Sheet Pile (steel slope protection) 1710(2)a Grouted Riprap, Class ACASALOGAN RIVER, CASIGURAN, AURORA10,000,000.00
CONSTRUCTION OF WAREHOUSE WITH MPDP GENERAL REQUIREMENTSLAYOUT & EXCAVATIONFILLING OF MATERIALSCONCRETE & MASONRY WORKSFORMWORKS & SCAFFOLDING CARPENTRY WORKSDOORS & WINDOWSPAINTING WORKSTILE WORKSDOWNSPOUTPLUMBING WORKSROOF FRAMING & ROOFING WORKS DRYING PAVEMENT (1.8X16.225M X 0.15M)ELECTRICAL WORKSBRGY. URA, DILASAG, AURORA4,500,000.00
CONSTRUCTION OF FTMR DITUMABO L. PIMENTEL PART A OTHER GENERAL REQUIREMENTS B.4 CONSTRUCTION SURVEY AND STAKING B.5(a) Project Billboard/ Sign Board (PGA) b.5b  Project Billboard/ Sign Board (COA) B.9 Mobilization/ Demobilization PART B Earthworks 100(1) Clearing & Grubbing (with stripping) 102(2)a Roadway Excavation (surplus common) 103(1)a structure Excavation (Surplus Common) 104(1)a Embankment (from borrow) 105(1) Subgrade Preparation (common material) PART C SUBBASE AND BASE COURSE 200 Aggregate Subbase Course PART D SURFACE COURSE 311(1)a.2 PCCP pavement (Plain) – Conventional Method, 200mm thk. PART E DRAINAGE AND SLOPE PROTECTION STRUCTURES 505(5) Grouted Riprap (Class A)SAN LUIS, AURORA3,000,000.00
TOTAL  

Prospective bidders should possess a valid PCAB License applicable to the contract, have completed a similar contract with a value of at least 50% of the ABC, and have key personnel and equipment available for the prosecution of the contract.  The BAC will use non-discretionary pass/fail criteria in the Eligibility Check/Screening as well as the Preliminary Examination of Bids.  The BAC will conduct post-qualification of the lowest calculated bid.

The pertinent provisions of RA 9184 and its Implementing Rules and Regulations (IRR) shall govern all particulars relative to Eligibility Statement and Screening, Bid Security, Performance Security, Pre-bidding Conference, Evaluation of Bids, Post Qualification and Award of Contract.

The schedule of BAC activities is as follows:

ActivitiesSchedule
1.  Issuance of Bid DocumentsFebruary 18, 2021–March 10, 2021  until 9:00 AM
2.  Pre-bid ConferenceFebruary 26, 2021 @  2:00 PM
3.  Submission of Eligibility and BidsMarch 10, 2021  until 9:00 AM
4.  Opening of BidsMarch 10, 2021  @ 10:00 AM
  • Pre-Bid Conference/ Opening of Bids’ date is automatically re- scheduled to the next working day whenever such date is declared a holiday.

The BAC will issue to prospective bidders Eligibility Forms at BAC Secretariat Office, Capitol Compound, Baler, Aurora, upon their submission of a LOI.  Prospective bidders shall submit the Eligibility Requirements to the BAC at the said address.  They may also obtain the results of the Eligibility Check by the BAC at the same address. Bids document will be available only to prospective bidders upon payment to the Provincial Treasurer’s Office (PTO) of the Provincial Government of Aurora (PGA) of non-refundable amount for the following approved budget for the contract:

The Provincial Government of Aurora assumes no responsibility whatsoever to compensate or indemnify bidders for any expenses incurred in the preparation of the bid. Only those who have purchased the Bidding Documents shall be allowed to participate in the pre-bid conference and raise or submit written queries or clarifications.  The PGA also reserves the right to reject any or all bids, to declare the bidding a failure or waive any defect or informality and to accept bids as may be considered most advantageous to the PGA.


Infrastructure Project Batch 5 – 2021

The PROVINCIAL GOVERNMENT OF AURORA, through its Bids and Awards Committee (BAC), invites all eligible contractors registered with and classified by the Philippine Contractors Accreditation Board (PCAB), to bid for the hereunder contract:

Name Of ProjectLocationApproved Budget for the Contract
COMPLETION OF MULTI-PURPOSE BUILDING BRGY. DITAILEN SPCL –I GENERAL REQUIREMENTS (PGA & COA SIGN BOARD, CONSTRUCTION AND SAFETY & HEALTH PROGRAM AND OTHER REQUIRED DOCUMENTS SPCL –II MOBILIZATION AND DEMOBILIZATION SPCL-III CHIPPING OF CONCRETE PAVEMENT 804(1)c EMBANKMENT FROM COMMON BORROW 1046(2)a1 100mm CHB NON-LOAD BEARING (INCLUDING REINFORCING STEAL) 900 REINFORCED CONCRETE 902(1)a1 REINFORING STEEL OF REINFORCED CONCRETE STRUCTURES, GRADE 40 903(2) FORMWORKS AND FALSEWORKS 1047(2)b STRUCTURAL STEEL PURLINS 1047(2)a STRUCTURAL STEEL, TRUSSES STRUTS 1047(6) METAL STRUCTURE ACCESSORIES (STEEL PLATES) 1047(7)b METAL STRUCTURE ACCESSORIES (SAGRODS) 1047(4) METAL STRUCTURE ACCESSORIES (CROSSBRACING) 1047(3)c METAL STRUCTURE ACCESSORIES (TURNBUCKLE) 1014(1)b1 PREPAINTED METAL SHEETS (PREPAINTED, LONG SPAN, 0.5MM THK) 1032(1)c PAINTING WORKS (METAL PAINTING) 1032(1)a PAINTING WORKS (MASONRY PAINTING) SPCL IV CONSTRUCTION OF BASKETBALL RING & BOARD W/ ACCESSORIES & FRAMES (2 SETS)MA. AURORA, AURORA                        2,500,000.00
COMPLETION OF MULTI-PURPOSED BUILDING BRGY. DIKILDIT SPCL –I GENERAL REQUIREMENTS (PGA & COA SIGN BOARD, CONSTRUCTION AND SAFETY & HEALTH PROGRAM AND OTHER REQUIRED DOCUMENTS SPCL –II MOBILIZATION AND DEMOBILIZATION SPCL-III CHIPPING OF CONCRETE PAVEMENT 804(1)c EMBANKMENT FROM COMMON BORROW 1046(2)a1 100mm CHB NON-LOAD BEARING (INCLUDING REINFORCING STEAL) 900 REINFORCED CONCRETE 902(1)a1 REINFORING STEEL OF REINFORCED CONCRETE STRUCTURES, GRADE 40 903(2) FORMWORKS AND FALSEWORKS 1047(2)b STRUCTURAL STEEL PURLINS 1047(2)a STRUCTURAL STEEL, TRUSSES STRUTS 1047(6) METAL STRUCTURE ACCESSORIES (STEEL PLATES) 1047(7)b METAL STRUCTURE ACCESSORIES (SAGRODS) 1047(4) METAL STRUCTURE ACCESSORIES (CROSSBRACING) 1047(3) METAL STRUCTURE ACCESSORIES (TURNBUCKLE) 1014(1)b1 PREPAINTED METAL SHEETS (PREPAINTED, LONG SPAN, 0.5MM THK) 1032(1)c PAINTING WORKS (METAL PAINTING) 1032(1)a PAINTING WORKS (MASONRY PAINTING) SPCL IV CONSTRUCTION OF BASKETBALL RING & BOARD W/ ACCESSORIES & FRAMES (2 SETS)MA. AURORA, AURORA2,500,000.00
COMPLETION OF MULTI-PURPOSE BUILDING BRGY. DIMASESET SPCL –I GENERAL REQUIREMENTS (PGA & COA SIGN BOARD, CONSTRUCTION AND SAFETY & HEALTH PROGRAM AND OTHER REQUIRED DOCUMENTS 704.3 CONCRETE MASONRY BLOCKS 900 REINFORCED CONCRETE 902(1)a1 REINFORING STEEL OF REINFORCED CONCRETE STRUCTURES, GRADE 40 903(2) FORMWORKS AND FALSEWORKS 1047(2)b STRUCTURAL STEEL PURLINS 1047(2)a STRUCTURAL STEEL, TRUSSES STRUTS 1047(6) METAL STRUCTURE ACCESSORIES (STEEL PLATES) 1047(7)b METAL STRUCTURE ACCESSORIES (SAGRODS) 1047(4) METAL STRUCTURE ACCESSORIES (CROSSBRACING) 1047(3)c METAL STRUCTURE ACCESSORIES (TURNBUCKLE) 1014(1)b1 PREPAINTED METAL SHEETS (PREPAINTED, LONG SPAN, 0.5MM THK) 1032(1)c PAINTING WORKS (METAL PAINTING) SPCL III BASKETBALL RING & BOARD W/ ACCESSORIES & FRAMESDILASAG, AURORA2,500,000.00
COMPLETION OF MULTI-PURPOSED BUILDING BRGY. DICOLIAT SPCL –I GENERAL REQUIREMENTS (PGA & COA SIGN BOARD, CONSTRUCTION AND SAFETY & HEALTH PROGRAM AND OTHER REQUIRED DOCUMENTS SPCL –II MOBILIZATION AND DEMOBILIZATION SPCL-III CHIPPING OF CONCRETE PAVEMENT 804(1)c EMBANKMENT FROM COMMON BORROW 1046(2)a1 100mm CHB NON-LOAD BEARING (INCLUDING REINFORCING STEAL) 900 REINFORCED CONCRETE 902(1)a1 REINFORING STEEL OF REINFORCED CONCRETE STRUCTURES, GRADE 40 903(2) FORMWORKS AND FALSEWORKS 1047(2)b STRUCTURAL STEEL PURLINS 1047(2)a STRUCTURAL STEEL, TRUSSES STRUTS 1047(6) METAL STRUCTURE ACCESSORIES (STEEL PLATES) 1047(7)b METAL STRUCTURE ACCESSORIES (SAGRODS) 1047(4) METAL STRUCTURE ACCESSORIES (CROSSBRACING) 1047(3)c METAL STRUCTURE ACCESSORIES (TURNBUCKLE) 1014(1)b1 PREPAINTED METAL SHEETS (PREPAINTED, LONG SPAN, 0.5MM THK) 1032(1)c PAINTING WORKS (METAL PAINTING) 1032(1)a PAINTING WORKS (MASONRY PAINTING) SPCL IV CONSTRUCTION OF BASKETBALL RING & BOARD W/ ACCESSORIES & FRAMES (2 SETS)MA. AURORA, AURORA2,500,000.00
FLOOD CONTROL AT BANGCO-PACUGAO RIVER (GABION TYPE), PUROK 07, BRGY. BANGCO SPCL I GENERAL REQUIREMENTS B.9 MOBILIZATION AND DEMOBILIZATION B.7 CONSTRUCTION AND SAFETY AND HEALTH PROGRAM B.5 PROJECT SIGNBOARD 103(1)a STRUCTURE EXCAVATION (COMMON SOIL) 104(1)a STRUCTURE EXCAVATION FROM ROADWAY EXCAVATION 511(1) GABIONS 511(2) MATTRESSESMA. AURORA, AURORA3,000,000.00
COMPLETION OF MULTI-PURPOSE BUILDING BRGY. DIBUTUNAN SPCL –I GENERAL REQUIREMENTS (PGA & COA SIGN BOARD, CONSTRUCTION AND SAFETY & HEALTH PROGRAM AND OTHER REQUIRED DOCUMENTS SPCL –II MOBILIZATION AND DEMOBILIZATION 903(2) FORMWORKS AND FALSEWORKS 1047(2)b STRUCTURAL STEEL PURLINS 1047(2)a STRUCTURAL STEEL, TRUSSES STRUTS 1047(6) METAL STRUCTURE ACCESSORIES (STEEL PLATES) 1047(7)b METAL STRUCTURE ACCESSORIES (SAGRODS) 1047(4) METAL STRUCTURE ACCESSORIES (CROSSBRACING) 1047(3)c METAL STRUCTURE ACCESSORIES (TURNBUCKLE) 1014(1)b1 PREPAINTED METAL SHEETS (PREPAINTED, LONG SPAN, 0.5MM THK) 1032(1)c PAINTING WORKS (METAL PAINTING) 1032(1)a PAINTING WORKS (MASONRY PAINTING) SPCL III ELECTRICAL WORKS SPCL IV CONSTRUCTION OF BASKETBALL RING & BOARD W/ ACCESSORIES & FRAMES (2 SETS)DIPACULAO, AURORA2,500,000.00
COMPLETION OF MULTI-PURPOSED BUILDING BRGY. SUGUIT   SPCL –I GENERAL REQUIREMENTS (PGA & COA SIGN BOARD, CONSTRUCTION AND SAFETY & HEALTH PROGRAM AND OTHER REQUIRED DOCUMENTS SPCL –II MOBILIZATION AND DEMOBILIZATION SPCL-III CHIPPING OF CONCRETE PAVEMENT 804(1)c EMBANKMENT FROM COMMON BORROW 1046(2)a1 100mm CHB NON-LOAD BEARING (INCLUDING REINFORCING STEAL) 900 REINFORCED CONCRETE 902(1)a1 REINFORING STEEL OF REINFORCED CONCRETE STRUCTURES, GRADE 40 903(2) FORMWORKS AND FALSEWORKS 1047(2)b STRUCTURAL STEEL PURLINS 1047(2)a STRUCTURAL STEEL, TRUSSES STRUTS 1047(6) METAL STRUCTURE ACCESSORIES (STEEL PLATES) 1047(7)b METAL STRUCTURE ACCESSORIES (SAGRODS) 1047(4) METAL STRUCTURE ACCESSORIES (CROSSBRACING) 1047(3)c METAL STRUCTURE ACCESSORIES (TURNBUCKLE) 1014(1)b1 PREPAINTED METAL SHEETS (PREPAINTED, LONG SPAN, 0.5MM THK) 1032(1)c PAINTING WORKS (METAL PAINTING) 1032(1)a PAINTING WORKS (MASONRY PAINTING) SPCL IV CONSTRUCTION OF BASKETBALL RING & BOARD W/ ACCESSORIES & FRAMES (2 SETS)MA. AURORA, AURORA2,500,000.00
COMPLETION OF MULTI-PURPOSE BUILDING BRGY. MASAGANA   SPCL –I GENERAL REQUIREMENTS (PGA & COA SIGN BOARD, CONSTRUCTION AND SAFETY & HEALTH PROGRAM AND OTHER REQUIRED DOCUMENTS 704.3 CONCRETE MASONRY BLOCKS 900 REINFORCED CONCRETE 902(1)a1 REINFORING STEEL OF REINFORCED CONCRETE STRUCTURES, GRADE 40 903(2) FORMWORKS AND FALSEWORKS 1047(2)b STRUCTURAL STEEL PURLINS 1047(2)a STRUCTURAL STEEL, TRUSSES STRUTS 1047(6) METAL STRUCTURE ACCESSORIES (STEEL PLATES) 1047(7)b METAL STRUCTURE ACCESSORIES (SAGRODS) 1047(4) METAL STRUCTURE ACCESSORIES (CROSSBRACING) 1047(3)c METAL STRUCTURE ACCESSORIES (TURNBUCKLE) 1014(1)b1 PREPAINTED METAL SHEETS (PREPAINTED, LONG SPAN, 0.5MM THK) 1032(1)c PAINTING WORKS (METAL PAINTING) SPCL III BASKETBALL RING & BOARD W/ ACCESSORIES & FRAMESDILASAG, AURORA2,500,000.00
CONSTRUCTION OF FLOOD CONTROL AT SALAY CREEK (PHAE II) I GENERAL REQUIREMENTS I.1 MOBILIZATION AND DEMOBILIZATION I.2 PROJECT SIGN BOARD (INCLD. COA AND PGA) I.3 CONSTRUCTION AND SAFETY AND HEALTH PROGRAM 100(2)a INDIVIDUAL REMOVAL OF TREES (small a, 150-300mmǾ 103(1)a STRUCTURE EXCAVATION (COMMON SOIL) 104(4) EARTH BERM 511(1) GABIONS 511(2) MATTRESSESDIPACULAO, AURORA5,000,000.00
COMPLETION OF MULTI-PURPOSE BUILDING BRGY. RAMADA   SPCL –I GENERAL REQUIREMENTS (PGA & COA SIGN BOARD, CONSTRUCTION AND SAFETY & HEALTH PROGRAM AND OTHER REQUIRED DOCUMENTS SPCL –II MOBILIZATION AND DEMOBILIZATION SPCL-III CHIPPING OF CONCRETE PAVEMENT 804(1)c EMBANKMENT FROM COMMON BORROW 1046(2)a1 100mm CHB NON-LOAD BEARING (INCLUDING REINFORCING STEAL) 900 REINFORCED CONCRETE 902(1)a1 REINFORING STEEL OF REINFORCED CONCRETE STRUCTURES, GRADE 40 903(2) FORMWORKS AND FALSEWORKS 1047(2)b STRUCTURAL STEEL PURLINS 1047(2)a STRUCTURAL STEEL, TRUSSES STRUTS 1047(6) METAL STRUCTURE ACCESSORIES (STEEL PLATES) 1047(7)b METAL STRUCTURE ACCESSORIES (SAGRODS) 1047(4) METAL STRUCTURE ACCESSORIES (CROSSBRACING) 1047(3)c METAL STRUCTURE ACCESSORIES (TURNBUCKLE) 1014(1)b1 PREPAINTED METAL SHEETS (PREPAINTED, LONG SPAN, 0.5MM THK) 1032(1)c PAINTING WORKS (METAL PAINTING) 1032(1)a PAINTING WORKS (MASONRY PAINTING) SPCL IV CONSTRUCTION OF BASKETBALL RING & BOARD W/ ACCESSORIES & FRAMES (2 SETS)MA. AURORA, AURORA2,500,000.00
COMPLETION OF MULTI-PURPOSE BUILDING BRGY. SAN JUAN   SPCL –I GENERAL REQUIREMENTS (PGA & COA SIGN BOARD, CONSTRUCTION AND SAFETY & HEALTH PROGRAM AND OTHER REQUIRED DOCUMENTS SPCL –II MOBILIZATION AND DEMOBILIZATION SPCL-III CHIPPING OF CONCRETE PAVEMENT 804(1)c EMBANKMENT FROM COMMON BORROW 1046(2)a1 100mm CHB NON-LOAD BEARING (INCLUDING REINFORCING STEAL) 900 REINFORCED CONCRETE 902(1)a1 REINFORING STEEL OF REINFORCED CONCRETE STRUCTURES, GRADE 40 903(2) FORMWORKS AND FALSEWORKS 1047(2)b STRUCTURAL STEEL PURLINS 1047(2)a STRUCTURAL STEEL, TRUSSES STRUTS 1047(6) METAL STRUCTURE ACCESSORIES (STEEL PLATES) 1047(7)b METAL STRUCTURE ACCESSORIES (SAGRODS) 1047(4) METAL STRUCTURE ACCESSORIES (CROSSBRACING) 1047(3)c METAL STRUCTURE ACCESSORIES (TURNBUCKLE) 1014(1)b1 PREPAINTED METAL SHEETS (PREPAINTED, LONG SPAN, 0.5MM THK) 1032(1)c PAINTING WORKS (METAL PAINTING) 1032(1)a PAINTING WORKS (MASONRY PAINTING) SPCL IV CONSTRUCTION OF BASKETBALL RING & BOARD W/ ACCESSORIES & FRAMES (2 SETS) SPCL V GUTTER AND DOWNSPOUT W/C FACIABOARDMA. AURORA, AURORA2,500,000.00
COMPLETION OF MULTI-PURPOSED BUILDING BRGY. DIOME SPCL –I GENERAL REQUIREMENTS (PGA & COA SIGN BOARD, CONSTRUCTION AND SAFETY & HEALTH PROGRAM AND OTHER REQUIRED DOCUMENTS SPCL –II MOBILIZATION AND DEMOBILIZATION SPCL-III CHIPPING OF CONCRETE PAVEMENT 804(1)c EMBANKMENT FROM COMMON BORROW 1046(2)a1 100mm CHB NON-LOAD BEARING (INCLUDING REINFORCING STEAL) 900 REINFORCED CONCRETE 902(1)a1 REINFORING STEEL OF REINFORCED CONCRETE STRUCTURES, GRADE 40 903(2) FORMWORKS AND FALSEWORKS 1047(2)b STRUCTURAL STEEL PURLINS 1047(2)a STRUCTURAL STEEL, TRUSSES STRUTS 1047(6) METAL STRUCTURE ACCESSORIES (STEEL PLATES) 1047(7)b METAL STRUCTURE ACCESSORIES (SAGRODS) 1047(4) METAL STRUCTURE ACCESSORIES (CROSSBRACING) 1047(3)c METAL STRUCTURE ACCESSORIES (TURNBUCKLE) 1014(1)b1 PREPAINTED METAL SHEETS (PREPAINTED, LONG SPAN, 0.5MM THK) 1032(1)c PAINTING WORKS (METAL PAINTING) 1032(1)a PAINTING WORKS (MASONRY PAINTING) SPCL IV CONSTRUCTION OF BASKETBALL RING & BOARD W/ ACCESSORIES & FRAMES (2 SETS)MA. AURORA, AURORA2,500,000.00
COMPLETION OF MULTI-PURPOSED BUILDING BRGY. MALASIN SPCL –I GENERAL REQUIREMENTS (PGA & COA SIGN BOARD, CONSTRUCTION AND SAFETY & HEALTH PROGRAM AND OTHER REQUIRED DOCUMENTS SPCL –II MOBILIZATION AND DEMOBILIZATION SPCL-III CHIPPING OF CONCRETE PAVEMENT 804(1)c EMBANKMENT FROM COMMON BORROW 1046(2)a1 100mm CHB NON-LOAD BEARING (INCLUDING REINFORCING STEAL) 900 REINFORCED CONCRETE 902(1)a1 REINFORING STEEL OF REINFORCED CONCRETE STRUCTURES, GRADE 40 903(2) FORMWORKS AND FALSEWORKS 1047(2)b STRUCTURAL STEEL PURLINS 1047(2)a STRUCTURAL STEEL, TRUSSES STRUTS 1047(6) METAL STRUCTURE ACCESSORIES (STEEL PLATES) 1047(7)b METAL STRUCTURE ACCESSORIES (SAGRODS) 1047(4) METAL STRUCTURE ACCESSORIES (CROSSBRACING) 1047(3)c METAL STRUCTURE ACCESSORIES (TURNBUCKLE) 1014(1)b1 PREPAINTED METAL SHEETS (PREPAINTED, LONG SPAN, 0.5MM THK) 1032(1)c PAINTING WORKS (METAL PAINTING) 1032(1)a PAINTING WORKS (MASONRY PAINTING) SPCL IV CONSTRUCTION OF BASKETBALL RING & BOARD W/ ACCESSORIES & FRAMES (2 SETS)MA. AURORA, AURORA2,500,000.00
CONSTRUCTION OF TWO-STOREY MULTI-PURPOSE BLDG. GENERAL REQUIREMENTS GENERAL REQUIREMENTS (MOB./DEMOB.,AND PGA SIGN BOARD AND OTHER REQUIRED DOCUMENTS)EARTHWORKS 803(1)a STRUCTURE EXCAVATION(COMMON SOIL) 804(4) GRAVEL BEDDING 804(4)1 EMBANKMENT SPCL ISOIL POISONING CONCRETE WORKS 900.0 REINFORCED CONCRETE 902(1)a1 REINFORCING STEEL OF REINFORCED CONCRETE STRUCTURES, GRADE 40 MASONRY WORKS 1046(2)a1 150mm CHB Non –Load Bearing (including Reinforcing Steel) 903(2) FORMWORKS AND FALSEWORKS PLASTERING 1027(1) CEMENT PLASTER FINISH DOORS (1-D1,2-D2, 2-D3) 1010(1) FRAMES (JAMBS, SILL, HEAD, TRANSOMS AND MULLIONS) 1004(2)G HINGES WINDOWS (GROUND FLOOR ONLY) 1005(1) UPVC CASEMENT WINDOW 1005(1)a UPVC AWNING –FIXED WINDOW WITH TRANSOM 1005(1)b UPVC AWNING YPE WINDOW IX CEILING WORKS (GROUND FLOOR ONLY) 1003(1) ¼ THK MARINE PLYWOOD ON METAL FRAME CEILING X ROOFRAMING WORKS 1047(2)b STRUCTURAL STEEL PURLINS INCLUDING C FASCIA BOARD 1047(2)a STRUCTURALL STEEL TRUSSES 1047(6) METAL STRUCTURE ACCESSORIES (STEEL PLATES) 1047(7)b METAL STRUCTURE ACCESSORIES (SAGRODS) XI TINSMITHRY WORKS 1014(1)b1 PREPAINTED METAL SHEETS (CORRUGATED, LONG SPAN, 0.5MM THK.) 1013(2)a FABRICATED METAL ROOFING ACCESSORY (RIDGE ROLL) 1013(2) c FABRICATED METAL ROOFING ACCESSORY (GUTTER) SPCL II DOWNSPOUT XII PAINTING WORKS 1032(1)c PAINTING WORKS (METAL PAINTING) 1001(6)b1 CATCH BASIN SPCL III SEPTIC VAULT 1001(6)b1 PLUMBING WORKS SANITARY   PIPE AND FITTINGS, WATER LINES XIII ELECTRICAL WORKS (ROUGH IN)BRGY. DIBARAYBAY, DINALUNGAN, AURORA2,500,000.00
TOTAL  

Prospective bidders should possess a valid PCAB License applicable to the contract, have completed a similar contract with a value of at least 50% of the ABC, and have key personnel and equipment available for the prosecution of the contract.  The BAC will use non-discretionary pass/fail criteria in the Eligibility Check/Screening as well as the Preliminary Examination of Bids.  The BAC will conduct post-qualification of the lowest calculated bid.

The pertinent provisions of RA 9184 and its Implementing Rules and Regulations (IRR) shall govern all particulars relative to Eligibility Statement and Screening, Bid Security, Performance Security, Pre-bidding Conference, Evaluation of Bids, Post Qualification and Award of Contract. The schedule of BAC activities is as follows:

ActivitiesSchedule
1.  Issuance of Bid DocumentsMARCH 9, 2021 – MARCH 29, 2021  until 9:00 AM
2.  Pre-bid ConferenceMARCH 17, 2021 @  10:00 AM
3.  Submission of Eligibility and BidsMARCH 29, 2021 until 9:00 AM
4.  Opening of BidsMARCH 29, 2021  @ 10:00 AM
  • Pre-Bid Conference/ Opening of Bids’ date is automatically re- scheduled to the next working day whenever such date is declared a holiday.

The BAC will issue to prospective bidders Eligibility Forms at BAC Secretariat Office, Capitol Compound, Baler, Aurora, upon their submission of a LOI.  Prospective bidders shall submit the Eligibility Requirements to the BAC at the said address.  They may also obtain the results of the Eligibility Check by the BAC at the same address. Bids document will be available only to prospective bidders upon payment to the Provincial Treasurer’s Office (PTO) of the Provincial Government of Aurora (PGA) of non-refundable amount for the following approved budget for the contract:

The Provincial Government of Aurora assumes no responsibility whatsoever to compensate or indemnify bidders for any expenses incurred in the preparation of the bid. Only those who have purchased the Bidding Documents shall be allowed to participate in the pre-bid conference and raise or submit written queries or clarifications.  The PGA also reserves the right to reject any or all bids, to declare the bidding a failure or waive any defect or informality and to accept bids as may be considered most advantageous to the PGA.


Negotiated Procurement – 2021

The PROVINCIAL GOVERNMENT OF AURORA, through its Bids and Awards Committee (BAC), invites all eligible suppliers/manufacturers/distributors/contractors to bid for the hereunder project:

Name Of ProjectLocationApproved Budget for the Contract
PROCUREMENT OF SPARE PARTS FOR FARM TRACTORSBALER, AURORA1,145,000.00
TOTAL  

Prospective bidders should have experience in undertaking a similar project within the last two (2) years with an amount of at least 50% of the proposed project for bidding. The Eligibility Check/Screening as well as the Preliminary Examination of Bids shall use non-discretionary “pass/fail” criteria.  Post-qualification of the lowest calculated bid shall be conducted.

All particulars relative to Eligibility Statement and Screening, Bid Security, Performance Security, Pre-bidding Conference, Evaluation of Bids, Post Qualification and Awards of Contract shall be governed by the pertinent provisions of RA 9184 and its Implementing Rules and Regulations (IRR).

The complete schedule of activities is listed, as follows:

ActivitiesSchedule
1.  Issuance of Bid DocumentsJanuary 6, 2021 – January 26, 2021  until 9:00 AM
2.  Pre-bid ConferenceJanuary 14, 2021 @  2:00 PM
3.  Submission of Eligibility and BidsJanuary 26, 2021 until 9:00 AM
4.  Opening of BidsJanuary 26, 2021  @ 10:00 AM
  • Pre-Bid Conference/ Opening of Bids’ date is automatically re- scheduled to the next working day whenever such date is declared a holiday.

The BAC will issue to prospective bidders Eligibility Forms upon payment to the Provincial Treasurer’s Office of the PGA of a non-refundable amount for the following approved budget for the contract.

The Provincial Government of Aurora assumes no responsibility whatsoever to compensate or indemnify bidders for any expenses incurred in the preparation of the bid. Only those who have purchased the Bidding Documents shall be allowed to participate in the pre-bid conference and raise or submit written queries or clarifications. The PGA also reserves the right to reject any or all bids, to declare the bidding a failure or waive any defect or informality and to accept bids as may be considered most advantageous to the PGA without thereby incurring any of the following: (a) liability whatsoever to offset expenses or losses the bidder may incur in the preparation of the bids and (b) obligation to inform the affected bidder/s of the grounds for the basis of BAC’s action.


Goods Batch 3 – 2021

The PROVINCIAL GOVERNMENT OF AURORA, through its Bids and Awards Committee (BAC), invites all eligible suppliers/manufacturers/distributors/contractors to bid for the hereunder project:

Name Of ProjectLocationApproved Budget for the Contract
PROCUREMENT OF OFFICE, IT, JANITORIAL AND OTHER SUPPLIESPGA, BALER, AURORA3,359,399.00
PROCUREMENT OF MEDICAL AND LABORATORY SUPPLIESAMH, BALER, AURORA1,731,366.60
PROCUREMENT OF FARM TRACTOR ACCESSORIESOPAG, BALER, AURORA1,135,000.00
PROCUREMENT OF IT EQUIPMENT AND ACCESSORIESPGA, BALER, AURORA1,080,500.00
PROCUREMENT OF FEMALE CATTLE (BRAHMAN GRADES) BATCH 2PVO, BALER, AURORA2,400,000.00
PROCUREMENT OF MEDICAL, DENTAL & LABORATORY SUPPLIES AND MATERIALSAMH,MACH PHO, AURORA7,351,564.00
PROCUREMENT OF FEMALE CATTLE (BRAHMAN GRADES)PVO, BALER, AURORA1,400,000.00
TOTAL  

Prospective bidders should have experience in undertaking a similar project within the last two (2) years with an amount of at least 50% of the proposed project for bidding. The Eligibility Check/Screening as well as the Preliminary Examination of Bids shall use non-discretionary “pass/fail” criteria.  Post-qualification of the lowest calculated bid shall be conducted.

All particulars relative to Eligibility Statement and Screening, Bid Security, Performance Security, Pre-bidding Conference, Evaluation of Bids, Post Qualification and Awards of Contract shall be governed by the pertinent provisions of RA 9184 and its Implementing Rules and Regulations (IRR).

The complete schedule of activities is listed, as follows:

ActivitiesSchedule
1.  Issuance of Bid DocumentsMARCH 9, 2021 – MARCH 29, 2021  until 9:00 AM
2.  Pre-bid ConferenceMARCH 17, 2021 @  10:00 AM
3.  Submission of Eligibility and BidsMARCH 29, 2021 until 9:00 AM
4.  Opening of BidsMARCH 29, 2021  @ 10:00 AM
  • Pre-Bid Conference/ Opening of Bids’ date is automatically re- scheduled to the next working day whenever such date is declared a holiday.

The BAC will issue to prospective bidders Eligibility Forms upon payment to the Provincial Treasurer’s Office of the PGA of a non-refundable amount for the following approved budget for the contract.

The Provincial Government of Aurora assumes no responsibility whatsoever to compensate or indemnify bidders for any expenses incurred in the preparation of the bid. Only those who have purchased the Bidding Documents shall be allowed to participate in the pre-bid conference and raise or submit written queries or clarifications. The PGA also reserves the right to reject any or all bids, to declare the bidding a failure or waive any defect or informality and to accept bids as may be considered most advantageous to the PGA without thereby incurring any of the following: (a) liability whatsoever to offset expenses or losses the bidder may incur in the preparation of the bids and (b) obligation to inform the affected bidder/s of the grounds for the basis of BAC’s action.


Infrastructure Project Batch 6 – 2021

The PROVINCIAL GOVERNMENT OF AURORA, through its Bids and Awards Committee (BAC), invites all eligible contractors registered with and classified by the Philippine Contractors Accreditation Board (PCAB), to bid for the hereunder contract:

Name Of ProjectLocationApproved Budget for the Contract
COMPLETION OF MULTI-PURPOSE BUILDING, BRGY. ESPERANZA SPCL –I GENERAL REQUIREMENTS (Mobilization & Demobilization, PGA & COA, Sign Board, Construction Safety & Health Program and other Required Documents) 704.3 Concrete Masonry Blocks 900 Reinforced Concrete 902(1)a1 Reinforcing Steel of Reinforced Concrete structures, Grade 40 903(2) Formworks and falseworks 1047(2)b structural steel purlins 1047(2)a Structural steel, trusses, strut 1047(6) Metal structures Accessories (steel Plates) 1047(7)b Metal structures Accessories (sagrods) 1047(4) Metal structures Accessories (crossbracing) 1047(3)c Metal structures Accessories (Turnbuckle) 1014(1)b1 Prepainted Metal Sheets (Corrugated, Long Span 0.5mm thk) 1032(1)c Painting Works (Metal Pinting) SPCL III Basketball Ring & Board w/ Accessories & FramesDILASAG, AURORA2,500,000.00
COMPLETION OF MULTI-PURPOSED BUILDING BRGY. GALINTUJA SPCL –I GENERAL REQUIREMENTS (PGA & COA SIGN BOARD, CONSTRUCTION AND SAFETY & HEALTH PROGRAM AND OTHER REQUIRED DOCUMENTS SPCL –II MOBILIZATION AND DEMOBILIZATION SPCL-III CHIPPING OF CONCRETE PAVEMENT 804(1)c EMBANKMENT FROM COMMON BORROW 1046(2)a1 100mm CHB NON-LOAD BEARING (INCLUDING REINFORCING STEAL) 900 REINFORCED CONCRETE 902(1)a1 REINFORING STEEL OF REINFORCED CONCRETE STRUCTURES, GRADE 40 903(2) FORMWORKS AND FALSEWORKS 1047(2)b STRUCTURAL STEEL PURLINS 1047(2)a STRUCTURAL STEEL, TRUSSES STRUTS 1047(6) METAL STRUCTURE ACCESSORIES (STEEL PLATES) 1047(7)b METAL STRUCTURE ACCESSORIES (SAGRODS) 1047(4) METAL STRUCTURE ACCESSORIES (CROSSBRACING) 1047(3)c METAL STRUCTURE ACCESSORIES (TURNBUCKLE) 1014(1)b1 PREPAINTED METAL SHEETS (PREPAINTED, LONG SPAN, 0.5MM THK) 1032(1)c PAINTING WORKS (METAL PAINTING) 1032(1)a PAINTING WORKS (MASONRY PAINTING) SPCL IV CONSTRUCTION OF BASKETBALL RING & BOARD W/ ACCESSORIES & FRAMES (2 SETS) SPCL V Gutter and Downspout w/ C Fascia BoardMA. AURORA, AURORA2,500,000.00
COMPLETION OF MULTI-PURPOSE BUILDING BRGY. BANGCO SPCL –I GENERAL REQUIREMENTS (PGA & COA SIGN BOARD, CONSTRUCTION AND SAFETY & HEALTH PROGRAM AND OTHER REQUIRED DOCUMENTS) SPCL II MOBILIZATION AND DEMOBILIZATION 804(1)c EMBANKMENT FROM COMMON BORROW 1046(2)a1 100mm CHB NON-LOAD BEARING (INCLUDING REINFORCING STEAL) 900 REINFORCED CONCRETE 902(1)a1 REINFORING STEEL OF REINFORCED CONCRETE STRUCTURES, GRADE 40 903(2) FORMWORKS AND FALSEWORKS 1047(2)b STRUCTURAL STEEL PURLINS 1047(2)a STRUCTURAL STEEL, TRUSSES STRUTS 1047(6) METAL STRUCTURE ACCESSORIES (STEEL PLATES) 1047(7)b METAL STRUCTURE ACCESSORIES (SAGRODS) 1047(4) METAL STRUCTURE ACCESSORIES (CROSSBRACING) 1047(3)c METAL STRUCTURE ACCESSORIES (TURNBUCKLE) 1014(1)b1 PREPAINTED METAL SHEETS (PREPAINTED, LONG SPAN, 0.5MM THK) 1032(1)c PAINTING WORKS (METAL PAINTING) 1032(1)a PAINTING WORKS (MASONRY PAINTING) SPCL III Construction of BASKETBALL RING & BOARD W/ ACCESSORIES & FRAMES (2sets)MA. AURORA, AURORA2,500,000.00
CONSTRUCTION OF DRAINAGE CANAL AT BRGY. SITE PROPER, BRGY. DICABASAN SPCL I General Requirements I.1 MOBILIZATION AND DEMOBILIZATION I.2 Setting out and staking I.3 CONSTRUCTION AND SAFETY & HEALTH PROGRAM I.4 Project Sign board I.5 Project Sign board COA SPCL II Demolition of Existing Canal SPCL III Repair of Existing Canal SPCL IV Relocation of Electrical Post 103(1)a Structure Excavation (Common Soil) 404 Reinforcing steel bar, Grade 40 (minor structures) 405 Structural Concrete Class A Minor (minor structures)DILASAG, AURORA2,000,000.00
COMPLETION OF MULTI-PURPOSED BUILDING BRGY. LAWANG SPCL –I GENERAL REQUIREMENTS (PGA & COA SIGN BOARD, CONSTRUCTION AND SAFETY & HEALTH PROGRAM AND OTHER REQUIRED DOCUMENTS) 803(1)a STRUCTURE EXCAVATION (COMMON SOIL)\ 804 GRAVEL BEDDING 900 REINFORCED CONCRETE 902(1)a1 REINFORING STEEL OF REINFORCED CONCRETE STRUCTURES, GRADE 40 903(2) FORMWORKS AND FALSEWORKS 1027(1) CEMENT PLASTER FINISH 1047(2)b STRUCTURAL STEEL PURLINS 1047(2)a STRUCTURAL STEEL, TRUSSES STRUTS 1047(6) METAL STRUCTURE ACCESSORIES (STEEL PLATES) 1047(7)b METAL STRUCTURE ACCESSORIES (SAGRODS) 1047(4) METAL STRUCTURE ACCESSORIES (CROSSBRACING) 1047(3)c METAL STRUCTURE ACCESSORIES (TURNBUCKLE) 1014(1)b1 PREPAINTED METAL SHEETS (PREPAINTED, LONG SPAN, 0.5MM THK) 1032(1)c PAINTING WORKS (METAL PAINTING)DILASAG, AURORA2,500,000.00
COMPLETION OF MULTI-PURPOSE BUILDING, BRGY. REAL I GENERAL REQUIREMENTS II CHIPPING OF EXISTING PAVEMENT 900(a) REINFORCED CONCRETE (14M X 30M X0.10M PAVEMENT) 902(1)a1 REINFORING STEEL OF REINFORCED CONCRETE STRUCTURES, GRADE 40 903(2) FORMWORKS AND FALSEWORKS 1047(2)b STRUCTURAL STEEL PURLINS 1047(2)a STRUCTURAL STEEL, TRUSSES 1047(6) METAL STRUCTURE ACCESSORIES (STEEL PLATES) 1047(7)b METAL STRUCTURE ACCESSORIES (SAGRODS) 1047(4) METAL STRUCTURE ACCESSORIES (CROSSBRACING) 1047(3)c METAL STRUCTURE ACCESSORIES (TURNBUCKLE) 1014(1)b1 PREPAINTED METAL SHEETS (PREPAINTED, LONG SPAN, 0.5MM THK) 1032(1)c PAINTING WORKS (METAL PAINTING) SPCL III Basketball Ring & Board w/ Accessories & FramesSAN LUIS, AURORA1,000,000.00
FLOOD CONTROL PROJECT PART B GENERAL REQUIREMENTS B.5a Project Billboard/Signboard (PGA) B.5b Project Signboard (COA) B.7 Occupational Safety and Health Program B.9 Mobilization/Demobilization PART J FLOOD CONTROL AND DRAINAGE PART I-A EARTHWORK 1702 Structure Excavation 1704(1)b Embankment from Borrow PART I-B BANK AND SLOPE PROTECTION WORKS 404 Reinforcing Steel Bars G40 405 Structural Concrete Class A 1714(a) GabionsBRGY. 1, CASIGURAN, AURORA3,000,000.00
TOTAL  

Prospective bidders should possess a valid PCAB License applicable to the contract, have completed a similar contract with a value of at least 50% of the ABC, and have key personnel and equipment available for the prosecution of the contract.  The BAC will use non-discretionary pass/fail criteria in the Eligibility Check/Screening as well as the Preliminary Examination of Bids.  The BAC will conduct post-qualification of the lowest calculated bid.

The pertinent provisions of RA 9184 and its Implementing Rules and Regulations (IRR) shall govern all particulars relative to Eligibility Statement and Screening, Bid Security, Performance Security, Pre-bidding Conference, Evaluation of Bids, Post Qualification and Award of Contract. The schedule of BAC activities is as follows:

ActivitiesSchedule
1.  Issuance of Bid DocumentsMARCH 12, 2021 – MARCH 31, 2021  until 9:00 AM
2.  Pre-bid ConferenceMARCH 19, 2021 @  10:00 AM
3.  Submission of Eligibility and BidsMARCH 31, 2021 until 9:00 AM
4.  Opening of BidsMARCH 31, 2021  @ 10:00 AM
  • Pre-Bid Conference/ Opening of Bids’ date is automatically re- scheduled to the next working day whenever such date is declared a holiday.

The BAC will issue to prospective bidders Eligibility Forms at BAC Secretariat Office, Capitol Compound, Baler, Aurora, upon their submission of a LOI.  Prospective bidders shall submit the Eligibility Requirements to the BAC at the said address.  They may also obtain the results of the Eligibility Check by the BAC at the same address. Bids document will be available only to prospective bidders upon payment to the Provincial Treasurer’s Office (PTO) of the Provincial Government of Aurora (PGA) of non-refundable amount for the following approved budget for the contract:

The Provincial Government of Aurora assumes no responsibility whatsoever to compensate or indemnify bidders for any expenses incurred in the preparation of the bid. Only those who have purchased the Bidding Documents shall be allowed to participate in the pre-bid conference and raise or submit written queries or clarifications.  The PGA also reserves the right to reject any or all bids, to declare the bidding a failure or waive any defect or informality and to accept bids as may be considered most advantageous to the PGA.


Goods Batch 4 – 2021

The PROVINCIAL GOVERNMENT OF AURORA, through its Bids and Awards Committee (BAC), invites all eligible suppliers/manufacturers/distributors/contractors to bid for the hereunder project:

Name Of ProjectLocationApproved Budget for the Contract
PROCUREMENT OF FOOD SUPPLIES FOR THE PREPOSITIONING OF RELIEF GOODS FOR DISASTER OPERATIONBALER, AURORA1,403,000.00
PROCUREMENT OF VARIOUS VARIETIES OF CORN SEEDSBALER, AURORA836,879.00
TOTAL  

Prospective bidders should have experience in undertaking a similar project within the last two (2) years with an amount of at least 50% of the proposed project for bidding. The Eligibility Check/Screening as well as the Preliminary Examination of Bids shall use non-discretionary “pass/fail” criteria.  Post-qualification of the lowest calculated bid shall be conducted.

All particulars relative to Eligibility Statement and Screening, Bid Security, Performance Security, Pre-bidding Conference, Evaluation of Bids, Post Qualification and Awards of Contract shall be governed by the pertinent provisions of RA 9184 and its Implementing Rules and Regulations (IRR). The complete schedule of activities is listed, as follows:

ActivitiesSchedule
1.  Issuance of Bid DocumentsMARCH 12, 2021 – MARCH 31, 2021  until 9:00 AM
2.  Pre-bid ConferenceMARCH 19, 2021 @  10:00 AM
3.  Submission of Eligibility and BidsMARCH 31, 2021 until 9:00 AM
4.  Opening of BidsMARCH 31, 2021  @ 10:00 AM
  • Pre-Bid Conference/ Opening of Bids’ date is automatically re- scheduled to the next working day whenever such date is declared a holiday.

The BAC will issue to prospective bidders Eligibility Forms upon payment to the Provincial Treasurer’s Office of the PGA of a non-refundable amount for the following approved budget for the contract.

The Provincial Government of Aurora assumes no responsibility whatsoever to compensate or indemnify bidders for any expenses incurred in the preparation of the bid. Only those who have purchased the Bidding Documents shall be allowed to participate in the pre-bid conference and raise or submit written queries or clarifications. The PGA also reserves the right to reject any or all bids, to declare the bidding a failure or waive any defect or informality and to accept bids as may be considered most advantageous to the PGA without thereby incurring any of the following: (a) liability whatsoever to offset expenses or losses the bidder may incur in the preparation of the bids and (b) obligation to inform the affected bidder/s of the grounds for the basis of BAC’s action.


Infrastructure Project Batch 7 – 2021

The PROVINCIAL GOVERNMENT OF AURORA, through its Bids and Awards Committee (BAC), invites all eligible contractors registered with and classified by the Philippine Contractors Accreditation Board (PCAB), to bid for the hereunder contract:

Name Of ProjectLocationApproved Budget for the Contract
CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. DIBUT I General Requirements II Transhipment of Materials (Double Handling) III Removal of Existing Basketball Ring and Chipping of Existing Pavement 900(a) Reinforced Concrete (15mx 30m Pavement) 902(1)a1 Reinforcing Steel of Reinforced Concrete structures, Grade 40 903(2) Formworks and false works 1047(2)b structural steel purlins 1047(2)a Structural steel, trusses 1047(6) Metal structures Accessories (steel Plates) 1047(7)b Metal structures Accessories (sagrods) 1047(4) Metal structures Accessories (crossbracing) 1047(3)c Metal structures Accessories (Turnbuckle) 1014(1)b1 Prepainted Metal Sheets (Corrugated, Long Span 0.5mm thk) 1032(1)c Painting Works (Metal Pinting) 1032(1)a Painting Works (Masonry Painting) IV Electrical Works V Construction of Basketball Ring Fabrication and Installation of Fiber Glass w/ Ring & ¼” thk. 50mm x50mm Angular Bar (Frame, Hanger, Stud) Standard board Dimension SPCL VI Relocation of Electrical Post  SAN LUIS, AURORA1,300,000.00
COMPLETION OF MULTI-PURPOSE BUILDING BRGY. DIBACONG SPCL I General Requirements (Mob. /Demob., Const. Health & Safety Requirements, Layout & Excavation incl. Breakage of Existing Pavement) 903(2) Formworks and False works 1027(1) Cement Plaster Finish (for slab) 1032 Painting Works (concrete surfaces including basketball Goal) 1032(1)c Painting Works (Metal Painting) SPCL II Electrical Works SPCL III Basketball Ring & Board w/ Accessories & FramesCASIGURAN, AURORA700,000.00
COMPLETION OF MULTI-PURPOSE BUILDING BRGY. DIMABUNO General requirements SPCL I Mobilization and demobilization SPCL II Construction of Safety And Health SPCL III Project Sign Board (PGA) SPCL IV Project Sign Board (COA) SPCL V Board and Ring (3/4 THK. Fiber Glass) 104(1)a Embankment (from borrow ) 101(3) a.1 Removal of Existing Concrete Pavement (0.20m thk.) 900 Reinforced Concrete 1047(2)a Structural Steel, Trusses Struts 1014(1)b1 Prepainted Metal Sheets (Prepainted, Long Span, 0.5mm Thk) 1032(1)c Painting Works ( inc. All Metals, Roof and Concrete) 1013(2)c Fabricated Metal Roofing Accessory (Gutter) III Electrical Works (Including Scoreboard)DIPACULAO, AURORA2,000,000.00
COMPLETION OF MULTI-PURPOSE BUILDING BRGY. UMIRAY I GENERAL REQUIREMENTS 903(2) Formworks and Falseworks 1047(2)b Structural Steel Purlins 1047(2)a Structural Steel, Trusses 1047(6) Metal Structure Accessories (Steel Plates) 1047(7)b Metal Structure Accessories (Sagrods) 1047(4) Metal Structure Accessories (Crossbracing) 1047(3)c Metal Structure Accessories (Turnbuckle) 1014(1)b1 Prepainted Metal Sheets (Prepainted, Long Span, 0.5mm Thk) 1032(1)c Painting Works (Metal Painting) II Construction of Basketball Ring Fabrication and Installation of Fiber Glass w/ Ring & ¼” thk. 50mm x50mm Angular Bar (Frame, Hanger, Stud) Standard board Dimension III Electrical WorksDINGALAN, AURORA1,000,000.00
COMPLETION OF MULTI-PURPOSED BUILDING, BRGY. SAN LEONARDO SPCL –I GENERAL REQUIREMENTS (Mobilization & Demobilization, PGA & COA, Sign Board, Construction Safety & Health Program and other Required Documents) SPCL II Mobilization and Demobilization SPCL III Chipping of Concrete Pavement 804(1)c Embankment from Common Borrow 1046(2)a 100mm CHB Non –Load Bearing (Including Reinforcing Steel) 900 Reinforced Concrete 902(1)a1 Reinforcing Steel Of Reinforced Concrete Structures, Grade 40 903(2) Formworks and Falseworks 1047(2)b Structural Steel Purlins 1047(2)a Structural Steel, Trusses 1047(6) Metal Structure Accessories (Steel Plates) 1047(7)b Metal Structure Accessories (Sagrods) 1047(4) Metal Structure Accessories (Crossbracing) 1047(3)c Metal Structure Accessories (Turnbuckle) 1014(1)b1 Prepainted Metal Sheets (Prepainted, Long Span, 0.5mm Thk) 1032(1)c Painting Works (Metal Painting) 1032(1)a Painting Works (Masonry Painting) SPCL IV Construction of Basketball Ring & Board w/ Accessories & Frames (2sets) SPCL V Flashing Gutter and Downspout w/ Fascia Board  MARIA AURORA, AURORA2,500,000.00
REPLACEMENT OF DIMALANG BRIDGE (12m) Sta. Ko. 353+096 TO Ko. 353+104.5, CASIGURAN-DILASAG PROVINCIAL ROAD PART A TEMPORARY FACILITIES A.1.1(8)  PROVISION OF THE FIELD OFFICE FOR THE ENGINEER (RENTAL BASIS) PART B OTHER GENERAL REQUIREMENTS B.5.a  PROJECT SIGN BOARD (PGA) B.5.b  PROJECT SIGN BOARD (COA BILLBOARD) B.7(1) OCCUPATIONAL SAFETY & HEALTH PROGRAM B.8(1) TRAFFIC MANAGEMENT B.9     MOBILIZATION/DEMOBILIZATION PART C         EARTHWORKS 100(1) CLEARING & GRUBBING (APPROACHES) 102(1) ROADWAY EXCAVATION (UNSUITABLE) 103(1)a STRUCTURE EXCAVATION 104(2) EMBANKMENT (BORROW), COMPACTED VOLUME PART D         BRIDGE CONSTRUCTION 400(17)C CONCRETE PILE CAST IN DRILLEDD HOLES 400(23)C1 STEEL CASING (1.8m Ө) 400(26)b PILE INTEGRITY TESTING (Ordinary Soil Cond.) 400(27) HIGH STRAIN DYNAMIC TESTING (PDA) 410(2)A CONCRETE RAILING (STANDARD) 403(4) STRUCTURAL STEEL, FURNISHED & FABRICATED (Bored Pile) 404(3)a.1 REINFORCING STEEL BARS (DECK SLAB) 404(3)a.2 REINFORCING STEEL BARS (GIRDER) 405(1)B2 STRUCTURAL CONCRETE CLASS 14 DAYS, fc = 27.60 Mpa 405(1)B3 STRUCTURAL CONCRETE CLASS 28 DAYS, fc = 27.60 Mpa (Deck Slab) 406(1)F8 PRESTRESSED STRUCTURAL CONCRETE, MEMBERS (TYPE III, L = 12.0m) 411(2) PAINTING WORKS, Guardrail 412(1) ELASTOMERIC PAD 413(4)B EXPANSION JOINT 414(1) FORMS & SCAFFOLDINGS 729(1) PROTECTIVE COATING FOR CONCRETE, (Water Proofing for Deck Slab) PART E         SURFACE COARSES/ASPHALT OVERLAY 302(2) EMULSIFIED ASPHALT 310(1)A3 BITUMINOUS CONCRETE SURFACE, WEARING COARSE, HOT LAID (50mm) PART F         MISCELLANEOUS STRUCTURES 612(1)a Reflectorized Thermoplastic Pavement MARKING (White) 612(1)b Reflectorized Thermoplastic Pavement MARKING (Yellow) PART G         ROADWAY 104(2) EMBANKMENT 105(1) SUBGRADE PREPARATION (COMMON MATERIAL) 200    AGGREGATE SUBBASE COURSE 201    AGGREGATE BASE COURSE 311(1)a.3 PORTLAND CEMENT CONCRETE PAVEMENT (UNREINFORCED), 230mm thk. – 14 PART H DRAINAGE & SLOPE PROTECTION (BRIDGE, CREEK, PCCP W/ CONCRETE BARRIER) 505(5) GROUTED RIPRAP (CLASS A) 510(2) CONCRETE SLOPE PROTECTIONCASIGURAN, AURORA15,000,000.00
TOTAL  

Prospective bidders should possess a valid PCAB License applicable to the contract, have completed a similar contract with a value of at least 50% of the ABC, and have key personnel and equipment available for the prosecution of the contract.  The BAC will use non-discretionary pass/fail criteria in the Eligibility Check/Screening as well as the Preliminary Examination of Bids.  The BAC will conduct post-qualification of the lowest calculated bid.

The pertinent provisions of RA 9184 and its Implementing Rules and Regulations (IRR) shall govern all particulars relative to Eligibility Statement and Screening, Bid Security, Performance Security, Pre-bidding Conference, Evaluation of Bids, Post Qualification and Award of Contract.

The schedule of BAC activities is as follows:

ActivitiesSchedule
1.  Issuance of Bid DocumentsMARCH 24, 2021 – APRIL 12, 2021  until 9:00 AM
2.  Pre-bid ConferenceMARCH 31, 2021 @  10:00 AM
3.  Submission of Eligibility and BidsAPRIL 12, 2021  until 9:00 AM
4.  Opening of BidsAPRIL 12, 2021  @ 10:00 AM
  • Pre-Bid Conference/ Opening of Bids’ date is automatically re- scheduled to the next working day whenever such date is declared a holiday.

The BAC will issue to prospective bidders Eligibility Forms at BAC Secretariat Office, Capitol Compound, Baler, Aurora, upon their submission of a LOI.  Prospective bidders shall submit the Eligibility Requirements to the BAC at the said address.  They may also obtain the results of the Eligibility Check by the BAC at the same address. Bids document will be available only to prospective bidders upon payment to the Provincial Treasurer’s Office (PTO) of the Provincial Government of Aurora (PGA) of non-refundable amount for the following approved budget for the contract:

The Provincial Government of Aurora assumes no responsibility whatsoever to compensate or indemnify bidders for any expenses incurred in the preparation of the bid. Only those who have purchased the Bidding Documents shall be allowed to participate in the pre-bid conference and raise or submit written queries or clarifications.  The PGA also reserves the right to reject any or all bids, to declare the bidding a failure or waive any defect or informality and to accept bids as may be considered most advantageous to the PGA.


Infrastructure Project Batch 8 – 2021

The PROVINCIAL GOVERNMENT OF AURORA, through its Bids and Awards Committee (BAC), invites all eligible contractors registered with and classified by the Philippine Contractors Accreditation Board (PCAB), to bid for the hereunder contract:

Name Of ProjectLocationApproved Budget for the Contract
COMPLETION OF MULTI-PURPOSED BUILDING BRGY. DIKILDIT SPCL –I GENERAL REQUIREMENTS (PGA & COA SIGN BOARD, CONSTRUCTION AND SAFETY & HEALTH PROGRAM AND OTHER REQUIRED DOCUMENTS SPCL –II MOBILIZATION AND DEMOBILIZATION SPCL-III CHIPPING OF CONCRETE PAVEMENT 804(1)c EMBANKMENT FROM COMMON BORROW 1046(2)a1 100mm CHB NON-LOAD BEARING (INCLUDING REINFORCING STEAL) 900 REINFORCED CONCRETE 902(1)a1 REINFORING STEEL OF REINFORCED CONCRETE STRUCTURES, GRADE 40 903(2) FORMWORKS AND FALSEWORKS 1047(2)b STRUCTURAL STEEL PURLINS 1047(2)a STRUCTURAL STEEL, TRUSSES STRUTS 1047(6) METAL STRUCTURE ACCESSORIES (STEEL PLATES) 1047(7)b METAL STRUCTURE ACCESSORIES (SAGRODS) 1047(4) METAL STRUCTURE ACCESSORIES (CROSSBRACING) 1047(3) METAL STRUCTURE ACCESSORIES (TURNBUCKLE) 1014(1)b1 PREPAINTED METAL SHEETS (PREPAINTED, LONG SPAN, 0.5MM THK) 1032(1)c PAINTING WORKS (METAL PAINTING) 1032(1)a PAINTING WORKS (MASONRY PAINTING) SPCL IV CONSTRUCTION OF BASKETBALL RING & BOARD W/ ACCESSORIES & FRAMES (2 SETS)MA. AURORA, AURORA2,500,000.00
COMPLETION OF MULTI-PURPOSE BUILDING BRGY. DIMASESET SPCL –I GENERAL REQUIREMENTS (PGA & COA SIGN BOARD, CONSTRUCTION AND SAFETY & HEALTH PROGRAM AND OTHER REQUIRED DOCUMENTS 704.3 CONCRETE MASONRY BLOCKS 900 REINFORCED CONCRETE 902(1)a1 REINFORING STEEL OF REINFORCED CONCRETE STRUCTURES, GRADE 40 903(2) FORMWORKS AND FALSEWORKS 1047(2)b STRUCTURAL STEEL PURLINS 1047(2)a STRUCTURAL STEEL, TRUSSES STRUTS 1047(6) METAL STRUCTURE ACCESSORIES (STEEL PLATES) 1047(7)b METAL STRUCTURE ACCESSORIES (SAGRODS) 1047(4) METAL STRUCTURE ACCESSORIES (CROSSBRACING) 1047(3)c METAL STRUCTURE ACCESSORIES (TURNBUCKLE) 1014(1)b1 PREPAINTED METAL SHEETS (PREPAINTED, LONG SPAN, 0.5MM THK) 1032(1)c PAINTING WORKS (METAL PAINTING) SPCL III BASKETBALL RING & BOARD W/ ACCESSORIES & FRAMESDILASAG, AURORA2,500,000.00
COMPLETION OF MULTI-PURPOSED BUILDING BRGY. DICOLIAT SPCL –I GENERAL REQUIREMENTS (PGA & COA SIGN BOARD, CONSTRUCTION AND SAFETY & HEALTH PROGRAM AND OTHER REQUIRED DOCUMENTS SPCL –II MOBILIZATION AND DEMOBILIZATION SPCL-III CHIPPING OF CONCRETE PAVEMENT 804(1)c EMBANKMENT FROM COMMON BORROW 1046(2)a1 100mm CHB NON-LOAD BEARING (INCLUDING REINFORCING STEAL) 900 REINFORCED CONCRETE 902(1)a1 REINFORING STEEL OF REINFORCED CONCRETE STRUCTURES, GRADE 40 903(2) FORMWORKS AND FALSEWORKS 1047(2)b STRUCTURAL STEEL PURLINS 1047(2)a STRUCTURAL STEEL, TRUSSES STRUTS 1047(6) METAL STRUCTURE ACCESSORIES (STEEL PLATES) 1047(7)b METAL STRUCTURE ACCESSORIES (SAGRODS) 1047(4) METAL STRUCTURE ACCESSORIES (CROSSBRACING) 1047(3)c METAL STRUCTURE ACCESSORIES (TURNBUCKLE) 1014(1)b1 PREPAINTED METAL SHEETS (PREPAINTED, LONG SPAN, 0.5MM THK) 1032(1)c PAINTING WORKS (METAL PAINTING) 1032(1)a PAINTING WORKS (MASONRY PAINTING) SPCL IV CONSTRUCTION OF BASKETBALL RING & BOARD W/ ACCESSORIES & FRAMES (2 SETS)MA. AURORA, AURORA2,500,000.00
COMPLETION OF MULTI-PURPOSED BUILDING BRGY. SUGUIT SPCL –I GENERAL REQUIREMENTS (PGA & COA SIGN BOARD, CONSTRUCTION AND SAFETY & HEALTH PROGRAM AND OTHER REQUIRED DOCUMENTS SPCL –II MOBILIZATION AND DEMOBILIZATION SPCL-III CHIPPING OF CONCRETE PAVEMENT 804(1)c EMBANKMENT FROM COMMON BORROW 1046(2)a1 100mm CHB NON-LOAD BEARING (INCLUDING REINFORCING STEAL) 900 REINFORCED CONCRETE 902(1)a1 REINFORING STEEL OF REINFORCED CONCRETE STRUCTURES, GRADE 40 903(2) FORMWORKS AND FALSEWORKS 1047(2)b STRUCTURAL STEEL PURLINS 1047(2)a STRUCTURAL STEEL, TRUSSES STRUTS 1047(6) METAL STRUCTURE ACCESSORIES (STEEL PLATES) 1047(7)b METAL STRUCTURE ACCESSORIES (SAGRODS) 1047(4) METAL STRUCTURE ACCESSORIES (CROSSBRACING) 1047(3)c METAL STRUCTURE ACCESSORIES (TURNBUCKLE) 1014(1)b1 PREPAINTED METAL SHEETS (PREPAINTED, LONG SPAN, 0.5MM THK) 1032(1)c PAINTING WORKS (METAL PAINTING) 1032(1)a PAINTING WORKS (MASONRY PAINTING) SPCL IV CONSTRUCTION OF BASKETBALL RING & BOARD W/ ACCESSORIES & FRAMES (2 SETS)MA. AURORA, AURORA2,500,000.00
CONSTRUCTION OF TWO-STOREY MULTI-PURPOSE BLDG. GENERAL REQUIREMENTS GENERAL REQUIREMENTS (MOB./DEMOB.,AND PGA SIGN BOARD AND OTHER REQUIRED DOCUMENTS)EARTHWORKS 803(1)a STRUCTURE EXCAVATION (COMMON SOIL) 804(4) GRAVEL BEDDING 804(4)1 EMBANKMENT SPCL ISOIL POISONING CONCRETE WORKS 900.0 REINFORCED CONCRETE 902(1)a1 REINFORCING STEEL OF REINFORCED CONCRETE STRUCTURES, GRADE 40 MASONRY WORKS 1046(2)a1 150mm CHB Non –Load Bearing (including Reinforcing Steel) 903(2) FORMWORKS AND FALSEWORKS PLASTERING 1027(1) CEMENT PLASTER FINISH DOORS (1-D1,2-D2, 2-D3) 1010(1) FRAMES (JAMBS, SILL, HEAD, TRANSOMS AND MULLIONS) 1004(2)G HINGES WINDOWS (GROUND FLOOR ONLY) 1005(1) UPVC CASEMENT WINDOW 1005(1)a UPVC AWNING –FIXED WINDOW WITH TRANSOM 1005(1)b UPVC AWNING YPE WINDOW IX CEILING WORKS (GROUND FLOOR ONLY) 1003(1) ¼ THK MARINE PLYWOOD ON METAL FRAME CEILING X ROOFRAMING WORKS 1047(2)b STRUCTURAL STEEL PURLINS INCLUDING C FASCIA BOARD 1047(2)a STRUCTURALL STEEL TRUSSES 1047(6) METAL STRUCTURE ACCESSORIES (STEEL PLATES) 1047(7)b METAL STRUCTURE ACCESSORIES (SAGRODS) XI TINSMITHRY WORKS 1014(1)b1 PREPAINTED METAL SHEETS (CORRUGATED, LONG SPAN, 0.5MM THK.) 1013(2)a FABRICATED METAL ROOFING ACCESSORY (RIDGE ROLL) 1013(2) c FABRICATED METAL ROOFING ACCESSORY (GUTTER) SPCL II DOWNSPOUT XII PAINTING WORKS 1032(1)c PAINTING WORKS (METAL PAINTING) 1001(6)b1 CATCH BASIN SPCL III SEPTIC VAULT 1001(6)b1 PLUMBING WORKS SANITARY   PIPE AND FITTINGS, WATER LINES XIII ELECTRICAL WORKS (ROUGH IN)BRGY. DIBARAYBAY, DINALUNGAN, AURORA2,500,000.00
FLOOD CONTROL PROJECT
PART B GENERAL REQUIREMENTS
B.5a Project Billboard/Signboard (PGA)
B.5b Project Signboard (COA)
B.7 Occupational Safety and Health Program
B.9 Mobilization/Demobilization
PART J FLOOD CONTROL AND DRAINAGE
PART I-A EARTHWORK
1702 Structure Excavation
1704(1)b Embankment from Borrow
PART I-B BANK AND SLOPE PROTECTION WORKS
404 Reinforcing Steel Bars G40
405 Structural Concrete Class A
1714(a) Gabions
BRGY. 1,
CASIGURAN,
AURORA
3,000,000.00
TOTAL  

Prospective bidders should possess a valid PCAB License applicable to the contract, have completed a similar contract with a value of at least 50% of the ABC, and have key personnel and equipment available for the prosecution of the contract.  The BAC will use non-discretionary pass/fail criteria in the Eligibility Check/Screening as well as the Preliminary Examination of Bids.  The BAC will conduct post-qualification of the lowest calculated bid.

The pertinent provisions of RA 9184 and its Implementing Rules and Regulations (IRR) shall govern all particulars relative to Eligibility Statement and Screening, Bid Security, Performance Security, Pre-bidding Conference, Evaluation of Bids, Post Qualification and Award of Contract.

The schedule of BAC activities is as follows:

ActivitiesSchedule
1.  Issuance of Bid DocumentsAPRIL 6, 2021 – APRIL 26, 2021  until 9:00 AM
2.  Pre-bid ConferenceAPRIL 14, 2021 @  10:00 AM
3.  Submission of Eligibility and BidsAPRIL 26, 2021 until 9:00 AM
4.  Opening of BidsAPRIL 26, 2021  @ 10:00 AM
  • Pre-Bid Conference/ Opening of Bids’ date is automatically re- scheduled in case the deadline for each activity falls on a non-working day (i.e. Saturday and Sunday), legal holiday, or special non-working holiday, the deadline shall be the next working day. (Section 38.2 of RA 9184)

The BAC will issue to prospective bidders Eligibility Forms at BAC Secretariat Office, Capitol Compound, Baler, Aurora, upon their submission of a LOI.  Prospective bidders shall submit the Eligibility Requirements to the BAC at the said address.  They may also obtain the results of the Eligibility Check by the BAC at the same address. Bids document will be available only to prospective bidders upon payment to the Provincial Treasurer’s Office (PTO) of the Provincial Government of Aurora (PGA) of non-refundable amount for the following approved budget for the contract:

The Provincial Government of Aurora assumes no responsibility whatsoever to compensate or indemnify bidders for any expenses incurred in the preparation of the bid. Only those who have purchased the Bidding Documents shall be allowed to participate in the pre-bid conference and raise or submit written queries or clarifications.  The PGA also reserves the right to reject any or all bids, to declare the bidding a failure or waive any defect or informality and to accept bids as may be considered most advantageous to the PGA.


Goods Batch 5 – 2021

The PROVINCIAL GOVERNMENT OF AURORA, through its Bids and Awards Committee (BAC), invites all eligible suppliers/manufacturers/distributors/contractors to bid for the hereunder project:

Name Of ProjectLocationApproved Budget for the Contract
PROCUREMENT OF MEDICAL AND LABORATORY SUPPLIESBALER, AURORA

850,780.00  
TOTAL  

Prospective bidders should have experience in undertaking a similar project within the last two (2) years with an amount of at least 50% of the proposed project for bidding. The Eligibility Check/Screening as well as the Preliminary Examination of Bids shall use non-discretionary “pass/fail” criteria. Post-qualification of the lowest calculated bid shall be conducted.

All particulars relative to Eligibility Statement and Screening, Bid Security, Performance Security, Pre-bidding Conference, Evaluation of Bids, Post Qualification and Awards of Contract shall be governed by the pertinent provisions of RA 9184 and its Implementing Rules and Regulations (IRR).

The schedule of BAC activities is as follows:

ActivitiesSchedule
1.  Issuance of Bid DocumentsMARCH 24, 2021 – APRIL 12, 2021  until 9:00 AM
2.  Pre-bid ConferenceMARCH 31, 2021 @  10:00 AM
3.  Submission of Eligibility and BidsAPRIL 12, 2021  until 9:00 AM
4.  Opening of BidsAPRIL 12, 2021  @ 10:00 AM
  • Pre-Bid Conference/ Opening of Bids’ date is automatically re- scheduled to the next working day whenever such date is declared a holiday.

The BAC will issue to prospective bidders Eligibility Forms upon payment to the Provincial Treasurer’s Office of the PGA of a non-refundable amount for the following approved budget for the contract.

The Provincial Government of Aurora assumes no responsibility whatsoever to compensate or indemnify bidders for any expenses incurred in the preparation of the bid. Only those who have purchased the Bidding Documents shall be allowed to participate in the pre-bid conference and raise or submit written queries or clarifications. The PGA also reserves the right to reject any or all bids, to declare the bidding a failure or waive any defect or informality and to accept bids as may be considered most advantageous to the PGA without thereby incurring any of the following: (a) liability whatsoever to offset expenses or losses the bidder may incur in the preparation of the bids and (b) obligation to inform the affected bidder/s of the grounds for the basis of BAC’s action.


Goods Batch 6 – 2021

The PROVINCIAL GOVERNMENT OF AURORA, through its Bids and Awards Committee (BAC), invites all eligible suppliers/manufacturers/distributors/contractors to bid for the hereunder project:

Name Of ProjectLocationApproved Budget for the Contract
PROCUREMENT OF RESCUE VEHICLEBALER, AURORA2,000,000.00
PROCUREMENT OF LONG LASTING INSECTICIDE TREATED NETSBALER, AURORA1,200,000.00
TOTAL  

Prospective bidders should have experience in undertaking a similar project within the last two (2) years with an amount of at least 50% of the proposed project for bidding. The Eligibility Check/Screening as well as the Preliminary Examination of Bids shall use non-discretionary “pass/fail” criteria.  Post-qualification of the lowest calculated bid shall be conducted.

All particulars relative to Eligibility Statement and Screening, Bid Security, Performance Security, Pre-bidding Conference, Evaluation of Bids, Post Qualification and Awards of Contract shall be governed by the pertinent provisions of RA 9184 and its Implementing Rules and Regulations (IRR).

The complete schedule of activities is listed, as follows:

ActivitiesSchedule
1.  Issuance of Bid DocumentsAPRIL 6, 2021 – APRIL 26, 2021  until 9:00 AM
2.  Pre-bid ConferenceAPRIL 14, 2021 @  10:00 AM
3.  Submission of Eligibility and BidsAPRIL 26, 2021  until 9:00 AM
4.  Opening of BidsAPRIL 26, 2021  @ 10:00 AM
  • Pre-Bid Conference/ Opening of Bids’ date is automatically re- scheduled in case the deadline for each activity falls on a non-working day (i.e. Saturday and Sunday), legal holiday, or special non-working holiday, the deadline shall be the next working day. (Section 38.2 of RA 9184)

The BAC will issue to prospective bidders Eligibility Forms upon payment to the Provincial Treasurer’s Office of the PGA of a non-refundable amount for the following approved budget for the contract.

The Provincial Government of Aurora assumes no responsibility whatsoever to compensate or indemnify bidders for any expenses incurred in the preparation of the bid. Only those who have purchased the Bidding Documents shall be allowed to participate in the pre-bid conference and raise or submit written queries or clarifications. The PGA also reserves the right to reject any or all bids, to declare the bidding a failure or waive any defect or informality and to accept bids as may be considered most advantageous to the PGA without thereby incurring any of the following: (a) liability whatsoever to offset expenses or losses the bidder may incur in the preparation of the bids and (b) obligation to inform the affected bidder/s of the grounds for the basis of BAC’s action.


Infrastructure Project Batch 9 – 2021

The PROVINCIAL GOVERNMENT OF AURORA, through its Bids and Awards Committee (BAC), invites all eligible contractors registered with and classified by the Philippine Contractors Accreditation Board (PCAB), to bid for the hereunder contract:

Name Of ProjectLocationApproved Budget for the Contract
COMPLETION OF MULTI-PURPOSE BUILDING BRGY. UMIRAY I GENERAL REQUIREMENTS 903(2) Formworks and Falseworks 1047(2)b Structural Steel Purlins 1047(2)a Structural Steel, Trusses 1047(6) Metal Structure Accessories (Steel Plates) 1047(7)b Metal Structure Accessories (Sagrods) 1047(4) Metal Structure Accessories (Crossbracing) 1047(3)c Metal Structure Accessories (Turnbuckle) 1014(1)b1 Prepainted Metal Sheets (Prepainted, Long Span, 0.5mm Thk) 1032(1)c Painting Works (Metal Painting) II Construction of Basketball Ring Fabrication and Installation of Fiber Glass w/ Ring & ¼” thk. 50mm x50mm Angular Bar (Frame, Hanger, Stud) Standard board Dimension III Electrical WorksDINGALAN, AURORA1,000,000.00
REPLACEMENT OF DIMALANG BRIDGE (12m) Sta. Ko. 353+096 TO Ko. 353+104.5, CASIGURAN-DILASAG PROVINCIAL ROAD PART A TEMPORARY FACILITIES A.1.1(8)  PROVISION OF THE FIELD OFFICE FOR THE ENGINEER (RENTAL BASIS) PART B OTHER GENERAL REQUIREMENTS B.5.a  PROJECT SIGN BOARD (PGA) B.5.b  PROJECT SIGN BOARD (COA BILLBOARD) B.7(1) OCCUPATIONAL SAFETY & HEALTH PROGRAM B.8(1) TRAFFIC MANAGEMENT B.9     MOBILIZATION/DEMOBILIZATION PART C         EARTHWORKS 100(1) CLEARING & GRUBBING (APPROACHES) 102(1) ROADWAY EXCAVATION (UNSUITABLE) 103(1)a STRUCTURE EXCAVATION 104(2) EMBANKMENT (BORROW), COMPACTED VOLUME PART D         BRIDGE CONSTRUCTION 400(17)C CONCRETE PILE CAST IN DRILLEDD HOLES 400(23)C1 STEEL CASING (1.8m Ө) 400(26)b PILE INTEGRITY TESTING (Ordinary Soil Cond.) 400(27) HIGH STRAIN DYNAMIC TESTING (PDA) 410(2)A CONCRETE RAILING (STANDARD) 403(4) STRUCTURAL STEEL, FURNISHED & FABRICATED (Bored Pile) 404(3)a.1 REINFORCING STEEL BARS (DECK SLAB) 404(3)a.2 REINFORCING STEEL BARS (GIRDER) 405(1)B2 STRUCTURAL CONCRETE CLASS 14 DAYS, fc = 27.60 Mpa 405(1)B3 STRUCTURAL CONCRETE CLASS 28 DAYS, fc = 27.60 Mpa (Deck Slab) 406(1)F8 PRESTRESSED STRUCTURAL CONCRETE, MEMBERS (TYPE III, L = 12.0m) 411(2) PAINTING WORKS, Guardrail 412(1) ELASTOMERIC PAD 413(4)B EXPANSION JOINT 414(1) FORMS & SCAFFOLDINGS 729(1) PROTECTIVE COATING FOR CONCRETE, (Water Proofing for Deck Slab) PART E         SURFACE COARSES/ASPHALT OVERLAY 302(2) EMULSIFIED ASPHALT 310(1)A3 BITUMINOUS CONCRETE SURFACE, WEARING COARSE, HOT LAID (50mm) PART F         MISCELLANEOUS STRUCTURES 612(1)a Reflectorized Thermoplastic Pavement MARKING (White) 612(1)b Reflectorized Thermoplastic Pavement MARKING (Yellow) PART G         ROADWAY 104(2) EMBANKMENT 105(1) SUBGRADE PREPARATION (COMMON MATERIAL) 200    AGGREGATE SUBBASE COURSE 201    AGGREGATE BASE COURSE 311(1)a.3 PORTLAND CEMENT CONCRETE PAVEMENT (UNREINFORCED), 230mm thk. – 14 PART H DRAINAGE & SLOPE PROTECTION (BRIDGE, CREEK, PCCP W/ CONCRETE BARRIER) 505(5) GROUTED RIPRAP (CLASS A) 510(2) CONCRETE SLOPE PROTECTIONCASIGURAN, AURORA15,000,000.00
TOTAL  

Prospective bidders should possess a valid PCAB License applicable to the contract, have completed a similar contract with a value of at least 50% of the ABC, and have key personnel and equipment available for the prosecution of the contract.  The BAC will use non-discretionary pass/fail criteria in the Eligibility Check/Screening as well as the Preliminary Examination of Bids.  The BAC will conduct post-qualification of the lowest calculated bid.

The pertinent provisions of RA 9184 and its Implementing Rules and Regulations (IRR) shall govern all particulars relative to Eligibility Statement and Screening, Bid Security, Performance Security, Pre-bidding Conference, Evaluation of Bids, Post Qualification and Award of Contract.

The schedule of BAC activities is as follows:

ActivitiesSchedule
1.  Issuance of Bid DocumentsApril 13, 2021 – May 3, 2021  until 9:00 AM
2.  Pre-bid ConferenceAPRIL 21, 2021  @  10:00 AM
3.  Submission of Eligibility and BidsMAY 3, 2021  2021  until 9:00 AM
4.  Opening of BidsMAY 3, 2021  @ 10:00 AM
  • Pre-Bid Conference/ Opening of Bids’ date is automatically re- scheduled to the next working day whenever such date is declared a holiday.

The BAC will issue to prospective bidders Eligibility Forms at BAC Secretariat Office, Capitol Compound, Baler, Aurora, upon their submission of a LOI.  Prospective bidders shall submit the Eligibility Requirements to the BAC at the said address.  They may also obtain the results of the

Eligibility Check by the BAC at the same address. Bids document will be available only to prospective bidders upon payment to the Provincial Treasurer’s Office (PTO) of the Provincial Government of Aurora (PGA) of non-refundable amount for the following approved budget for the contract:

The Provincial Government of Aurora assumes no responsibility whatsoever to compensate or indemnify bidders for any expenses incurred in the preparation of the bid. Only those who have purchased the Bidding Documents shall be allowed to participate in the pre-bid conference and raise or submit written queries or clarifications.  The PGA also reserves the right to reject any or all bids, to declare the bidding a failure or waive any defect or informality and to accept bids as may be considered most advantageous to the PGA.


Printing and Reproduction of Instructional Materials and SLMs (Batch 3)

The PROVINCIAL GOVERNMENT OF AURORA, through its Bids and Awards Committee (BAC), invites all eligible suppliers/manufacturers/distributors/contractors to bid for the hereunder project:

Name Of ProjectLocationApproved Budget for the Contract
Printing and Reproduction of Instructional Materials and SLMs (Batch 3)BALER, AURORA6,380,017.00
TOTAL  

Prospective bidders should have experience in undertaking a similar project within the last two (2) years with an amount of at least 50% of the proposed project for bidding. The Eligibility Check/Screening as well as the Preliminary Examination of Bids shall use non-discretionary “pass/fail” criteria.  Post-qualification of the lowest calculated bid shall be conducted.

All particulars relative to Eligibility Statement and Screening, Bid Security, Performance Security, Pre-bidding Conference, Evaluation of Bids, Post Qualification and Awards of Contract shall be governed by the pertinent provisions of RA 9184 and its Implementing Rules and Regulations (IRR).

The complete schedule of activities is listed, as follows:

ActivitiesSchedule
1.  Issuance of Bid DocumentsApril 13, 2021 – May 3, 2021  until 9:00 AM
2.  Pre-bid ConferenceAPRIL 21, 2021  @  10:00 AM
3.  Submission of Eligibility and BidsMAY 3, 2021  2021  until 9:00 AM
4.  Opening of BidsMAY 3, 2021  @ 10:00 AM
  • Pre-Bid Conference/ Opening of Bids’ date is automatically re- scheduled to the next working day whenever such date is declared a holiday.

The BAC will issue to prospective bidders Eligibility Forms upon payment to the Provincial Treasurer’s Office of the PGA of a non-refundable amount for the following approved budget for the contract.

The Provincial Government of Aurora assumes no responsibility whatsoever to compensate or indemnify bidders for any expenses incurred in the preparation of the bid. Only those who have purchased the Bidding Documents shall be allowed to participate in the pre-bid conference and raise or submit written queries or clarifications. The PGA also reserves the right to reject any or all bids, to declare the bidding a failure or waive any defect or informality and to accept bids as may be considered most advantageous to the PGA without thereby incurring any of the following: (a) liability whatsoever to offset expenses or losses the bidder may incur in the preparation of the bids and (b) obligation to inform the affected bidder/s of the grounds for the basis of BAC’s action.


Infrastructure Project Batch 10 – 2021

The PROVINCIAL GOVERNMENT OF AURORA, through its Bids and Awards Committee (BAC), invites all eligible contractors registered with and classified by the Philippine Contractors Accreditation Board (PCAB), to bid for the hereunder contract:

Name Of ProjectLocationApproved Budget for the Contract
CONSTRUCTION OF BRIDGE AT AMUTAN RIVER, BRGY. BUTAS NA BATO PART A TEMPORARY FACILITIES A.1.1(8) Provision of Field Office for the Engineer (Rental Basis) PART B OTHER GENERAL REQUIREMENTS B.5.a Project Sign Board (PGA) B.5.b Project Sign Board (COA Billboard) B.7(1) Occupational Safety and Health Program B.8(1) Traffic Management B.9 Mobilization/Demobilization B.15 Detour/ Access Road PART C EARTHWORKS 100(1) Clearing & Grubbing (approaches) 103(1)a Structure Excavation 104(2) Embankment (Borrow), Compacted Volume PART D BRIDGE CONSTRUCTION 400(17)C CONCRETE PILE CAST IN DRILLED HOLES 400(23)C1 STEEL CASING (1.4m Φ) 400(26)b PILE INTEGRITYTESTING (Ordinary Soil Cond.) 400(27) HIGH STRAIN DYNAMIC TESTING (PDA) 410(2)A CONCRETE RAILING (STANDARD) 403(4) STRUCTURAL STEEL, FURNISHED & FABRICATED 404(3)a.1 REINFORCING STEEL BARS (DECK SLAB) 404(3)a.2 REINFORCING STEEL BARS (GIRDER) 405(1)B2 STRUCTURAL CONCRETE CLASS 14 DAYS, fc =27.60 Mpa (Girder) 405(1)B3 STRUCTURAL CONCRETE CLASS 28 DAYS, fc =27.60 Mpa (Deck Slab) 406(1)F8 PRESTRESSED STRUCTURAL CONCRETE, MEMBERS (TYPE III, L=20.0m) 411(2) PAINTING WORKS, Guardrail 412(1) ELASTOMERIC PAD 413(4)B EXPANSION JOINT 414(1) FORMS & SCAFFOLDINGS 414.0 Reinforced Concrete Approach Slab 507.0 Rubble Concrete 729(1) PROTECTIVE COATING FOR CONCRETE, (Water Proofing for Deck Slab) PART E SURFACE COARSES/ASPHALT     OVERLAY 302(2) EMULSIFIED ASPHALT 310(1)A3 BITUMINOUS CONCRETE SURFACE, WEARING COURSE, HOT LAID (50mm) PART F MISCELLANEOUS STRUCTURES 603(3)a Metal Guardrails (Metal Beam) including Concrete Post 603(3)b Guardrail End Pieces 605(2)a Regulatory Sign, 600mm Circular Post 605(3) Informatory Sign, 750mm Triangular with Post 620(1) Chevron Signs, Type HM-1A, 18″(450mm) x 24″(600mm) 612(1)a Reflectorized Thermoplastic Pavement Marking (White) 612(1)b Reflectorized Thermoplastic Pavement Marking (Yellow) PART G ROADWAY 101(3)a.1 Removal of Existing Concrete Pavement (0.23m thk.) 102(2)b Roadway Excavation (Surplus Common) 102(3)c Roadway Excavation (Surplus Hard Rock) – Blasting 104(1)b Embankment from Roadway Excavation 104(2) Embankment 105(1) Subgrade Preparation (Common Material) 200 Aggregate Subbase Course 201 Aggregate Base Course 311(1)a.3 Portland Cement Concrete Pavement (Unreinforced), 230mm thk. – 14 days PART H DRAINAGE & SLOPE PROTECTION (Bridge, Creek, PCCP w/ Concrete Barrier) 505(5) Grouted Riprap (Class A) 510(2) CONCRETE SLOPE PROTECTION PART I RIVER TRAINING WORKS 102(1) Re-Channeling/ Dredging Excavation of River Bed 511(a) Gabions (1.0×1.0x2.0m) 511(c) Mattresses (t=300mm) PART J INCIDENTALS Spcl. I Relocation of Electrical Post  Dingalan, Aurora50,000,000.00
TOTAL  

Prospective bidders should possess a valid PCAB License applicable to the contract, have completed a similar contract with a value of at least 50% of the ABC, and have key personnel and equipment available for the prosecution of the contract.  The BAC will use non-discretionary pass/fail criteria in the Eligibility Check/Screening as well as the Preliminary Examination of Bids.  The BAC will conduct post-qualification of the lowest calculated bid.

The pertinent provisions of RA 9184 and its Implementing Rules and Regulations (IRR) shall govern all particulars relative to Eligibility Statement and Screening, Bid Security, Performance Security, Pre-bidding Conference, Evaluation of Bids, Post Qualification and Award of Contract.

The schedule of BAC activities is as follows:

ActivitiesSchedule
1.  Issuance of Bid DocumentsApril 22, 2021 – May 12, 2021  until 9:00 AM
2.  Pre-bid ConferenceAPRIL 30, 2021  @  10:00 AM
3.  Submission of Eligibility and BidsMAY 12, 2021  2021  until 9:00 AM
4.  Opening of BidsMAY 12, 2021  @ 10:00 AM
  • Pre-Bid Conference/ Opening of Bids’ date is automatically re- scheduled to the next working day whenever such date is declared a holiday.

The BAC will issue to prospective bidders Eligibility Forms at BAC Secretariat Office, Capitol Compound, Baler, Aurora, upon their submission of a LOI.  Prospective bidders shall submit the Eligibility Requirements to the BAC at the said address.  They may also obtain the results of the

Eligibility Check by the BAC at the same address. Bids document will be available only to prospective bidders upon payment to the Provincial Treasurer’s Office (PTO) of the Provincial Government of Aurora (PGA) of non-refundable amount for the following approved budget for the contract:

The Provincial Government of Aurora assumes no responsibility whatsoever to compensate or indemnify bidders for any expenses incurred in the preparation of the bid. Only those who have purchased the Bidding Documents shall be allowed to participate in the pre-bid conference and raise or submit written queries or clarifications.  The PGA also reserves the right to reject any or all bids, to declare the bidding a failure or waive any defect or informality and to accept bids as may be considered most advantageous to the PGA.


Infrastructure Project Batch 11 – 2021

The PROVINCIAL GOVERNMENT OF AURORA, through its Bids and Awards Committee (BAC), invites all eligible contractors registered with and classified by the Philippine Contractors Accreditation Board (PCAB), to bid for the hereunder contract:

Name Of ProjectLocationApproved Budget for the Contract
REBLOCKING OF ROAD GOING TO MARIA AURORA COMMUNITY HOSPITAL (MACH) I.1 Mobilization/Demobilization I.2 Setting Out and Staking I.3 Construction Safety and Health Program I.4 Project Billboard (PGA) I.5 Project Billboard (COA) 101(3)a.1 Removal of Existing Concrete Pavement 104 Embankment (from borrow) 105(1) Subgrade Preparation (Existing Pavement) 200 Aggregate Base Course 811(1)a.2 PCC Pavement (plain)- Conventional Method, 200mm thk.BRGY. 1, MA. AURORA, AURORA1,600,000.00
ESTABLISHMENT OF WOMEN IN INTEGRATED DEVELOPMENT CENTER (WIDE) I General Requirements A.1.1 Provision of Field Office for the Engineers B.5(a) Project Billboard B.5(b) Project Billboard (COA) B.7 Occupational Safety & Health II Demolition of Existing Structure 101(1) Removal Structure & Obstruction III Earthworks 803(1)a Structure Excavation (common soil) 804(4)Gravel Bedding 804(4)1 Embankment IV Plain & Reinforced Concrete Works 900 Reinforced Concrete 902(1)a1 Reinforcing Steel of Reinforced Concrete Structures, Grade 40 903(2) Formworks & Falseworks V Masonry Works 1046(2)a1 100mm CHB Non Load Bearing (Including Reinforcing Steel) 1046(2)a2 150mm CHB Non Load Bearing Wall (Including Reinforcing Steel) VI Plastering 1053(2)a2 Dia. G.I. Pipe Handrail (stair) 1003(1)a1 Fiber Cement Board Ceiling on Metal Frame 1003(1)a2 Wood Composite Ceiling 1018(1) Glazed Tile & Trims (comport rooms & pantry) 1018(2) Unglazed Tiles (comport rooms, office room pantry, training hall & hall way) VII Doors 1010(1) Frames (Jambs, Sill, Head, Transoms and Mullions) 1010(2)b Wooden Panel Doors (Varnish Finished) 1010(2)a uPVC Door with Louver 1004(2)a Lockset 1004(2)g Hinges VIII Windows 1005(1) uPVC Coated Sliding Window w/ Fixed Glass IX Painting Works 1032(1)a Painting Works (Masonry Painting) X Fabricated Tampered Glass uPVC Frames Fixed Tempered Glass ½” thk XI Plumbing 1001(8) Sewer Line Works 1002(6) Cold Water Line Works 1002(5) Sanitary/ Plumbing Fixtures XII Electrical WorksATC COMPOUND, BALER, AURORA5,000,000.00
CONSTRUCTION OF POTABLE WATER SYSTEM I General Requirements I.1 Mobilization/ Staking I.2 Construction of Safety and Health Program I.3 Project Billboard (PGA) I.4 Project Billboard (COA) 103(1)a Structure Excavation (Common Soil) SPCL I. Backfilling/ Restoration 404 Reinforcing steel bar, Grade 40 (Minor Structures) 405 Structural Concrete Class A (Minor Structures) SPCL 2 Pipe LineBRGY. DITALE, DIPACULAO, AURORA2,000,000.00
CONSTRUCTION/ REPAIR OF TRIBAL HALL General Requirements Layout & Excavation Filling of MaterialsConcrete & Masonry WorksFormworks & Scaffolding Fabricated Materials Carpentry WorksDoors & Windows Tinsmitry WorksPainting Works Tile Works (Including CR)DownspoutPlumbing WorksElectrical WorksBRGY. MUCDOL, DIPACULAO, AURORA1,200,000.00
COMPLETION OF DAY CARE CENTER II General RequirementsFormworks & Scaffolding Carpentry WorksPainting WorksTile Works (CR)DownspoutElectrical WorksBRGY. DITALE, DIPACULAO, AURORA500,000.00
CONSTRUCTION OF MULTI-PURPOSE BUILDING(ADDITIONAL REPAIR BA, PARKINGAREA FOR H.E., EVACUATION AREA FOR SPORTS EVENT, PEPO SPCL-I General Requirements   803(1)A Structure Excavation (Common Soil) 704.3 Concrete Masonry Blocks   900 Reinforced Concrete   902(1)a1 Reinforcing Steel of Reinforced Concrete Structures, Grade 40 903(2) Formworks and Falseworks   1027(1) Cement Plaster Finish   1047(2)b Structural Steel Purlins   1047(2)a Structural Steel, Trusses, Strut   1047(6) Metal Structure Accessories (Steel Plates) 1047(7)b Metal Structure Accessories (Sagrods) 1047(4) Metal Structure Accessories (Crossbracing) 1047(3)c Metal Structure Accessories (Turnbuckle)   1014(1)b1 Prepainted Metal Sheets ( Corrugated, Long Span,0.5mm thk) 1032(1)c Painting Works (Metal Painting)  BRGY. SUKLAYIN, BALER, AURORA4,100,000.00
TOTAL  

Prospective bidders should possess a valid PCAB License applicable to the contract, have completed a similar contract with a value of at least 50% of the ABC, and have key personnel and equipment available for the prosecution of the contract.  The BAC will use non-discretionary pass/fail criteria in the Eligibility Check/Screening as well as the Preliminary Examination of Bids.  The BAC will conduct post-qualification of the lowest calculated bid.

The pertinent provisions of RA 9184 and its Implementing Rules and Regulations (IRR) shall govern all particulars relative to Eligibility Statement and Screening, Bid Security, Performance Security, Pre-bidding Conference, Evaluation of Bids, Post Qualification and Award of Contract.

The schedule of BAC activities is as follows:

ActivitiesSchedule
1.  Issuance of Bid DocumentsAPRIL 28, 2021 – May 18, 2021 until 9:00 AM
2.  Pre-bid ConferenceMay 6, 2021 @  10:00 AM
3.  Submission of Eligibility and BidsMay 18, 2021  until 9:00 AM
4.  Opening of BidsMay 18, 2021  @ 10:00 AM
  • Pre-Bid Conference/ Opening of Bids’ date is automatically re- scheduled to the next working day whenever such date is declared a holiday.

The BAC will issue to prospective bidders Eligibility Forms at BAC Secretariat Office, Capitol Compound, Baler, Aurora, upon their submission of a LOI.  Prospective bidders shall submit the Eligibility Requirements to the BAC at the said address.  They may also obtain the results of the Eligibility Check by the BAC at the same address. Bids document will be available only to prospective bidders upon payment to the Provincial Treasurer’s Office (PTO) of the Provincial Government of Aurora (PGA) of non-refundable amount for the following approved budget for the contract:

The Provincial Government of Aurora assumes no responsibility whatsoever to compensate or indemnify bidders for any expenses incurred in the preparation of the bid. Only those who have purchased the Bidding Documents shall be allowed to participate in the pre-bid conference and raise or submit written queries or clarifications.  The PGA also reserves the right to reject any or all bids, to declare the bidding a failure or waive any defect or informality and to accept bids as may be considered most advantageous to the PGA.


Procurement of Rescue Ambulance

The PROVINCIAL GOVERNMENT OF AURORA, through its Bids and Awards Committee (BAC), invites all eligible suppliers/manufacturers/distributors/contractors to bid for the hereunder project:

Name Of ProjectLocationApproved Budget for the Contract
PROCUREMENT OF RESCUE AMBULANCEBALER, AURORA2,000,000.00
TOTAL  

Prospective bidders should have experience in undertaking a similar project within the last two (2) years with an amount of at least 50% of the proposed project for bidding. The Eligibility Check/Screening as well as the Preliminary Examination of Bids shall use non-discretionary “pass/fail” criteria.  Post-qualification of the lowest calculated bid shall be conducted.

All particulars relative to Eligibility Statement and Screening, Bid Security, Performance Security, Pre-bidding Conference, Evaluation of Bids, Post Qualification and Awards of Contract shall be governed by the pertinent provisions of RA 9184 and its Implementing Rules and Regulations (IRR).

The complete schedule of activities is listed, as follows:

ActivitiesSchedule
1.  Issuance of Bid DocumentsApril 22, 2021 – May 12, 2021  until 9:00 AM
2.  Pre-bid ConferenceAPRIL 30, 2021  @  10:00 AM
3.  Submission of Eligibility and BidsMAY 12, 2021  2021  until 9:00 AM
4.  Opening of BidsMAY 12, 2021  @ 10:00 AM
  • Pre-Bid Conference/ Opening of Bids’ date is automatically re- scheduled to the next working day whenever such date is declared a holiday.

The BAC will issue to prospective bidders Eligibility Forms upon payment to the Provincial Treasurer’s Office of the PGA of a non-refundable amount for the following approved budget for the contract.

The Provincial Government of Aurora assumes no responsibility whatsoever to compensate or indemnify bidders for any expenses incurred in the preparation of the bid. Only those who have purchased the Bidding Documents shall be allowed to participate in the pre-bid conference and raise or submit written queries or clarifications. The PGA also reserves the right to reject any or all bids, to declare the bidding a failure or waive any defect or informality and to accept bids as may be considered most advantageous to the PGA without thereby incurring any of the following: (a) liability whatsoever to offset expenses or losses the bidder may incur in the preparation of the bids and (b) obligation to inform the affected bidder/s of the grounds for the basis of BAC’s action.


Infrastructure Project Batch 12 – 2021

The PROVINCIAL GOVERNMENT OF AURORA, through its Bids and Awards Committee (BAC), invites all eligible contractors registered with and classified by the Philippine Contractors Accreditation Board (PCAB), to bid for the hereunder contract:

Name Of ProjectLocationApproved Budget for the Contract
CONSTRUCTION OF MULTI – PURPOSE HALL GENERAL REQUIREMENTSDEMOLITIONLAYOUT & EXCAVATIONFILLING OF MATERIALSCONCRETE & MASONRY WORKSFORMWORKS & SCAFFOLDINGFABRICATED MATERIALSCARPENTRY WORKSDOORS & WINDOWSPAINTING WORKSELECTRICAL WORKS (ROUGH IN)BRGY. OBLIGACION, BALER, AURORA2,000,000.00
CONSTRUCTION OF MULTI-PURPOSE BUILDING SPCL I General Requirements (PGA & COA SIGN BOARD, CONSTRUCTION SAFETY & HEALTH PROGRAM AND OTHER REQUIRED DOCUMENTS SPCL II MOBILIZATION AND DEMOLIZATION 803(1)a STRUCTURE EXCAVATION (COMMON SOIL) 804 GRAVEL BEDDING 900 REINFORCED CONCRETR 902(1)a1 REINFORCING STEEL OF REINFORCED CONCRETE STRUCTURES GRADE 40 903(2) FORMWORKS AND FALSEWORKS 1027(1)CEMENT PLASTER FINISH 1047(2)b STRUCTURAL STEEL PURLINS 1047(2)a STRUCTURAL STEEL TRUSSES, STRUT 1047(6) METAL STRUCTURE ACCESSORIES (STEEL PLATES) 1047(7)b METAL STRUCTURE ACCESSORIES (SAGRODS) 1047(4) METAL STRUCTURE ACCESSORIES(CROSSBRACING) 1047(3)C METAL STRUCTURE ACCESSORIES (TURNBUCKLE) 1914(1)b1 PREPAINTED METAL SHEETS (PREPAINTED, LONG SPSN. 0.5THK.)BRGY. STA. LUCIA, MA. AURORA, AURORA2,500,000.00
CONSTRUCTION OF FLOOD CONTROL I General Requirements I.1 Mobilization and Demobilization I.2 Project Sign Board (Incd. COA and PGA) I.3 Construction Safety and Health 100(2)a Individuals Removal of Trees (small a 150-300mm Ø) 103(1)a Structure Excavation (Common Soil) 104(4) Earth Berm 511(1) GabionsBRGY. DIMABUNO, DIPACULAO, AURORA5,000, 000.00
CONSTRUCTION OF MULTI-PURPOSE HALL (PHASE II) I TRANSHIPMENT OF MATERIALS SPCL II GENERAL REQUIREMENTS 704.3 CONCRETE MASONRY BLOCKS 900 REINFORCED CONCRETE 902(1)a1 a1 REINFORCING STEEL OF REINFORCED CONCRETE STRUCTURES GRADE 40 903(2) FORMWORKS AND FALSEWORKS 1027(1) CEMENT PLASTER FINISH 1047(2)b STRUCTURAL STEEL PURLINS 1047(2)a STRUCTURAL STEEL TRUSSES, STRUT 1047(6) METAL STRUCTURE ACCESSORIES (STEEL PLATES) 1047(7)b METAL STRUCTURE ACCESSORIES (SAGRODS) 1047(4) METAL STRUCTURE ACCESSORIES(CROSSBRACING) 1047(3)C METAL STRUCTURE ACCESSORIES (TURNBUCKLE) 1914(1)b1 PREPAINTED METAL SHEETS (CORRUGATED, LONG SPAN. 0.5MM THK.) 1032 PAINTING WORKS (CONCRETE SURFACES) 1032(1)c PAINTING WORKS (METAL PAINTING) SPCL II ELECTRICAL WORKS SPCL III BASKET BALL RING & BOARD W/ ACCESSORIES & FRAMESBRGY. DIBALO, SAN LUIS, AURORA3,000,000.00
CONSTRUCTION OF FLOOD CONTROL PROJECT ALONG PACUGAO RIVER Part A Facilities for the Engineers A.1.1(8) Provision of field office for the Engineer Part B Other General Requirements B.5 (a) Project Sign Board B.5 (b) Project Billboard/sign Board (COA) B.7 Occupational Safety & Health Program B.9 Mobilization and Demobilization Part D Subbase and Base Course 200(1) Aggregate Subbase Course Part E Surface Course 311(1)a.2 PCC Pavement (plain)- Conventional method, 200mm thk Part J Flood Control and Drainages Part I-A Earthworks 1701(2) surplus common excavation/channel excavation 1701(1)a structure excavation (common soil) 1704(1)a embankment (from excavation) Part I-B Bank and Slope 1712(2) Concrete Slope Protection 404(1)a Reinforcing Steel Bar, Grade 40 (Minor Structure) 405(1)a3 Structural Concrete (20.68mpa, Class A, 28days) 1717(2)a1 Sheet Pile (Steel Concrete Slope Protection) 1710(2)a Grouted RiprapMA. AURORA, AURORA13,000,000.00
TOTAL  

Prospective bidders should possess a valid PCAB License applicable to the contract, have completed a similar contract with a value of at least 50% of the ABC, and have key personnel and equipment available for the prosecution of the contract.  The BAC will use non-discretionary pass/fail criteria in the Eligibility Check/Screening as well as the Preliminary Examination of Bids.  The BAC wiCOll conduct post-qualification of the lowest calculated bid.

The pertinent provisions of RA 9184 and its Implementing Rules and Regulations (IRR) shall govern all particulars relative to Eligibility Statement and Screening, Bid Security, Performance Security, Pre-bidding Conference, Evaluation of Bids, Post Qualification and Award of Contract.

The schedule of BAC activities is as follows:

ActivitiesSchedule
1.  Issuance of Bid DocumentsMay 4 – May 24, 2021  until 9:00 AM
2.  Pre-bid ConferenceMay 12, 2021  @  10:00 AM
3.  Submission of Eligibility and BidsMAY 24, 2021  2021  until 9:00 AM
4.  Opening of BidsMAY 24, 2021  @ 10:00 AM
  • Pre-Bid Conference/ Opening of Bids’ date is automatically re- scheduled to the next working day whenever such date is declared a holiday.

The BAC will issue to prospective bidders Eligibility Forms at BAC Secretariat Office, Capitol Compound, Baler, Aurora, upon their submission of a LOI.  Prospective bidders shall submit the Eligibility Requirements to the BAC at the said address.  They may also obtain the results of the Eligibility Check by the BAC at the same address. Bids document will be available only to prospective bidders upon payment to the Provincial Treasurer’s Office (PTO) of the Provincial Government of Aurora (PGA) of non-refundable amount for the following approved budget for the contract:

The Provincial Government of Aurora assumes no responsibility whatsoever to compensate or indemnify bidders for any expenses incurred in the preparation of the bid. Only those who have purchased the Bidding Documents shall be allowed to participate in the pre-bid conference and raise or submit written queries or clarifications.  The PGA also reserves the right to reject any or all bids, to declare the bidding a failure or waive any defect or informality and to accept bids as may be considered most advantageous to the PGA.


Procurement of Rescue Vehicles

The PROVINCIAL GOVERNMENT OF AURORA, through its Bids and Awards Committee (BAC), invites all eligible suppliers/manufacturers/distributors/contractors to bid for the hereunder project:

Name Of ProjectLocationApproved Budget for the Contract
PROCUREMENT OF RESCUE VEHICLEBALER, AURORA2,000,000.00
TOTAL  

Prospective bidders should have experience in undertaking a similar project within the last two (2) years with an amount of at least 50% of the proposed project for bidding. The Eligibility Check/Screening as well as the Preliminary Examination of Bids shall use non-discretionary “pass/fail” criteria.  Post-qualification of the lowest calculated bid shall be conducted.

All particulars relative to Eligibility Statement and Screening, Bid Security, Performance Security, Pre-bidding Conference, Evaluation of Bids, Post Qualification and Awards of Contract shall be governed by the pertinent provisions of RA 9184 and its Implementing Rules and Regulations (IRR).

The complete schedule of activities is listed, as follows:

ActivitiesSchedule
1.  Issuance of Bid DocumentsMay 4 – May 24, 2021  until 9:00 AM
2.  Pre-bid ConferenceMay 12, 2021  @  10:00 AM
3.  Submission of Eligibility and BidsMAY 24, 2021  2021  until 9:00 AM
4.  Opening of BidsMAY 24, 2021  @ 10:00 AM
  • Pre-Bid Conference/ Opening of Bids’ date is automatically re- scheduled to the next working day whenever such date is declared a holiday.

The BAC will issue to prospective bidders Eligibility Forms upon payment to the Provincial Treasurer’s Office of the PGA of a non-refundable amount for the following approved budget for the contract.

The Provincial Government of Aurora assumes no responsibility whatsoever to compensate or indemnify bidders for any expenses incurred in the preparation of the bid. Only those who have purchased the Bidding Documents shall be allowed to participate in the pre-bid conference and raise or submit written queries or clarifications. The PGA also reserves the right to reject any or all bids, to declare the bidding a failure or waive any defect or informality and to accept bids as may be considered most advantageous to the PGA without thereby incurring any of the following: (a) liability whatsoever to offset expenses or losses the bidder may incur in the preparation of the bids and (b) obligation to inform the affected bidder/s of the grounds for the basis of BAC’s action.


Goods Batch 1

The PROVINCIAL GOVERNMENT OF AURORA, through its Bids and Awards Committee (BAC), invites all eligible suppliers/manufacturers/distributors/contractors to bid for the hereunder project:

Name Of ProjectLocationApproved Budget for the Contract
Procurement of LaptopBaler, Aurora3,000,000.00
Procurement of Multifunctional Copier MachineBaler, Aurora1,300,000.00
Procurement of Ultrasound MachineBaler, Aurora2,000,000.00
Procurement of 4 units Brand New Multi Purpose Vehicle (MPV) Diesel Engine M/T, Euro 4 Emission standardBaler, Aurora5,200,000.00
Procurement of 4×4 Pick UP Vehicle – Diesel Engine (Silver)Baler, Aurora1,500,000.00
TOTAL  

Prospective bidders should have experience in undertaking a similar project within the last two (2) years with an amount of at least 50% of the proposed project for bidding. The Eligibility Check/Screening as well as the Preliminary Examination of Bids shall use non-discretionary “pass/fail” criteria.  Post-qualification of the lowest calculated bid shall be conducted.

All particulars relative to Eligibility Statement and Screening, Bid Security, Performance Security, Pre-bidding Conference, Evaluation of Bids, Post Qualification and Awards of Contract shall be governed by the pertinent provisions of RA 9184 and its Implementing Rules and Regulations (IRR).

The complete schedule of activities is listed, as follows:

ActivitiesSchedule
1.  Issuance of Bid DocumentsJune 22 – July 12, 2021  until 9:00 AM
2.  Pre-bid ConferenceJune 30, 2021  @  10:00 AM
3.  Submission of Eligibility and BidsJuly 12, 2021   until 9:00 AM
4.  Opening of BidsJuly 12, 2021  @ 10:00 AM
  • Pre-Bid Conference/ Opening of Bids’ date is automatically re- scheduled to the next working day whenever such date is declared a holiday.

The BAC will issue to prospective bidders Eligibility Forms upon payment to the Provincial Treasurer’s Office of the PGA of a non-refundable amount for the following approved budget for the contract.

The Provincial Government of Aurora assumes no responsibility whatsoever to compensate or indemnify bidders for any expenses incurred in the preparation of the bid. Only those who have purchased the Bidding Documents shall be allowed to participate in the pre-bid conference and raise or submit written queries or clarifications. The PGA also reserves the right to reject any or all bids, to declare the bidding a failure or waive any defect or informality and to accept bids as may be considered most advantageous to the PGA without thereby incurring any of the following: (a) liability whatsoever to offset expenses or losses the bidder may incur in the preparation of the bids and (b) obligation to inform the affected bidder/s of the grounds for the basis of BAC’s action.


Infrastructure Project Batch 13

The PROVINCIAL GOVERNMENT OF AURORA, through its Bids and Awards Committee (BAC), invites all eligible contractors registered with and classified by the Philippine Contractors Accreditation Board (PCAB), to bid for the hereunder contract:

Name Of ProjectLocationApproved Budget for the Contract
CONSTRUCTION OF 3 ROOMS COMFORT ROOM (PHASE II) AT AURORA PROVINCIAL JAIL General Requirements I.1 MOBILIZATION AND DEMOBILIZATION I.2 Construction and Safety and Health Program I.3 Project Signboard (PGA & COA) II. Fabricated Materials and Hardwares 1010(b) Panel Doors w/ Door Frame and Complete Accessories 1010( c) Louver Wooden Door (Push and Pull) 1004(2)g Hinges Heavy duty III Reinforced Concrete 900 Reinforced Concrete V Tile Works 1018(1) Glazed Tiles and Trims 1018(2) Unglazed Tiles VI Finishing Works 1021(c-2) Non-Skid cement Finish with 6mm goove lines 1027(a) Skim Coat Finish VII Carpentry Works 1003(1)a1  ¼ thk. Marine Plywood on Metal Frame Ceiling VIII  Railings 1053(2)a2  1.5 inches Ǿ Gauge # 304 Stainless Pipe Handrail on Vertical Railing Stiffer IX  Roof and Framing Works 1014(1)b1 Prepainted Metal Sheet (Corrugated, long Span 0.5mm thk.) 1013(2)a Fabricated Metal Roofing Accessory(Ridge roll) 1013(2)b Fabricated Metal Roofing Accessory(Flashing) including Fascia Board 1013(2)c Fabricated Metal Roofing Accessory(Gutter) 1047(2)b Structural Steel purlins and Rafters 1047(2)a Structural Steel, trusses 1047(6) Metal Structure Accessories (Steel Plates) 1001(9) Storm Drainage and Downspout X Painting Works 1032(1)a Painting Works (Masonry Paintings) 1032(1)c  Painting Works (Metal Painting) 1032(1)b  Painting Works (Wood Paintings) XI Electrical Works 1103(1) Light Fixture, Wiring And Others 1001(8) Sewer Line Works 1002(6) Water Line Works 1002(5) Sanitary/Plumbing FixturesBALER, AURORA695,438.92
CONSTRUCTION OF CENTRAL TERMINAL AT BRGY. MASAGANA, DILASAG, AURORA GENERAL REQUIREMENTSLAYOUT & EXCAVATIONFILLING OF MATERIALSCONCETE & MASONRY WORKSFORMWORKS & SCAFFOLDINGFABRICATED MATERIALSCEILING WORKSDOORS AND WINDOWSPAINTING WORKSTILE WORKS (INCLDING CR)DOWNSPOUTPLUMBINGWORKSELECTRICAL WORKSDILASAG, AURORA3,000,000.00
CONSTRUCTION OF FTMR (PHASE III), SO. AMURAWEN, BRGY. ESPERANZA SPCL GENERAL REQUIREMENTS I.1 MOBILIZATION AND DEMOBILIZATION I.2 SETTING OUT AND STAKING I.3 CONSTRUCTION SAFETY AND HEATH PROGRAM I.4.a PROJECT SIGN BOARD (PGA) I.4.b PROJECT SIGN BOARD (COA) 100 (1) CLEARING & GRUBBING 103 (1)a STRUCTURE EXCAVATION ( COMMON SOIL ) 104 (1)a EMBANKMENT ( FROM BORROW ) 105 (1) SUBGRADE PREPARATION ( COMMON SOIL ) 200 AGGREGATE SUBBASE COURSE 311 (1)a.2 PCC PAVEMENT ( PLAIN ) – CONVENTIONAL METHOD 505 (5) GROUTED RIPRAP ( CLASS A )DILASAG, AURORA5,000,000.00
CONSTRUCTION OF HEATH FACILITY WITH ISOLATION WARD AT AURORA PROVINCIAL JAIL GENERAL REQUIREMENTSLAYOUT & EXCAVATIONFILLING OF MATERIALSCONCETE & MASONRY WORKSFORMWORKS & SCAFFOLDINGROOF FRAMING & TINSMITHRYPLUMBINGWORKSELECTRICAL WORKSBALER, AURORA500,000.00
CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE III), SO. DIOTORIN, BRGY. DIBAYABAY Transshipment of Materials (Triple Handling SPCL -1  General Requirements 900 Reinforced Concrete 902(1)a1 Reinforcing Steel of Reinforced Concrete Structures, Grade 40 903 (2) Formworks and Falseworks 1027(1) Cement Plaster Finish 1047(2)b Structural Steel Purlins 1047(2)a Structural Steel Trusses, Strut 1047(6) Metal Structure Accessories (Steel Plates) 1047(7)b Metal Structure Accessories (Sagrod) 1047 Metal Structure Accessories (Cross Bracing) 1047(3)c Metal Structure Accessories (turnbuckle) 1014(1)b1 Prepainted Metal Sheets (Corrugated Long Span, 0.5mmthk.) 1032 Painting Works (Concrete Surfaces) 1032(1)c Painting Works (Metal Painting) SPCL II Electrical Works SPCL III Basketball Ring & Board w/ Accessories & FramesSAN LUIS, AURORA2,800,000.00
CONSTRUCTION OF TRIBAL HALL, BRGY. ABULEG GENERAL REQUIREMENTSLAYOUT & EXCAVATIONFILLING OF MATERIALSCONCRETE & MASONRY WORKSFORMWORKS & SCAFFOLDINGROOF FRAMING & TINSMITHRY WORKSFABRICATED PIPE RAILINGSCEILING WORKSDOORS & WINDOWSPAINTING WORKSPLUMBING WORKSELECTRICAL WORKSDINALUNGAN, AURORA1,200,000.00
CONSTRUCTION OF TWO – STOREY MULTI-PURPOSE BUILDING, BRGY, ZABALI GENERAL REQUIREMENTSLAYOUT & EXCAVATIONFILLING OF MATERIALSCONCRETE & MASONRY WORKSFORMWORKS & SCAFFOLDINGFABRICATED MATERIALSCARPENTRY WORKS DOORS & WINDOWSPAINTING WORKSTILE WORKS (INCLUDING CR)DOWNSPOUTPLUMBING WORKSELECTRICAL WORKSBALER, AURORA5,000,000.00
CONSTRUCTION OF POTABLE WATER SYSTEM I General Requirements I.1 Mobilization/ Staking I.2 Construction of Safety and Health Program I.3 Project Billboard (PGA) I.4 Project Billboard (COA) 103(1)a Structure Excavation (Common Soil) SPCL I. Backfilling/ Restoration 404 Reinforcing steel bar, Grade 40 (Minor Structures) 405 Structural Concrete Class A (Minor Structures) SPCL 2 Pipe LineBRGY. DITALE, DIPACULAO, AURORA2,000,000.00
COMPLETION OF OPEN MULTI-PURPOSE HALL, BRGY. IPIL General Requirements SPCL.I Mobilization / Demobilization SPCL.II Construction of Safety and Health SPCL.III Project Sign Board (PGA) SPCL.IV Project Sign Board (COA) SPCL.V Board and Ring (Movable) 1047(2)a Structural Steel , Trusses, Strut 1014(1)b1 Prepainted Metal Sheet ( Corrugated, Long Span, 0.5mm thk ) III Electrical Works 1032(1)c Painting Works (All Steel Inc. Concrete)BRGY. IPIL, DIPACULAO, AURORA1,000,000.00  
IMPROVEMENT OF SALAY-DIPACULAO PROVINCIAL ROAD BRGY. SALAY  PART A – FACILITIES FOR THE ENGINEERS A.1.1(8) PROVISION OF FIELD OFFICE FOR ENGINEER PART B – OTHER GENERAL REQUIREMENTS B.4     CONSTRUCTION SURVEY AND STAKING B.5(a) PROJECT SIGN BOARD B.5(b) PROJECT BILLBOARD/SIGN BOARD ( COA ) B.7 OCCUPATIONAL SAFETY AND HEALTH PROGRAM B.9 MOBILIZATION AND DEMOBILIZATION PART C – EARTHWORKS 100(1) CLEARING AND GRUBBING (WITH STRIPPING ) 101(3)a.1 REMOVAL OF EXISTING CONCRETE PAVAMENT ( 0.2MM THK. ) 102(2)a ROADWAY EXCAVATION ( SURPLUS COMMON ) 104(1)a EMBANKMENT FROM BORROW 105(1) SUBGRADE PREPARATION ( COMMON MATERIAL ) PART D – SUBBASE AND BASE COURSE 200 AGGREGATE SUBBASE COURSE PART E – SURFACE COURSE 311(1)a.2 PCC PAVEMENT ( PLAIN  ) – CONVENTIONAL METHOD, 200 mm THK. PART G – SLOPE PROTECTION STRUCTURES 505(5) GROUTED RIPRAP, CLASS A PART H MISCELLANEOUS STRUCTURES 405(2)d STRUCTURAL CONCRETE CLASS B ( WHEEL GUARD )BRGY. SALAY, DIPACULAO, AURORA4,500,000.00
SPCL.I I.1 Mobilization / Demobilization I.2 Setting out and Staking I.3 Construction Safety and Health Program I.4 Project Signboard I.5 Project Signboard ( COA ) 100(1) Clearing & Grubbing ( with Stripping ) 105(1) Subgrade Preparation ( Common Material ) 200 Aggregate Subbase Course 404 Reinforcing Steel Bar, Grade 40 ( Minor Structure ) 405 Structure Concrete Class A ( minor Structure ) 103(1)a Structure Excavation ( Common Soil ) 101(2) Removal of Concrete Drainage Structure 311(1)a.2 PCCP Conventional Method ( 200mm thk. )BRGY. TABAS, CASIGURAN, AURORA2,700,000.00
CONSTRUCTION OF STAGE, BRGY. IPIL I. GENERAL REQUIREMENTS II. LAYOUT & EXCAVATION III. BACK FILLING IV. CONCRETE & MASONRY WORKS V. FORMWORKS & SCAFFOLDING VI. ROOF FRAMING & TINSMITHRY WORKSDIPACULAO, AURORA500,00.00
CONSTRUCTION OF SECURITY TOWER AT AURORA PROVINCIAL JAIL I.GENERAL REQUIREMENTS II. LAYOUT EXCAVATION AND BACK FILLING III. CONCRETE & MASONRY WORKS IV. FORMWORKS & SCAFFOLDING V. ROOF FRAMING VI. TINSMITHRY WORKSBALER, AURORA200,000.00
TOTAL  

Prospective bidders should possess a valid PCAB License applicable to the contract, have completed a similar contract with a value of at least 50% of the ABC, and have key personnel and equipment available for the prosecution of the contract.  The BAC will use non-discretionary pass/fail criteria in the Eligibility Check/Screening as well as the Preliminary Examination of Bids.  The BAC wiCOll conduct post-qualification of the lowest calculated bid.

The pertinent provisions of RA 9184 and its Implementing Rules and Regulations (IRR) shall govern all particulars relative to Eligibility Statement and Screening, Bid Security, Performance Security, Pre-bidding Conference, Evaluation of Bids, Post Qualification and Award of Contract.

The schedule of BAC activities is as follows:

ActivitiesSchedule
1.  Issuance of Bid DocumentsJune 22 – July 12, 2021  until 9:00 AM
2.  Pre-bid ConferenceJune 30, 2021  @  10:00 AM
3.  Submission of Eligibility and BidsJuly 12, 2021   until 9:00 AM
4.  Opening of BidsJuly 12, 2021  @ 10:00 AM
  • Pre-Bid Conference/ Opening of Bids’ date is automatically re- scheduled to the next working day whenever such date is declared a holiday.

The BAC will issue to prospective bidders Eligibility Forms at BAC Secretariat Office, Capitol Compound, Baler, Aurora, upon their submission of a LOI.  Prospective bidders shall submit the Eligibility Requirements to the BAC at the said address.  They may also obtain the results of the Eligibility Check by the BAC at the same address. Bids document will be available only to prospective bidders upon payment to the Provincial Treasurer’s Office (PTO) of the Provincial Government of Aurora (PGA) of non-refundable amount for the following approved budget for the contract:

The Provincial Government of Aurora assumes no responsibility whatsoever to compensate or indemnify bidders for any expenses incurred in the preparation of the bid. Only those who have purchased the Bidding Documents shall be allowed to participate in the pre-bid conference and raise or submit written queries or clarifications.  The PGA also reserves the right to reject any or all bids, to declare the bidding a failure or waive any defect or informality and to accept bids as may be considered most advantageous to the PGA.


Infrastructure Project Batch 14

The PROVINCIAL GOVERNMENT OF AURORA, through its Bids and Awards Committee (BAC), invites all eligible contractors registered with and classified by the Philippine Contractors Accreditation Board (PCAB), to bid for the hereunder contract:

Name Of ProjectLocationApproved Budget for the Contract
CONSTRUCTION OF BRGY. HALL, BRGY. DIMANAYAT General Requirements (Including Transshipment)Layout & Excavation Filling of Materials Concrete & Masonry WorksFormworks & ScaffoldingCarpentry WorksDoors and WindowsPainting Works Tile WorksDownspoutRoofing WorksElectrical WorksSan Luis, Aurora1,200,000.00
COMPLETION OF MULTI-PURPOSE HALL, BRGY. MIJARES General Requirements (Including Project Sign Board)Doors and Window GrillsRoof Ceiling/ Inside CeilingPainting WorksElectrical WorksRailingsPlumbing WorksPlastering (Top of Attic)Dipaculao, Aurora1,000,000.00
REHABILITATION OF BRGY. ROAD, BRGY. DIBALO Part A General Requirements B.5a Project Billboard/ Sign Board(PGA) B.5b Project Billboard/ Sign Board(COA) B.7   Occupational Safety and Health B.9   Mobilization/ Demobilization Part B Earthworks 100(1) Clearing & Grubbing (with stripping) 102(2)a Roadway Excavation (Surplus Common) 104(1)a Embankment (from Borrow) Part C Cross Drain 103(6) Pipe Culvert and Drain Excavation 500(1)c Pipe Culverts, 910mm dia. (36” Ǿ) 505(5) Grouted Riprap (Class A)San Luis, Aurora1,100,000.00
CONSTRUCTION OF FLOOD CONTROL PROJECT ALONG PACUGAO RIVER Part A Facilities for the Engineers A.1.1(8) Provision of field office for the Engineer Part B Other General Requirements B.5 (a) Project Sign Board B.5 (b) Project Billboard/sign Board (COA) B.7 Occupational Safety & Health Program B.9 Mobilization and Demobilization Part D Subbase and Base Course 200(1) Aggregate Subbase Course Part E Surface Course 311(1)a.2 PCC Pavement (plain)- Conventional method, 200mm thk Part J Flood Control and Drainages Part I-A Earthworks 1701(2) surplus common excavation/channel excavation 1701(1)a structure excavation (common soil) 1704(1)a embankment (from excavation) Part I-B Bank and Slope 1712(2) Concrete Slope Protection 404(1)a Reinforcing Steel Bar, Grade 40 (Minor Structure) 405(1)a3 Structural Concrete (20.68mpa, Class A, 28days) 1717(2)a1 Sheet Pile (Steel Concrete Slope Protection) 1710(2)a Grouted Riprap Class AMA. AURORA, AURORA13,000,000.00
CONSTRUCTION OF FLOOD CONTROL AT PACUGAO RIVER (FLORIDA – DIMANPUDSO SECTION) Part A Facilities for the Engineers A.1.1(8) Provision of field office for the Engineer Part B Other General Requirements B.5 (a) Project Sign Board B.5 (b) Project Billboard/sign Board (COA) B.7 Occupational Safety & Health Program B.9 Mobilization and Demobilization Part J Flood Control and Drainages Part I-A Earthworks 1701(2) surplus common excavation/channel excavation 1701(1)a structure excavation (common soil) 1704(1)a embankment (from excavation) Part I-B Bank and Slope 1712(2) Concrete Slope Protection 404(1)a Reinforcing Steel Bar, Grade 40 (Minor Structure) 405(1)a3 Structural Concrete (20.68mpa, Class A, 28days) 1717(2)a1 Sheet Pile (Steel Concrete Slope Protection) 1710(2)a Grouted Riprap Class AMARIA AURORA, AURORA7,000,000.00
TOTAL  

Prospective bidders should possess a valid PCAB License applicable to the contract, have completed a similar contract with a value of at least 50% of the ABC, and have key personnel and equipment available for the prosecution of the contract.  The BAC will use non-discretionary pass/fail criteria in the Eligibility Check/Screening as well as the Preliminary Examination of Bids.  The BAC wiCOll conduct post-qualification of the lowest calculated bid.

The pertinent provisions of RA 9184 and its Implementing Rules and Regulations (IRR) shall govern all particulars relative to Eligibility Statement and Screening, Bid Security, Performance Security, Pre-bidding Conference, Evaluation of Bids, Post Qualification and Award of Contract.

The schedule of BAC activities is as follows:

ActivitiesSchedule
1.  Issuance of Bid DocumentsJuly 13, 2021 – August 2, 2021 until 9:00 AM
2.  Pre-bid ConferenceJuly 21, 2021  @  10:00 AM
3.  Submission of Eligibility and BidsAugust 2, 2021 until 9:00 AM
4.  Opening of BidsAugust 2, 2021 @ 10:00 AM
  • Pre-Bid Conference/ Opening of Bids’ date is automatically re- scheduled to the next working day whenever such date is declared a holiday.

The BAC will issue to prospective bidders Eligibility Forms at BAC Secretariat Office, Capitol Compound, Baler, Aurora, upon their submission of a LOI.  Prospective bidders shall submit the Eligibility Requirements to the BAC at the said address.  They may also obtain the results of the Eligibility Check by the BAC at the same address. Bids document will be available only to prospective bidders upon payment to the Provincial Treasurer’s Office (PTO) of the Provincial Government of Aurora (PGA) of non-refundable amount for the following approved budget for the contract:

The Provincial Government of Aurora assumes no responsibility whatsoever to compensate or indemnify bidders for any expenses incurred in the preparation of the bid. Only those who have purchased the Bidding Documents shall be allowed to participate in the pre-bid conference and raise or submit written queries or clarifications.  The PGA also reserves the right to reject any or all bids, to declare the bidding a failure or waive any defect or informality and to accept bids as may be considered most advantageous to the PGA.


Infrastructure Project Batch 15

The PROVINCIAL GOVERNMENT OF AURORA, through its Bids and Awards Committee (BAC), invites all eligible contractors registered with and classified by the Philippine Contractors Accreditation Board (PCAB), to bid for the hereunder contract:

Name Of ProjectLocationApproved Budget for the Contract
RENOVATION OF DRAINAGE CANAL INFRONT OF DITUMABO NATIONAL HIGH SCHOOL I. General Requirements I.1 Mobilization and Demobilization I.2 Construction Safety and Health and Environment B.5a Project Billboard/Signboard (PGA) B.5bProject Billboard/Signboard (COA) 101(2) Removal of Concrete Drainage Structures 103(1) Structure Excavation (Common Soil) 104(4) Earth Berm 404 Reinforcing Steel Bar Grade 40 405 Structural Concrete Class ASan Luis, Aurora2,000,000.00
REPAIR/ IMPROVEMENT OF DAY CARE CENTER, BRGY. DIANED I. General Requirements II. Formworks & Scafolding III. Carpentry Works IV. Painting Works V. Tile Works (Cr) IV. Roofing Works VI. Plumbimg Works VII. Doors VIII. Electrical WorksDipaculao, Aurora  500,000.00
CONSTRUCTION OF RIPRAP ALONG DIMASINGAN BRIDGE (APPROACH) STA. KO 353+054 TO KO 354+068 I.1 Mobilization/ Demobilization I.2 Setting out and staking I.3 Construction Safety and Health Program I.4 Project sign board I.5 Project sign board (COA) 103(1)a Structure Excavation (Common Material) 105(1) Subgrade Preparation(Common Materials) 200 Aggregate Subbase Course 505(5) Grouted Ripprap (Class A) 104(1)a Embankment (from Borrow) 102(2)b Roadway Excavation (Surplus Common) 311(1)a2 PCCP Conventional Method (200mm thk)Casiguran, Aurora2,000,000.00
CONSTRUCTION OF DRAINAGE SYSTEM, BRGY. MIJARES I. General Requirements I.1 Mobilization and Demobilization I.2 Setting out and Staking I.3 Construction Safety and Health Program I.4 Project Signboard(PGA) I.5 Project Signboard (COA) 101(3)a1 Removal of Exixting Concrete Pavement 103(1)a Structure Excavation (Common Soil) 104(4) Earth Berm 404 Reinforcing Steel Bar, Grade 40 405 Structural Concrete Class ADipaculao, Aurora1,000,000.00
CONCRETING OF ROAD PUROK 2, PACDAL ST., BRGY.3(300M) SPCL General Requirements I.1 Mobilization and Demobilization I.2 Setting out and Staking I.3 Construction Safety and Health Program I.4 Project Billboard/Signboard(PGA) I.5 Project Billboard/Signboard (COA) 104 Embankment (from Borrow) 105(1) Subgrade Preparation (Common Material) 200 Aggregate Base Course 311(1)a.2 PCC Pavement (Plain)-Conventional Method, 200mm thk.MA. AURORA, AURORA3,000,000.00
CONSTRUCTION OF DRAINAGE CANAL AT BARANGAY SITE PROPER, BRGY. DICABASAN SPCL General Requirements I.1 Mobilization and Demobilization I.2 Setting out and Staking I.3 Construction Safety and Health Program I.4 Project Billboard/Signboard I.5 Project Billboard/Signboard (COA) SPCL II. Relocation of Electrical Post 103(1)a Structure Excavation (Common Soil) 404 Reinforcing Steel Bar, Grade 40 405 Structural Concrete Class A (Minor Structures)Dilasag, Aurora2,000,000.00
CONSTRUCTION OF MULTI-PURPOSE HALL, BRGY. CABITUCULAN WEST SPCL I General Requirement (COA and PGA Sign Board, and Other Required Document) SPCL II Mobilization and Demobilization 803(1)a Structure Excavation (Common soil) 804 Gravel Bedding 900 Reinforced Concrete 902(1)a Reinforcing Steel of Reinforced Concrete Structure, Grade 40 903(2) Form Works and Falseworks 1027(1) Cement Plaster Finish (Rough -in) 1047(2)b Structural Steel Purlins 1047(2)a Structural steel, Trusses, strut 1047(6) Metal Structure Accessories (Steel plates) 1047(7)b Metal structure(Sagrod) 1047(4) Metal Structure (Crossbracing) 1047(3)c Metal Stucture (Turnbuckle) 1014(1)b1 Prepainted Metal Sheets (Prepainted Long Span),0.05mm thk. 1032(1)c Painting works(metal painting)MA. AURORA, AURORA2,500,000.00
CONSTRUCTION OF LINE CANAL ALONG PROVINCIAL ROAD MALIGAYA SECTION, DILASAG AURORA SPCL.I General Requirements I.1 Mobilization,/Demobilization I.2 Setting out and Staking I.3 Construction Safety and Health Program I.4 Project Signboard I.5 Project Signboard (COA) 100(1) Clearing & Grubbing (with stripping) 101(3)a.2 Removal of Existing PCC Pavement, 0.23m thk. 103(1)a Structure Excavation (Common Soil) 404 Reinforcing steel Bar, Grade 40 (minor structures) 405 Strucural concrete Class A. (Minor Structures).DILASAG, AURORA2,000,000.00
CONSTRUCTION OF VETERINARY FUNCTION HALL, AURORA TRADING CENTER COMPOUND, SITIO SETAN, CALABUANAN, BALER, AURORA I. General Requirements II. Demolition, Layout & Excavation III. Filling of Materials IV. Concrete & Masonry Works V.Formworks & Scaffolding VI. Carpentry Works VII. Doors and Windows VIII. Tinsmithry Works IX. Painting Works X. Tile Works (including CR) XI. Downspout XII. Plumbing Works XIII. Electrical WorksBALER, AURORA1,000,000.00
REBLOCKING OF PROV. ROAD INFRONT OF DAES ELEMENTARY SCHOOL, BRGY. MALIGAYA, DILASAG, AURORA SPCL.I I.1 Mobilization/ Demobilization I.2 Setting out and staking I.3 Construction Safety and Health Program I.4 Project sign board I.5 Project sign board (COA) 101(3)a.1 Removal of Existing Concrete Pavement (0.23m thk.) 105(2) Subgrade Preparation(Existing Pavement) 200 Aggregate Subbase Course 311(1)a.2 PCCP Conventional Method (200mm thk)DILASAG, AURORA5,000,000.00
FARM TO MARKET ROAD, BRGY. PUNGLO TO DIAMAN, MARIA, AURORA SPCL.I General Requirements B.9 Mobilization/ Demobilization B.7 Construction Safety and Health Program B.5 Project Signboard 102(2)b Roadway Excavation(Surplus common) 103(1)a  Structure Excavation (Common Soil) 104(1)b Embankment (from Borrow) 105(1) Subgrade Preparation (Common Material) 200 Aggregate Subbase Course 311(1) PCC Pavement (Plain)-Conventional Method, 200mm 500(1)a Pipe Culverts 610mm dia. (24″Ǿ) 505(5) Grouted Riprap (Class A)MA. AURORA, AURORA2,000,000.00
CONSTRUCTION OF FLOOD CONTROL, IGANG RIVER, BRGY. MALIGAYA, DILASAG, AURORA PART B General Requirements B.5a Project Billboard/ Sign Board (PGA) B.5b Project Billboard/ Sign Board (COA) B.7 Occupational Safety and health Program B.9 Mobilization/ Demobilization PART J Flood Control and Drainages PART I-A Earth Work 1701(a) Channel Excavation 1702 Structure Excavation (Refer to the Item 103) PART I-B Bank and slope Protection works 1714(a) Gabions 1714(b) MattressesDILASAG, AURORA8,900,000.00
CONSTRUCTION OF FLOOD CONTROL PROJECT, BRGY. FLORIDA, MARIA AURORA, AURORA PART A – Facilities for the Engineers A.1.1(8) Provision of field office for the Engineer PART B – Other General Requirements B.5(a) Project Signboard B.5(b) Project Billboard/Sign Board(COA) B.7 Occupational safety & Health program B.9 Mobilization and Demobilization PART J Flood Control and Drainages PART I-A Earthworks 1701(2) Surplus Common Excavation/ Channel Excavation 1701(1)a Structure  excavation (Common soil) 1704(1)a Embankment (from Excavation) PART I-B Bank and Slope 1712(2) Concrete Slope Protection 404(1) Reinforcing Steel Bar, Grade 40(Minor Structures) 405(1)a3 Structural concrete (20.68MPA, Class A 28 days) 1717(2)A1 Sheet pile (Steel Concrete Slope Protection) 1710(2)a Grouted Riprap, Class AMA. AURORA, AURORA10,000,000.00
TOTAL  

Prospective bidders should possess a valid PCAB License applicable to the contract, have completed a similar contract with a value of at least 50% of the ABC, and have key personnel and equipment available for the prosecution of the contract.  The BAC will use non-discretionary pass/fail criteria in the Eligibility Check/Screening as well as the Preliminary Examination of Bids.  The BAC will conduct post-qualification of the lowest calculated bid.

The pertinent provisions of RA 9184 and its Implementing Rules and Regulations (IRR) shall govern all particulars relative to Eligibility Statement and Screening, Bid Security, Performance Security, Pre-bidding Conference, Evaluation of Bids, Post Qualification and Award of Contract.

The schedule of BAC activities is as follows:

ActivitiesSchedule
1.  Issuance of Bid DocumentsJuly 22, 2021 – August 11, 2021 until 9:00 AM
2.  Pre-bid ConferenceJuly 30, 2021  @  10:00 AM
3.  Submission of Eligibility and BidsAugust 11, 2021 until 9:00 AM
4.  Opening of BidsAugust 11, 2021 @ 10:00 AM
  • Pre-Bid Conference/ Opening of Bids’ date is automatically re- scheduled to the next working day whenever such date is declared a holiday.

The BAC will issue to prospective bidders Eligibility Forms at BAC Secretariat Office, Capitol Compound, Baler, Aurora, upon their submission of a LOI.  Prospective bidders shall submit the Eligibility Requirements to the BAC at the said address.  They may also obtain the results of the Eligibility Check by the BAC at the same address. Bids document will be available only to prospective bidders upon payment to the Provincial Treasurer’s Office (PTO) of the Provincial Government of Aurora (PGA) of non-refundable amount for the following approved budget for the contract:

The Provincial Government of Aurora assumes no responsibility whatsoever to compensate or indemnify bidders for any expenses incurred in the preparation of the bid. Only those who have purchased the Bidding Documents shall be allowed to participate in the pre-bid conference and raise or submit written queries or clarifications.  The PGA also reserves the right to reject any or all bids, to declare the bidding a failure or waive any defect or informality and to accept bids as may be considered most advantageous to the PGA.


Goods Batch 3

The PROVINCIAL GOVERNMENT OF AURORA, through its Bids and Awards Committee (BAC), invites all eligible suppliers/manufacturers/distributors/contractors to bid for the hereunder project:

Name Of ProjectLocationApproved Budget for the Contract
Procurement of LaptopBaler, Aurora3,000,000.00
Procurement of Multifunctional Copier MachineBaler, Aurora1,300,000.00
Procurement of 4 units Brand New Multi Purpose Vehicle (MPV) Diesel Engine M/T, Euro 4 Emission standardBaler, Aurora5,200,000.00
Procurement of 4×4 Pick UP Vehicle – Diesel Engine (Silver)Baler, Aurora1,500,000.00
TOTAL  

Prospective bidders should have experience in undertaking a similar project within the last two (2) years with an amount of at least 50% of the proposed project for bidding. The Eligibility Check/Screening as well as the Preliminary Examination of Bids shall use non-discretionary “pass/fail” criteria.  Post-qualification of the lowest calculated bid shall be conducted.

All particulars relative to Eligibility Statement and Screening, Bid Security, Performance Security, Pre-bidding Conference, Evaluation of Bids, Post Qualification and Awards of Contract shall be governed by the pertinent provisions of RA 9184 and its Implementing Rules and Regulations (IRR).

The complete schedule of activities is listed, as follows:

ActivitiesSchedule
1.  Issuance of Bid DocumentsJuly 23, 2021-August 11, 2021  until 9:00 AM
2.  Pre-bid ConferenceJuly 30, 2021  @  10:00 AM
3.  Submission of Eligibility and BidsAugust 11, 2021  until 9:00 AM
4.  Opening of BidsAugust 11, 2021  @ 10:00 AM
  • Pre-Bid Conference/ Opening of Bids’ date is automatically re- scheduled to the next working day whenever such date is declared a holiday.

The BAC will issue to prospective bidders Eligibility Forms upon payment to the Provincial Treasurer’s Office of the PGA of a non-refundable amount for the following approved budget for the contract.

The Provincial Government of Aurora assumes no responsibility whatsoever to compensate or indemnify bidders for any expenses incurred in the preparation of the bid. Only those who have purchased the Bidding Documents shall be allowed to participate in the pre-bid conference and raise or submit written queries or clarifications. The PGA also reserves the right to reject any or all bids, to declare the bidding a failure or waive any defect or informality and to accept bids as may be considered most advantageous to the PGA without thereby incurring any of the following: (a) liability whatsoever to offset expenses or losses the bidder may incur in the preparation of the bids and (b) obligation to inform the affected bidder/s of the grounds for the basis of BAC’s action.


Infrastructure Project Batch 16

The PROVINCIAL GOVERNMENT OF AURORA, through its Bids and Awards Committee (BAC), invites all eligible contractors registered with and classified by the Philippine Contractors Accreditation Board (PCAB), to bid for the hereunder contract:

Name Of ProjectLocationApproved Budget for the Contract
CONSTRUCTION OF 3 ROOMS COMFORT ROOM (PHASE II) AT AURORA PROVINCIAL JAIL General Requirements I.1 MOBILIZATION AND DEMOBILIZATION I.2 Construction and Safety and Health Program I.3 Project Signboard (PGA & COA) II. Fabricated Materials and Hardwares 1010(b) Panel Doors w/ Door Frame and Complete Accessories 1010( c) Louver Wooden Door (Push and Pull) 1004(2)g Hinges Heavy duty III Reinforced Concrete 900 Reinforced Concrete V Tile Works 1018(1) Glazed Tiles and Trims 1018(2) Unglazed Tiles VI Finishing Works 1021(c-2) Non-Skid cement Finish with 6mm goove lines 1027(a) Skim Coat Finish VII Carpentry Works 1003(1)a1  ¼ thk. Marine Plywood on Metal Frame Ceiling VIII  Railings 1053(2)a2  1.5 inches Ǿ Gauge # 304 Stainless Pipe Handrail on Vertical Railing Stiffer IX  Roof and Framing Works 1014(1)b1 Prepainted Metal Sheet (Corrugated, long Span 0.5mm thk.) 1013(2)a Fabricated Metal Roofing Accessory(Ridge roll) 1013(2)b Fabricated Metal Roofing Accessory(Flashing) including Fascia Board 1013(2)c Fabricated Metal Roofing Accessory(Gutter) 1047(2)b Structural Steel purlins and Rafters 1047(2)a Structural Steel, trusses 1047(6) Metal Structure Accessories (Steel Plates) 1001(9) Storm Drainage and Downspout X Painting Works 1032(1)a Painting Works (Masonry Paintings) 1032(1)c  Painting Works (Metal Painting) 1032(1)b  Painting Works (Wood Paintings) XI Electrical Works 1103(1) Light Fixture, Wiring And Others 1001(8) Sewer Line Works 1002(6) Water Line Works 1002(5) Sanitary/Plumbing FixturesBALER, AURORA695,438.92
CONSTRUCTION OF HEALTH FACILITY WITH ISOLATION WARD AT AURORA PROVINCIAL JAIL GENERAL REQUIREMENTSLAYOUT & EXCAVATIONFILLING OF MATERIALSCONCETE & MASONRY WORKSFORMWORKS & SCAFFOLDINGROOF FRAMING & TINSMITHRYPLUMBINGWORKSELECTRICAL WORKSBALER, AURORA500,000.00
CONSTRUCTION OF TWO – STOREY MULTI-PURPOSE BUILDING, BRGY, ZABALI GENERAL REQUIREMENTSLAYOUT & EXCAVATIONFILLING OF MATERIALSCONCRETE & MASONRY WORKSFORMWORKS & SCAFFOLDINGFABRICATED MATERIALSCARPENTRY WORKS DOORS & WINDOWSPAINTING WORKSTILE WORKS (INCLUDING CR)DOWNSPOUTPLUMBING WORKSELECTRICAL WORKSBALER, AURORA5,000,000.00
CONCRETING OF ROAD AT BRGY. TABAS SPCL.I I.1 Mobilization / Demobilization I.2 Setting out and Staking I.3 Construction Safety and Health Program I.4 Project Signboard I.5 Project Signboard ( COA ) 100(1) Clearing & Grubbing ( with Stripping ) 105(1) Subgrade Preparation ( Common Material ) 200 Aggregate Subbase Course 404 Reinforcing Steel Bar, Grade 40 ( Minor Structure ) 405 Structure Concrete Class A ( minor Structure ) 103(1)a Structure Excavation ( Common Soil ) 101(2) Removal of Concrete Drainage Structure 311(1)a.2 PCCP Conventional Method ( 200mm thk. ) CASIGURAN, AURORA2,700,000.00
CONSTRUCTION OF SECURITY TOWER AT AURORA PROVINCIAL JAIL I.GENERAL REQUIREMENTS II. LAYOUT EXCAVATION AND BACK FILLING III. CONCRETE & MASONRY WORKS IV. FORMWORKS & SCAFFOLDING V. ROOF FRAMING VI. TINSMITHRY WORKSBALER, AURORA200,000.00
CONSTRUCTION OF STAGE, BRGY. IPIL I. GENERAL REQUIREMENTS II. LAYOUT & EXCAVATION III. BACK FILLING IV. CONCRETE & MASONRY WORKS V. FORMWORKS & SCAFFOLDING VI. ROOF FRAMING & TINSMITHRY WORKSDIPACULAO, AURORA500,00.00
CONSTRUCTION OF FTMR DITUMABO L. PIMENTEL PART A OTHER GENERAL REQUIREMENTS B.4 CONSTRUCTION SURVEY AND STAKING B.5(a) Project Billboard/ Sign Board (PGA) b.5b  Project Billboard/ Sign Board (COA) B.9 Mobilization/ Demobilization PART B Earthworks 100(1) Clearing & Grubbing (with stripping) 102(2)a Roadway Excavation (surplus common) 103(1)a structure Excavation (Surplus Common) 104(1)a Embankment (from borrow) 105(1) Subgrade Preparation (common material) PART C SUBBASE AND BASE COURSE 200 Aggregate Subbase Course PART D SURFACE COURSE 311(1)a.2 PCCP pavement (Plain) – Conventional Method, 200mm thk. PART E DRAINAGE AND SLOPE PROTECTION STRUCTURES 505(5) Grouted Riprap (Class A)SAN LUIS, AURORA3,000,000.00
CONSTRUCTION OF FLOOD CONTROL AT SAPSAP RIVER PART B GENERAL REQUIREMENTS B.5a Project Billboard/Signboard (PGA) B.5b Project Signboard (COA) B.7 Occupational Safety and Health Program B.9 Mobilization/Demobilization PART J FLOOD CONTROL AND DRAINAGE PART I-A EARTHWORK 1701 (a) Channel Excavation 1702 Structure Excavation (Refer to Item 103) PART I-B BANK AND SLOPE PROTECTION WORKS 1714(a) Gabions 1714(b) MattressesBRGY. DILAGUIDI, DILASAG, AURORA10,000,000.00
CONSTRUCTION OF FLOOD CONTROL PROJECT CASALOGAN RIVER, PART B GENERAL REQUIREMENTS B.5a Project Billboard/Signboard (PGA) B.5b Project Signboard (COA) B.7 Occupational Safety and Health Program B.9 Mobilization/Demobilization PART J FLOOD CONTROL AND DRAINAGE PART I-A EARTHWORK 1702 Structure Excavation (Refer to Item 103, Vol. II Blue book) 1704(1)b Embankment from Borrow PART I-A EARTHWORK 1712(2) concrete slope protection 404 Reinforcing Steel Bars G40 405 Structural Concrete Class A 1717(2)a1 Sheet Pile (steel slope protection) 1710(2)a Grouted Riprap, Class ACASIGURAN, AURORA10,000,000.00
COMPLETION OF MULTI-PURPOSE BUILDING BRGY. SAN JUAN SPCL –I GENERAL REQUIREMENTS (PGA & COA SIGN BOARD, CONSTRUCTION AND SAFETY & HEALTH PROGRAM AND OTHER REQUIRED DOCUMENTS SPCL –II MOBILIZATION AND DEMOBILIZATION SPCL-III CHIPPING OF CONCRETE PAVEMENT 804(1)c EMBANKMENT FROM COMMON BORROW 1046(2)a1 100mm CHB NON-LOAD BEARING (INCLUDING REINFORCING STEAL) 900 REINFORCED CONCRETE 902(1)a1 REINFORING STEEL OF REINFORCED CONCRETE STRUCTURES, GRADE 40 903(2) FORMWORKS AND FALSEWORKS 1047(2)b STRUCTURAL STEEL PURLINS 1047(2)a STRUCTURAL STEEL, TRUSSES STRUTS 1047(6) METAL STRUCTURE ACCESSORIES (STEEL PLATES) 1047(7)b METAL STRUCTURE ACCESSORIES (SAGRODS) 1047(4) METAL STRUCTURE ACCESSORIES (CROSSBRACING) 1047(3)c METAL STRUCTURE ACCESSORIES (TURNBUCKLE) 1014(1)b1 PREPAINTED METAL SHEETS (PREPAINTED, LONG SPAN, 0.5MM THK) 1032(1)c PAINTING WORKS (METAL PAINTING) 1032(1)a PAINTING WORKS (MASONRY PAINTING) SPCL IV CONSTRUCTION OF BASKETBALL RING & BOARD W/ ACCESSORIES & FRAMES (2 SETS)MA. AURORA, AURORA2,500,000.00
COMPLETION OF OPEN MULTI-PURPOSE HALL, BRGY. DIANED General Requirements (PGA & COA SIGN BOARD, CONSTRUCTION AND  SAFETY & HEALTH PROGRAM AND OTHER REQUIRED DOCUMENTS) Concrete & Masonry Works     III.     Formworks, & Scaffolding     IV.     Cladding     V.       Painting Works     VI.      Electrical Works.DIPACULAO, AURORA1,500,000.00
CONCRETING OF ROAD NETWORK, GINTONG PANGARAP VILLAGE (0.50KM), POBLACION ZONE II Part A  Facilities for the Engineers A1.1(8) Provission of field office for the Engineer Part B Other General Requirements  I.1 Mobilization/Demobilization I.2  Setting out and Staking I.3  Construction safety and Health Program I.4  Project Signboard I.5  Project Signboard (COA) Part C Earthworks 100(1)  Clearing & Grubbing(with Stripping) 103(1)a Structure Excavation (Common Soil) 104(1)a Embankment (from borrow) 105(1)  Subgrade Preparation (Common Material) Part D Subbase and Base Course 200 Aggregate Subbase Course Part C Surface Course 311(1)a2 PCCP Conventional Method (200mm thk.) Part F  Slope Protection 505(5) Structures, Grouted Riprap (Class A).DINALUNGAN, AURORA4,000,000.00
CONSTRUCTION OF PERIMETER FENCE, BRGY. NORTH POBLACION General Requirements (PGA & COA SIGN BOARD, CONSTRUCTION AND SAFETY & HEALTH PROGRAM AND OTHER REQUIRED DOCUMENTS), Concrete & Masonry Works Formworks, & Scaffolding Painting WorksFabricated Materials Electrical WorksDipaculao, Aurora750,000.00
CONSTRUCTION OF POWERHOUSE AT PROVINCIAL CAPITOL Mobilization/Demobilization Temporary Facilities and Billboard Safety and Health Removal of Structures and Obstraction Layout & Excavation, Backfilling Formworks & Scaffolding, Concrete & Masonry works, Water proofing Works, Cable Trench and grating cover, doors and windows, Exhaust air duct generator, painting works, plumbingworks, electrical worksBaler, Aurora3, 000,000.00
CONSTRUCTION OF NEW ROAD OPENING/ ROAD GRAVELLING FRM. SO. UPPER TUNGED, BRGY. ESPERANZA   SPCL.I.   I.1 MOBILIZATION/ DEMOBILAZATION   I.2 SETTING OUT AND STAKING   I.3 CONSTRUCTION SAFETY AND HEALTH PROGRAM   I.4 PROJECT SIGNBOARD   I.5 PROJECT BILLBOARD / SIGNBOARD (COA)   104(1)a EMBANKMENT (from  borrow)DILLASAG, AURORA1,500,000.00  
REHABILITION OF DINADIAWAN COMMUNAL IRRIGATION SYSTEM, BRGY. DINADIAWAN   I GENERAL REQUIREMENTS   I.1 MOBILIZATION AND DEMOBILIZATION   I.2 SETTING OUT AND STAKING   I.3 CONSTRUCTION SAFETY AND HEALTH   I.4 PROJECT SIGN BOARD (COA)   I.5 PROJECT SIGN BOARD (PGA)   103(1)a STRUCTURE EXCAVATION (Common Soil)   104(4) EARTH BERM   404 REINFORCING STEEL BAR. GRADE 40   405 STRUCTURAL CONCRETE CLASS A AND PLASTERING   511(1) GABIONS   511(2) MATTRESSDIPACULAO, AURORA2,500,000.00
CONSTRUCTION OF LIGAS FTMR, BRGY. DIMASESET, DILASAG, AURORA   SPCL.I   I.1 MOBILIZATION / DEMOBILIZATION   I.2 SETTING OUT AND STAKING   I.3 CONSTRUCTION SAFETY AND HEALTH PROGRAM   I.4 PROJECT SIGN BOARD   I.5 PROJECT BILLBOARD / SIGNBOARD (COA)   104(1)a EMBANKMENT (from  borrow)DILASAG, AURORA2,000,000.00
CONSTRUCTION OF FARM TO MARKET ROAD SO. IGANG, BRGY. MALIGAYA, DILASAG AURORA   SPCL. I   I.1 MOBILIZATION / DEMOBILIZATION   I.2 SETTING OUT AND STAKING   I.3 CONSTRUCTION SAFETY AND HEALTH PROGRAM   I.4 PROJECT SIGN BOARD   I.5 PROJECT BILLBOARD / SIGNBOARD ( COA )   100(1) CLEARING & GRUBBING ( with stripping )   104(1)a EMBANKMENT (from  borrow)   103(1)a STRUCTURE EXCAVATION ( COMMON SOIL)   404 REINFORCING STEEL BAR, GRADE 40 ( Minor Structures )   405 STRUCTURE CONCRETE CLASS A  ( Minor Structures )   500(1) PIPE CULVERT, 910MM DIA. (36” DIA.)DILASAG, AURORA1,000,000.00
CONSTRUCTION OF MULTI PURPOSE HALL (PHASE II), BRGY. L. PIMENTEL GENERAL REQUIREMENTSDEMOLITION  AND DISMANTLINGREINFORCED  CONCTRETE WORKSMASONRY WORKSTILE WORKSDOORS AND WINDOWSCEILING WORKSROOF WORKSPLUMBING WORKSSEPTIC TANK AND CATCH BASINELECTRICAL WORKSPAINTING WORKSSAN LUIS, AURORA1,200,000.00
CONSTRUCTION OF FLOOD CONTROL AT PACUGAO RIVER PHASE  II CAB EAST –CAB WEST SECTION   PART A –  FACILITIES FOR THE ENGINEERS A.1.1(8) PROVISION FIELD OFFICE FOR THE ENGINEER   PART B – OTHER GENERAL REQUIREMENTS B.5(a) PROJECT SIGN BOARD B.5(b) PROJECT BILLBOARD / SIGNBOARD (COA) B.7 OCCUPATIONAL SAFETY & HEALTH PROGRAM B.9 MOBILIZATION AND DEMOBILIZATION   PART J FLOOD CONTROL AND DRAINAGES   PART I-A EARTHWORKS 1701(2) SURPLUS COMMON EXCAVATION / CHANNEL EXCAVATION 1701(1)a STRUCTURE EXCAVATION (Common Soil) 1704(1)a EMBANKMENT ( from Excavation )   PART I-B BANK AND SLOPE 1712(2) CONCRETE SLOPE PROTECTION 404(1)a REINFORCING STEEL BAR, GRADE 40 (Minor Structures) 405(1)a3 STRUCTURE CONCRETE (20.68 Mpa, Class A, 28 Days) 1714(b) MATTRESSES 1710(2)a GROUTED RIPRAP, CLASS AMARIA AURORA, AURORA10,000,000.00
CONSTRUCTION OF HOUSING FACILITY FOR ECO-DRYER GENERAL REQUIREMENTSLAYOUT, EXCAVATION & BACKFILLING FILLING OF MATERIALS CONCRETE WORKSFORMWORKS & SCAFFOLDING ROOF FRAMING & TINSMITHRY WORKSDIPACULAO, AURORA300,000.00
FLOOD CONTROL OF BANCO-PACUGAO RIVER (GAVION TYPE) PUROK 7, BRGY. BANCO, MARIA AURORA   SPCL. I GENERAL REQUIREMENTS   B.9 MOBILIZATION / DEMOBILIZATION
  B.7 CONSTRUCTION SAFETY ANF HEALTH  PROGRAM   B.5 PROJECT SIGN BOARD   103(1)a STRUCTURE EXCAVATION ( Common Soil )   104(1)a EMBANKMENT FROM ROADWAY  EXCAVATION   511(1) GABIONS   511(2) MATRESSES
MARIA AURORA, AURORA3,000,000.00
TOTAL  

Prospective bidders should possess a valid PCAB License applicable to the contract, have completed a similar contract with a value of at least 50% of the ABC, and have key personnel and equipment available for the prosecution of the contract.  The BAC will use non-discretionary pass/fail criteria in the Eligibility Check/Screening as well as the Preliminary Examination of Bids.  The BAC wiCOll conduct post-qualification of the lowest calculated bid.

The pertinent provisions of RA 9184 and its Implementing Rules and Regulations (IRR) shall govern all particulars relative to Eligibility Statement and Screening, Bid Security, Performance Security, Pre-bidding Conference, Evaluation of Bids, Post Qualification and Award of Contract.

The schedule of BAC activities is as follows:

ActivitiesSchedule
1.  Issuance of Bid DocumentsAugust 17, 2021 – September 6, 2021  until 9:00 AM
2.  Pre-bid ConferenceAugust 25, 2021  @  10:00 AM
3.  Submission of Eligibility and BidsSeptember 6, 2021   until 9:00 AM
4.  Opening of BidsSeptember 6, 2021   @ 10:00 AM
  • Pre-Bid Conference/ Opening of Bids’ date is automatically re- scheduled to the next working day whenever such date is declared a holiday.

The BAC will issue to prospective bidders Eligibility Forms at BAC Secretariat Office, Capitol Compound, Baler, Aurora, upon their submission of a LOI.  Prospective bidders shall submit the Eligibility Requirements to the BAC at the said address.  They may also obtain the results of the Eligibility Check by the BAC at the same address. Bids document will be available only to prospective bidders upon payment to the Provincial Treasurer’s Office (PTO) of the Provincial Government of Aurora (PGA) of non-refundable amount for the following approved budget for the contract:

The Provincial Government of Aurora assumes no responsibility whatsoever to compensate or indemnify bidders for any expenses incurred in the preparation of the bid. Only those who have purchased the Bidding Documents shall be allowed to participate in the pre-bid conference and raise or submit written queries or clarifications.  The PGA also reserves the right to reject any or all bids, to declare the bidding a failure or waive any defect or informality and to accept bids as may be considered most advantageous to the PGA.


Goods Batch 4

The PROVINCIAL GOVERNMENT OF AURORA, through its Bids and Awards Committee (BAC), invites all eligible suppliers/manufacturers/distributors/contractors to bid for the hereunder project:

Name Of ProjectLocationApproved Budget for the Contract
PROCUREMENT OF OFFICE, JANITORIAL, IT AND OTHER SUPPLIESBaler, Aurora2,003,159.00
PROCUREMENT OF OFFICE SUPPLIESBaler, Aurora1,820,000.00
TOTAL  

Prospective bidders should have experience in undertaking a similar project within the last two (2) years with an amount of at least 50% of the proposed project for bidding. The Eligibility Check/Screening as well as the Preliminary Examination of Bids shall use non-discretionary “pass/fail” criteria.  Post-qualification of the lowest calculated bid shall be conducted.

All particulars relative to Eligibility Statement and Screening, Bid Security, Performance Security, Pre-bidding Conference, Evaluation of Bids, Post Qualification and Awards of Contract shall be governed by the pertinent provisions of RA 9184 and its Implementing Rules and Regulations (IRR).

The complete schedule of activities is listed, as follows:

ActivitiesSchedule
1.  Issuance of Bid DocumentsSeptember 7, 2021-September 27, 2021  until 9:00 AM
2.  Pre-bid ConferenceSeptember 15, 2021  @  10:00 AM
3.  Submission of Eligibility and BidsSeptember 27, 2021  until 9:00 AM
4.  Opening of BidsSeptember 27, 2021  @ 10:00 AM

.

  • Pre-Bid Conference/ Opening of Bids’ date is automatically re- scheduled to the next working day whenever such date is declared a holiday.

The BAC will issue to prospective bidders Eligibility Forms upon payment to the Provincial Treasurer’s Office of the PGA of a non-refundable amount for the following approved budget for the contract.

The Provincial Government of Aurora assumes no responsibility whatsoever to compensate or indemnify bidders for any expenses incurred in the preparation of the bid. Only those who have purchased the Bidding Documents shall be allowed to participate in the pre-bid conference and raise or submit written queries or clarifications. The PGA also reserves the right to reject any or all bids, to declare the bidding a failure or waive any defect or informality and to accept bids as may be considered most advantageous to the PGA without thereby incurring any of the following: (a) liability whatsoever to offset expenses or losses the bidder may incur in the preparation of the bids and (b) obligation to inform the affected bidder/s of the grounds for the basis of BAC’s action.


Infrastructure Project Batch 17

The PROVINCIAL GOVERNMENT OF AURORA, through its Bids and Awards Committee (BAC), invites all eligible contractors registered with and classified by the Philippine Contractors Accreditation Board (PCAB), to bid for the hereunder contract:

Name Of ProjectLocationApproved Budget for the Contract
REPAIR/ IMPROVEMENT OF DAY CARE CENTER, BRGY. DIANED I. General Requirements II. Formworks & Scafolding III. Carpentry Works IV. Painting Works V. Tile Works (Cr) IV. Roofing Works VI. Plumbimg Works VII. Doors VIII. Electrical WorksDipaculao, Aurora  500,000.00
REBLOCKING OF PROV. ROAD INFRONT OF DAES ELEMENTARY SCHOOL, BRGY. MALIGAYA, DILASAG, AURORA SPCL.I I.1 Mobilization/ Demobilization I.2 Setting out and staking I.3 Construction Safety and Health Program I.4 Project sign board I.5 Project sign board (COA) 101(3)a.1 Removal of Existing Concrete Pavement (0.23m thk.) 105(2) Subgrade Preparation(Existing Pavement) 200 Aggregate Subbase Course 311(1)a.2 PCCP Conventional Method (200mm thk)DILASAG, AURORA5,000,000.00
FARM TO MARKET ROAD, BRGY. PUNGLO TO DIAMAN, MARIA, AURORA SPCL.I General Requirements B.9 Mobilization/ Demobilization B.7 Construction Safety and Health Program B.5 Project Signboard 102(2)b Roadway Excavation(Surplus common) 103(1)a  Structure Excavation (Common Soil) 104(1)b Embankment (from Borrow) 105(1) Subgrade Preparation (Common Material) 200 Aggregate Subbase Course 311(1) PCC Pavement (Plain)-Conventional Method, 200mm 500(1)a Pipe Culverts 610mm dia. (24″Ǿ) 505(5) Grouted Riprap (Class A)MA. AURORA, AURORA2,000,000.00
REHABILITATION OF ARTS ACADEMY BUILDING IN RESERVA BALER, AURORA, BRGY. RESERVA I.Mobilization/Demobilization II. Temporary Facilities/ Billboard III. Safety and Health IV. Site Works V. Tileworks VI. Doors and Windows VII.   Steel Works VIII. Roof and Framing Works IX. Plumbing Works X. Paiting Works.BALER, AURORA1,000,000.00
REPLACEMENT OF ROOFING AT PSWDO, COMELEC, PHRMO & PEO, CAPITOL COMPOUND, BRGY. SUKLAYIN I.Mobilization/Demobilization II.Site Works III.Roofing WorksBALER, AURORA683,583.00
IMPROVEMENT OF PERIMETER FENCE AT SUB CAPITOL  CASIGURAN AURORA, SUB-CAPITOL, BRGY, CALANGCUASAN  I. Mobilization/Demobilization II. Temporary Facilities/ Billboard III .Safety and Health IV .Site Works  V. Formworks and Scafolding VI. Masonry Works VII. Concrete Works  VIII. Steel Works IX. PaitingCASIGURAN, AURORA1,000,000.00
CONSTRUCTION OF FLOOD CONTROL PROJECT CASALOGAN RIVER, PART B GENERAL REQUIREMENTS B.5a Project Billboard/Signboard (PGA) B.5b Project Signboard (COA) B.7 Occupational Safety and Health Program B.9 Mobilization/Demobilization PART J FLOOD CONTROL AND DRAINAGE PART I-A EARTHWORK 1702 Structure Excavation (Refer to Item 103, Vol. II Blue book) 1704(1)b Embankment from Borrow PART I-A EARTHWORK 1712(2) concrete slope protection 404 Reinforcing Steel Bars G40 405 Structural Concrete Class A 1717(2)a1 Sheet Pile (steel slope protection) 1710(2)a Grouted Riprap, Class ACASIGURAN, AURORA10,000,000.00
CONSTRUCTION OF FLOOD CONTROL AT PACUGAO RIVER PHASE  II CAB EAST –CAB WEST SECTION   PART A –  FACILITIES FOR THE ENGINEERS A.1.1(8) PROVISION FIELD OFFICE FOR THE ENGINEER   PART B – OTHER GENERAL REQUIREMENTS B.5(a) PROJECT SIGN BOARD B.5(b) PROJECT BILLBOARD / SIGNBOARD (COA) B.7 OCCUPATIONAL SAFETY & HEALTH PROGRAM B.9 MOBILIZATION AND DEMOBILIZATION   PART J FLOOD CONTROL AND DRAINAGES   PART I-A EARTHWORKS 1701(2) SURPLUS COMMON EXCAVATION / CHANNEL EXCAVATION 1701(1)a STRUCTURE EXCAVATION (Common Soil) 1704(1)a EMBANKMENT ( from Excavation )   PART I-B BANK AND SLOPE 1712(2) CONCRETE SLOPE PROTECTION 404(1)a REINFORCING STEEL BAR, GRADE 40 (Minor Structures) 405(1)a3 STRUCTURE CONCRETE (20.68 Mpa, Class A, 28 Days) 1714(b) MATTRESSES 1710(2)a GROUTED RIPRAP, CLASS AMARIA AURORA, AURORA10,000,000.00
CONCRETING OF ROAD NETWORK, GINTONG PANGARAP VILLAGE (0.50KM), POBLACION ZONE II Part A  Facilities for the Engineers A1.1(8) Provission of field office for the Engineer Part B Other General Requirements  I.1 Mobilization/Demobilization I.2  Setting out and Staking I.3  Construction safety and Health Program I.4  Project Signboard I.5  Project Signboard (COA) Part C Earthworks 100(1)  Clearing & Grubbing(with Stripping) 103(1)a Structure Excavation (Common Soil) 104(1)a Embankment (from borrow) 105(1)  Subgrade Preparation (Common Material) Part D Subbase and Base Course 200 Aggregate Subbase Course Part C Surface Course 311(1)a2 PCCP Conventional Method (200mm thk.) Part F  Slope Protection 505(5) Structures, Grouted Riprap (Class A).DINALUNGAN, AURORA4,000,000.00
TOTAL  

Prospective bidders should possess a valid PCAB License applicable to the contract, have completed a similar contract with a value of at least 50% of the ABC, and have key personnel and equipment available for the prosecution of the contract.  The BAC will use non-discretionary pass/fail criteria in the Eligibility Check/Screening as well as the Preliminary Examination of Bids.  The BAC will conduct post-qualification of the lowest calculated bid.

The pertinent provisions of RA 9184 and its Implementing Rules and Regulations (IRR) shall govern all particulars relative to Eligibility Statement and Screening, Bid Security, Performance Security, Pre-bidding Conference, Evaluation of Bids, Post Qualification and Award of Contract.

The schedule of BAC activities is as follows:

ActivitiesSchedule
1.  Issuance of Bid DocumentsSeptember 7, 2021 – September 27, 2021 until 9:00 AM
2.  Pre-bid ConferenceSeptember 15, 2021@  10:00 AM
3.  Submission of Eligibility and BidsSeptember 27, 2021 until 9:00 AM
4.  Opening of BidsSeptember 27, 2021 @ 10:00 AM
  • Pre-Bid Conference/ Opening of Bids’ date is automatically re- scheduled to the next working day whenever such date is declared a holiday.

The BAC will issue to prospective bidders Eligibility Forms at BAC Secretariat Office, Capitol Compound, Baler, Aurora, upon their submission of a LOI.  Prospective bidders shall submit the Eligibility Requirements to the BAC at the said address.  They may also obtain the results of the Eligibility Check by the BAC at the same address. Bids document will be available only to prospective bidders upon payment to the Provincial Treasurer’s Office (PTO) of the Provincial Government of Aurora (PGA) of non-refundable amount for the following approved budget for the contract:

The Provincial Government of Aurora assumes no responsibility whatsoever to compensate or indemnify bidders for any expenses incurred in the preparation of the bid. Only those who have purchased the Bidding Documents shall be allowed to participate in the pre-bid conference and raise or submit written queries or clarifications.  The PGA also reserves the right to reject any or all bids, to declare the bidding a failure or waive any defect or informality and to accept bids as may be considered most advantageous to the PGA.


Notice of Award

CONTRACT NO. INF2020-124 CONSTRUCTION OF MULTI-PURPOSE HALL IN BRGY. BAGTU, MARIA AURORA, AURORA – DECEMBER 28, 2020


CONTRACT NO. INF2021-07 CONCRETING OF BANGCO-FLORIDA IN MARIA AURORA, AURORA – FEBRUARY 8, 2021


CONTRACT NO. INF2020-127 CONSTRUCTION OF MULTI-PURPOSE HALL (EXTENSION BUILDING) IN BRGY. BAYANIHAN, MARIA AURORA, AURORA – DECEMBER 28, 2020


CONTRACT NO. INF2021-05 CONSTRUCTION OF BLOOD BANK, PHILIPPINE NATIONAL RED CROSS IN BALER, AURORA – FEBRUARY 8, 2021


CONTRACT NO. INFRA2021-03 CONCRETING OF ROAD IN BRGY. 02, SAN LUIS, AURORA – FEBRUARY 8, 2021


CONTRACT NO. INFRA2021-10 CONSTRUCTION OF TWO-STOREY MULTI-PURPOSE HALL IN BRGY. 02, CASIGURAN, AURORA – FEBRUARY 8, 2021


CONTRACT NO. INFRA2020-118 CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE II) IN BRGY. CARAGSACAN, DINGALAN, AURORA – DECEMBER 17, 2020


CONTRACT NO. INFRA2021-06 BRGY. POTABLE WATER SYSTEM IN DIAMANEN, DIPACULAO, AURORA – FEBRUARY 8, 2021


CONTRACT NO. INFRA2021-06 BRGY. POTABLE WATER SYSTEM IN DIAMANEN, DIPACULAO, AURORA – FEBRUARY 8, 2021


CONTRACT NO. INFRA2021-04 COMPLETION OF BRGY. POTABLE WATER SYSTEM IN DIBUTUNAN, DIPACULAO, AURORA – FEBRUARY 8, 2021


CONTRACT NO. INFRA2020-132 COMPLETION OF MULTI-PURPOSE BUILDING (COVERED COURT) IN BRGY. DICABASAN, DILASAG, AURORA – DECEMBER 28, 2020


CONTRACT NO. INFRA2021-08 CONSTRUCTION OF MULTI-PURPOSE HALL PHASE II IN BRGY. DIMANAYAT, SAN LUIS, AURORA – FEBRUARY 8, 2021


CONTRACT NO. INFRA2020-126 REPAIR OF DIMASINGAN BRIDGE APPROACH CASIGURAN-DILASAG PROVINCIAL ROAD IN CASIGURAN-DILASAG, AURORA – DECEMBER 28, 2020


CONTRACT NO. INFRA2020-125 IMPROVEMENT OF POTABLE WATER SYSTEM AT SOURCE (CONSTRUCTION OF ADDITIONAL CAPTURE BOX) IN BRGY. DITAWINI, DINALUNGAN, AURORA – DECEMBER 28, 2020


CONTRACT NO. INFRA2020-120 COMPLETION OF MULTI-PURPOSE HALL IN BRGY. GUPA, DIPACULAO, AURORA – DECEMBER 28, 2020


CONTRACT NO. INFRA2020-121 CONSTRUCTION OF MULTI-PURPOSE BUILDING, IP TRAINING CENTER IN BRGY. RESERVA, BALER, AURORA – DECEMBER 28, 2020


CONTRACT NO. INFRA2020-128 CONSTRUCTION OF WOMEN’S DEVELOPMENT CENTER IN BRGY. MARIKIT, CASIGURAN, AURORA – DECEMBER 28, 2020


CONTRACT NO. INFRA2020-131 CONSTRUCTION OF 300 METERS DRAINAGE CANAL WITH COVER AT YÑIGO ST., BRGY. MASAGANA IN BRGY. MASAGANA, DILASAG, AURORA – DECEMBER 28, 2020


CONTRACT NO. INFRA2020-119 CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE III) IN BRGY. MATAWE, DINGALAN, AURORA – DECEMBER 17, 2020


CONTRACT NO. INFRA2020-122 CONCRETING OF LOCAL ROADS IN BRGY. OBLIGACION, BALER, AURORA – DECEMBER 28, 2020


CONTRACT NO. INFRA2020-122 CONCRETING OF LOCAL ROADS IN BRGY. OBLIGACION, BALER, AURORA – DECEMBER 28, 2020


CONTRACT NO. INFRA2020-133 CONSTRUCTION/IMPROVEMENT OF SUGUIT FMR IN BRGY. SUGUIT, BARIA AURORA, AURORA – DECEMBER 28, 2020


CONTRACT NO. INFRA2021-02 IMPROVEMENT OF TOURISM SITE AT BRGY. PALTIC (WHITE BEACH GOING TO MOUNTAIN VIEW) IN DINGALAN, AURORA – FEBRUARY 8, 2021


Contract No. INFRA2021-14 Construction of Flood Control Project, Casalogan River in casiguran, Aurora – March 15, 2021


Contract No. INFRA2021-16 Completion of Multi-Purpose Building in Brgy. Detailen, Maria Aurora, Aurora – April 5, 2021


Contract No. INFRA2021-18 Completion of Multi-Purpose Building in Brgy. Dibutunan, Dipaculao, Aurora – April 5, 2021


Contract No. INFRA2021-23 Completion of Multi-Purpose Building in Brgy. Diome, Maria Aurora, Aurora – April 5, 2021


Contract No. INFRA2021-12 Construction of FTMR, Ditumabo-L.Pimentel in San Luis, Aurora – March 15, 2021


Contract No. INFRA2021-13 Flood Control Project in Brgy. Lual, Casiguran, Aurora – March 15, 2021


Contract No. INFRA2021-24 Completion of Multi-Purposed Building in Brgy. Malasin, Maria Aurora, Aurora – April 5, 2021


Contract No. INFRA2021-20 Completion of Multi-Purposed Building in Brgy. Masagana, Dilasag, Aurora – April 5, 2021


Contract No. INFRA2021-21 Completion of Multi-Purposed Building in Brgy. Ramada, Maria Aurora, Aurora – April 5, 2021


Contract No. INFRA2021-19 Construction of Flood Control at Salay Creek (Phase II) in Dipaculao, Aurora – April 5, 2021


Contract No. INFRA2021-22 Completion of Multi-Purpose Building in Brgy. San Juan, Maria Aurora, Aurora – April 5, 2021


Contract No. INFRA2021-15 Construction of Flood Control at Sapsap River in Brgy. Dilaguidi, Dilasag, Aurora – March 15, 2021


Contract No. INFRA2021-11 Construction of Warehouse with MPDP in Brgy. Ura, Dilasag, Aurora – March 15, 2021


Contract No. INFRA2021-29 Completion of Multi-Purpose Building in Brgy. Bangco, Maria Aurora, Aurora – April 7, 2021


Contract No. INFRA2021-27 Construction of Drainage Canal at Brgy. Site Proper in Brgy. Dicabasan, Dilasag, Aurora – April 7, 2021


Contract No. INFRA2021-28 Completion of Multi-Purpose Building in Brgy. Esperanza, Dilasag, Aurora – April 7, 2021


Contract No. INFRA2021-30 Completion of Multi-Purposed Building in Brgy. Galintuja, Maria Aurora, Aurora – April 7, 2021


Contract No. INFRA2021-26 Construction of Multi-Purpose Building in Brgy. Lawang, Dilasag, Aurora – April 7, 2021


Contract No. INFRA2021-25 Completion of Multi-Purpose Building in Brgy. Real, San Luis, Aurora – April 7, 2021


Contract No. INFRA2021-35 Completion of Multi-Purpose Building in Brgy. Dibacong, Casiguran, Aurora – April 15, 2021


Contract No. INFRA2021-32 Construction of Multi-Purpose Building in Brgy. Dibut, San Luis, Aurora – April 15, 2021


Contract No. INFRA2021-34 Completion of Multi-Purpose Buiding in Brgy. Dimabuno, Dipaculao, Aurora – April 15, 2021


Contract No. INFRA2021-33 Completion of Multi-Purposed Building in Brgy. San Leonardo, Maria Aurora, Aurora – April 15, 2021


Contract No. INFRA2021-40 Flood Control Project in Brgy. 01, Casiguran, Aurora – April 29, 2021


Contract No. INFRA2021-37 Completion of Multi-Purposed Building in Brgy. Decoliat, Maria Aurora, Aurora – April 29, 2021


Contract No. INFRA2021-38 Construction of Two-Storey Multi-Purpose Building in Brgy. Dibaraybay, Dinalungan, Aurora – April 29, 2021


Contract No. INFRA2021-35 Completion of Multi-Purposed Building in Brgy. Dikildit, Maria Aurora, Aurora – April 29, 2021


Contract No. INFRA2021-36 Completion of Multi-Purpose Building in Brgy. Dimaseset, Dilasag, Aurora – April 29, 2021


Contract No. INFRA2021-39 Completion of Multi-Purposed Building in Brgy. Suguit, Maria Aurora, Aurora – April 29, 2021


Contract No. INFRA2021-42 Replacement of Dimalang Bridge (12m) Sta. Ko, 353 + 096 to Ko. 353 + 104.5, Casiguran-Dilasag Provincial Road in Casiguran, Aurora – May 7, 2021


Contract No. INFRA2021-41 Completion of Multi-Purpose Building in Brgy. Umiray, Dingalan, Aurora – May 7, 2021


Contract No. INFRA2021-43 Construction of Bridge at Amutan River in Brgy. Butas na Bato, Dingalan, Aurora – May 18, 2021


Contract No. INFRA2021-47 Completion of day care center II in Brgy. Ditale, Dipaculao, Aurora – May 21, 2021


Contract No. INFRA2021-44 Reblocking of road going to Maria Aurora Community Hospital (MACH) in Brgy. 01, Maria Aurora, Aurora – May 21, 2021


Contract No. INFRA2021-48 Construction of Multi-purpose building/additional repair bay, parking area for H.E., evacuation area for sports events PEPO in Brgy. Suklayin, Baler, Aurora – May 21, 2021


Contract No. INFRA2021-45 Establishment of Women in Integrated Development and Empowerment Center (WIDE) in ATC Compound, Brgy. Calabuanan, Baler, Aurora – May 21, 2021


Contract No. INFRA2021-52 Construction of Multi-purpose Hall Phase II in Brgy. Dibalo, San Luis, Aurora – May 27, 2021


Contract No. INFRA2021-50 Construction of Flood Control in Brgy. Dimabuno, Dipaculao, Aurora – May 27, 2021


Contract No. INFRA2021-49 Construction of Multi-purpose Hall in Brgy. Obligacion, Baler, Aurora – May 27, 2021


Contract No. INFRA2021-51 Construction of Multi-purpose building in Brgy. Sta. Lucia, Maria, Aurora, Aurora – May 27, 2021


Contract No. INFRA2021-56 Construction of Tribal hall in Brgy. Abuleg, Dinalungan, Aurora – July 15, 2021


Contract No. INFRA2021-54 Construction of FTMR (Phase III) in So, Amurawen, Brgy. Esperanza, Dilasag, Aurora – July 15, 2021


Contract No. INFRA2021-55 Construction of Multi-purpose building (Phase III) in So, Diotorin, Brgy. Dibayabay, San Luis, Aurora – July 15, 2021


Contract No. INFRA2021-57 Construction of Potable Water System in Brgy. Ditale, Dipaculao, Aurora – July 15, 2021


Contract No. INFRA2021-58 Completion of open Multi-purpose hall in Brgy. Ipil, Dipaculao, Aurora – July 15, 2021


Contract No. INFRA2021-53 Construction of Central Terminal in Brgy. Masagana, Dilasag, Aurora – July 15, 2021


Contract No. INFRA2021-59 Improvement of Salay, Dipaculao provincial road in Brgy. Salay, Dipaculao, Aurora – July 15, 2021



Notice to Proceed

CONTRACT NO. 2020-11-102-20DF (INFRA) CONSTRUCTION OF MULTI-PURPOSE HALL IN BRGY. BAGTU, MARIA AURORA, AURORA


CONTRACT NO. 2021-01-04-18DF (INFRA) CONCRETING OF BANGCO-FLORIDA IN MARIA, AURORA, AURORA


CONTRACT NO. 2020-11-104-20DF (INFRA) CONSTRUCTION OF MULTI-PURPOSE HALL (EXTENSION BUILDING) IN BRGY. BAYANIHAN, MARIA AURORA, AURORA


CONTRACT NO. 2021-01-05-17DF (INFRA) CONCRETING OF ROAD IN BRGY. 02, SAN LUIS, AURORA


CONTRACT NO. 2020-11-91-GF (INFRA) CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE II) IN BRGY. CARAGSACAN, DINGALAN, AURORA


CONTRACT NO. 2021-01-01-20DF (INFRA) BRGY. POTABLE WATER SYSTEM IN DIAMANEN, DIPACULAO, AURORA


CONTRACT NO. 2021-01-08-18DF (INFRA) CONSTRUCTION OF MULTI-PURPOSE HALL IN BRGY. DIBAYABAY, SAN LUIS, AURORA


CONTRACT NO. 2021-01-02-20DF (INFRA) COMPLETION OF BRGY. POTABLE WATER SYSTEM IN DIBUTUNAN, DIPACULAO, AURORA


CONTRACT NO. 2020-11-112-19DF (INFRA) COMPLETION OF MULTI-PURPOSE BUILDING (COVERED COURT) IN BRGY. DICABASAN, DILASAG, AURORA


CONTRACT NO. 2021-01-07-20DF (INFRA) CONSTRUCTION OF MULTI-PURPOSE HALL PHASE II IN BRGY. DIMANAYAT, SAN LUIS, AURORA


CONTRACT NO. 2020-11-101-20DF (INFRA) REPAIR OF DIMASINGAN BRIDGE APPROACH CASIGURAN-DILASAG PROVINCIAL ROAD IN CASIGURAN-DILASAG, AURORA


CONTRACT NO. 2020-11-103-20DF (INFRA) IMPROVEMENT OF POTABLE WATER SYSTEM AT SOURCE (CONSTRUCTION OF ADDITIONAL CAPTURE BOX) IN BRGY. DITAWINI, DINALUNGAN, AURORA


CONTRACT NO. 2020-11-97-18DF (INFRA) COMPLETION OF MULTI-PURPOSE HALL IN BRGY. GUPA, DIPACULAO, AURORA


CONTRACT NO. 2020-11-98-18DF (INFRA) CONSTRUCTION OF MULTI-PURPOSE BUILDING, IP TRAINING CENTER IN BRGY. RESERVA, BALER, AURORA


CONTRACT NO. 2020-11-106-20DF (INFRA) CONSTRUCTION OF WOMEN’S DEVELOPMENT CENTER IN BRGY. MARIKIT, CASIGURAN, AURORA


CONTRACT NO. 2020-11-109-18DF (INFRA) CONSTRUCTION OF 300 METERS DRAINAGE CANAL WITH COVER AT YÑIGO ST., BRGY. MASAGANA IN BRGY. MASAGANA, DILASAG, AURORA


CONTRACT NO. 2020-11-90-DF (INFRA) CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE III) IN BRGY. MATAWE, DINGALAN, AURORA


CONTRACT NO. 2020-11-99-18DF (INFRA) CONCRETING OF LOCAL ROADS IN BRGY. OBLIGACION, BALER, AURORA


CONTRACT NO. 2021-01-10-20DF (INFRA) IMPROVEMENT OF TOURISM SITE AT BRGY. PALTIC (WHITE BEACH GOING TO MOUNTAIN VIEW) IN DINGALAN, AURORA


CONTRACT NO. 2020-11-100-20DF (INFRA) CONSTRUCTION OF FLOOD CONTROL IN BRGY. SAPANGKAWAYAN, DIPACULAO, AURORA


CONTRACT NO. 2020-11-107-20DF (INFRA) CONSTRUCTION/IMPROVEMENT OF SUGUIT FMR IN BRGY. SUGUIT, MARIA AURORA, AURORA


CONTRACT NO. 2021-02-13-20DF (INFRA) Contract for the Flood Control Project in Brgy. Lual, Casiguran, Aurora


CONTRACT NO. 2020-02-105-20DF (INFRA) Construction of Warehouse with MPDP in Brgy. Ura, Dilasag, Aurora


CONTRACT NO. 2021-03-37-20DF (INFRA) Completion of Multi-purpose Building in Brgy. Dibacong, Casiguran, Aurora


CONTRACT NO. 2021-03-38-20DF (INFRA) Completion of Multi-purpose Building in Brgy. Dibut, San Luis, Aurora


CONTRACT NO. 2021-03-36-20DF (INFRA) Completion of Multi-purpose Building in Brgy. Dimabuno, Dipaculao, Aurora


CONTRACT NO. 2021-03-34-20DF (INFRA) Completion of Multi-purpose Building in Brgy. San Leonardo, Maria Aurora, Aurora


CONTRACT NO. 2021-04-12-20DF (INFRA) Flood Control Project in Brgy. 01, Casiguran, Aurora


CONTRACT NO. 2021-04-18-20DF (INFRA) Completion of Multi-purposed Building in Brgy. Decoliat, Maria Aurora, Aurora


CONTRACT NO. 2021-04-18-20DF (INFRA) Construction of Two-storey Multi-purpose Building in Brgy. Dibaraybay, Dinalungan, Aurora


CONTRACT NO. 2021-04-16-20DF (INFRA) Completion of Multi-purposed Building in Brgy. Dikildit, Maria Aurora, Aurora


CONTRACT NO. 2021-04-17-20DF (INFRA) Completion of Multi-purposed Building in Brgy. Dimaseset, Dilasag, Aurora


CONTRACT NO. 2021-04-21-20DF (INFRA) Completion of Multi-purposed Building in Brgy. Suguit, Maria Aurora, Aurora


CONTRACT NO. 2021-03-15-20DF (INFRA) Completion of Multi-purposed Building in Brgy. Detailen, Maria Aurora, Aurora


CONTRACT NO. 2021-03-20-20DF (INFRA) Completion of Multi-purposed Building in Brgy. Dibutunan, Dipaculao, Aurora


CONTRACT NO. 2021-03-26-20DF (INFRA) Completion of Multi-purposed Building in Brgy. Diome, Maria Aurora, Aurora


CONTRACT NO. 2021-03-27-20DF (INFRA) Completion of Multi-purposed Building in Brgy. Malasin, Maria Aurora, Aurora


CONTRACT NO. 2021-03-22-20DF (INFRA) Completion of Multi-purposed Building in Brgy. Masagana, Dilasag, Aurora


CONTRACT NO. 2021-03-22-20DF (INFRA) Flood Control at Bangco-Pacugao River (Gabion Type), Purok 7, Brgy. Bangco in Maria Aurora, Aurora


CONTRACT NO. 2021-03-24-20DF (INFRA) Completion of Multi-purpose Building in Brgy. Ramada, Maria Aurora, Aurora


CONTRACT NO. 2021-03-23-20DF (INFRA) Construction of Flood Control at Salay Creek (Phase II) in Dipaculao, Aurora


CONTRACT NO. 2021-03-32-20DF (INFRA) Completion of Multi-purpose Bulding in Brgy. Bangco, Maria Aurora, Aurora


CONTRACT NO. 2021-03-30-20DF (INFRA) Construction of Drainage Canal at Brgy. Site Proper in Brgy. Dicabasan, Dilasag, Aurora


CONTRACT NO. 2021-03-31-20DF (INFRA) Completion of Multi-purposed Building in Brgy. Esperanza, Dilasag, Aurora


CONTRACT NO. 2021-03-33-20DF (INFRA) Completion of Multi-purposed Building in Brgy. Galintuja, Maria Aurora, Aurora


CONTRACT NO. 2021-03-29-20DF (INFRA) Construction of Multi-purposed Building in Brgy. Lawang, Dilasag, Aurora


CONTRACT NO. 2021-03-28-20DF (INFRA) Completion of Multi-purposed Building in Brgy. Real, San Luis, Aurora


CONTRACT NO. 2021-03-39-20DF (INFRA) Replacement of Dimalang Bridge (12m) Sta. Ko. 353 + 096 to Ko. 353 + 104.5, Casiguran-Dilasag Provincial Road in Casiguran, Aurora


CONTRACT NO. 2021-03-35-20DF (INFRA) Completion of Multi-Purpose Building in Brgy. Umiray, Dingalan, Aurora


CONTRACT NO. 2021-04-40-20DF (INFRA) Construction of Bridge at Amutan River in Brgy. Butas na Bato, Dingalan, Aurora


CONTRACT NO. 2021-04-45-20GF (INFRA) Completion of Day Care Center II in Brgy. Ditale, Dipaculao, Aurora


CONTRACT NO. 2021-04-41-20DF (INFRA) Reblocking of Road going to Maria Aurora Community Hospital (MACH) in Brgy. 01, Maria Aurora, Aurora


CONTRACT NO. 2021-04-44-20DF (INFRA) Construction/Repair of Tribal Hall in Brgy. Mucdol, Dipaculao, Aurora


CONTRACT NO. 2021-04-46-GF (INFRA) Construction of Multi-purpose Bulding/Additional Repair Bay, Parking Area for H.E., Evacuation Area for Sports Events PEPO in Brgy. Suklayin, Baler, Aurora


CONTRACT NO. 2021-04-42-20DF (INFRA) Establishment of Women in Integrated Development and Empowerment Center (WIDE) in ATC Compound, Brgy. Calabuanan, Baler, Aurora


CONTRACT NO. 2021-05-50-20DF (INFRA) Construction of Multi-purpose Hall Phase II in Brgy. Dibalo, San Luis, Aurora


CONTRACT NO. 2021-05-48-20DF (INFRA) Construction of Flood Control in Brgy. Dimabuno, Dipaculao, Aurora


CONTRACT NO. 2021-05-47-20DF (INFRA) Construction of Multi-purpose Hall in Brgy. Obligacion, Baler, Aurora


CONTRACT NO. 2021-05-49-20DF (INFRA) Construction of Multi-purpose Building in Brgy. Sta. Lucia, Maria Aurora, Aurora



Request for Expression of Interest